PROJECT: TWO STOREY RESIDENTIAL HOUSE AT AMADEO, CAVITE

OWNER: MRS. MYREEN SELOSA AND MR. FREDERICK SELOSA


SUBJECT: PROPOSAL FOR PERMITER FENCE AND GATE

MATERIAL COST LABOR COST


ITEM DESCRIPTION QTY UNIT UNIT COST TOTAL COST UNIT COST TOTAL COST TOTAL AMOUNT NOTES/REMARKS
A STRUCTURAL WORKS
1 Columns
12mm diameter rebar, Grade 33 112.00 pcs 270.00 30,240.00 250.00 28,000.00 58,240.00
10mm diameter rebar, Grade 33 128.00 pcs 150.00 19,200.00 250.00 32,000.00 51,200.00
Concrete, 3000 psi 8.40 cu.m 3,500.00 29,400.00 500.00 4,200.00 33,600.00
Tie Wire 12.00 kgs 100.00 1,200.00 50.00 600.00 1,800.00
Using 1/4" thk
Formworks 1.00 lot 15,000.00 Plywood

Beams (at the top of the existing


2 fence)
12mm
12mm diameter rebar, Grade 33 60.00 pcs 270.00 16,200.00 250.00 15,000.00 31,200.00
10mm diameter rebar, Grade 33 81.00 pcs 150.00 12,150.00 250.00 20,250.00 32,400.00
Concrete, 3000 psi 4.00 cu.m 3,500.00 14,000.00 500.00 2,000.00 16,000.00
Tie Wire 6.00 kgs 100.00 600.00 50.00 300.00 900.00

CHB laying and mortar 10mm diameter


reinforcement spaced @ 600mm
3 bothways
4" CHB 2,835.00 pcs 22.00 62,370.00 11.00 31,185.00 93,555.00
10mm diameter rebar 160.00 pcs 150.00 24,000.00 250.00 40,000.00 64,000.00
Tie Wire 7.50 kgs 100.00 750.00 50.00 375.00 1,125.00
Portland Cement 310.00 pcs 230.00 71,300.00 115.00 35,650.00 106,950.00
Washed Sand 16.00 cu.m 2,000.00 32,000.00 1,000.00 16,000.00 48,000.00

4 Construction of Gates and Railing


100mm x 50mm x 2mm thk Tubular B.I 6.00 pcs 1,500.00 9,000.00 800.00 4,800.00 13,800.00
50mm x 50mm x 2mm thk Tubular B.I 13.00 pcs 1,000.00 13,000.00 800.00 10,400.00 23,400.00
Spray Paint Finish 1.00 lot 15,000.00 15,000.00 10,000.00 10,000.00 25,000.00
Mechanisms for Gates 1.00 lot 15,000.00

Subtotal 631,170.00

Note: TOTAL AMOUNT 631,170.00


Existing Footing and Wall Footing to be Re-used Overhead, Contingency, Profit, Misc. 31,558.50
New CHB Fence will be installated in existing (approximately 1.5m ht.) GRANDTOTAL 662,728.50