You are on page 1of 3

BILL OF MATERIALS

PROJECT: PROPOSED COTTAGE


LOCATION:
OWNER: JOSHUA S. UNABIA

Description Quantity Unit Cost Amount

I. FOOTING AND COLUMN

Cement 12 bags 260.00 3,120.00


Sand 3 cu.m. 980.00 2,940.00
Gravel 3 cu.m. 1,200.00 3,600.00
12 mmØ Def. Bars 15 pcs. 320.00 3,600.00
10 mmØ Def. Bars 20 pcs. 320.00 5,760.00
#16 G.I Tie Wires 5 kls. 96.00 480.00
4” x 4” x 10’ 6 pcs 480.00 2,880.00
Good Lumber
TOTAL= ₱ 24, 080.00

II. CARPENTRY WORKS:


2”X4”X12’ Good Lumber 48 pcs 240.00 11,520.00
2”X6”X12’ Good Lumber 8 pcs 360.00 2,880.00
2”x3”x12’ Good Lumber 36 pcs 180.00 6,480.00
6mm THK, Hardiflex Board 18 pcs 450.00 6,480.00
¾ “ THK. Marine Plywood 5 shts 1,300.00 6,500.00
(Flooring)
Pre-Painted Corrugated 16 shts 560.00 8,960.00
G.I Shts. X 10’
Ridge Roll X 2.40 3 pcs 310.00 930.00
Assorted Size Nails 12 kls. 85.00 1,020.00
Bamboo Slats x 8’ FT. 20 bls. 300.00 6,000.00

TOTAL: ₱ 52, 390.00


III. DOORS & WINDOWS

Paneled Door 2.10 x .80 1 pc 4,500.00 4,500.00


PVC Type Door 2.10 x .60 1 pc 2,400.00 2,400.00
French Type Window 4 sets 3,200.00 12,800.00
1.20 x1.20
French Type Window .60x.60 1 set 800.00 800.00
Door Knob 2 pairs 750.00 750.00
Door Hinges 2 sets 200.00 400.00
2” x 2” x 10’ Good Lumber 46 pcs 120.00 5,520.00
4.5 mm THK. Hardiflex 11 shts. 397.00 4,367.00
Board
Assorted Size Nails 5 kls. 85.00 425.00

TOTAL: ₱10,312.00

IV. CEILING WORKS

2” X2” X10’ Good Lumber 46 pcs 120.00 5,520.00


IV.5 mm THK. Hardiflex 11 shts 397.00 4,367.00
Board
Assorted Size Nails 5 kls 85.00 425.00

TOTAL: ₱10,312.00

V. ELECTRICAL WORKS

Panel Board 30 amp 1 set 1,500.00 1,500.00


20 mmØ x 10’ RSC. Pipe 1 pc 900.00 900.00
# 8.0 mm2 cu. TW. Wire 20 mts. 125.00 2,500.00
#3.5 mm2 cu. TW. Wire 1 box 3,400.00 3,400.00
#2.0 mm2 cu.TW. Wire 1 box 3,200.00 3,200.00
20 mmØ PVC. Flexible 1 roll 840.00 840.00
Hose
Utility Box 8 pcs 40.00 320.00
Junction Box 3 pcs 50.00 150.00
Led Bulb 9 watts 5 pcs 180.00 900.00
Conv. Outlet (2-Gang) 3 pcs 240.00 720.00
Switch Outlet 3 pcs 195.00 585.00

TOTAL: ₱ 15,015.00

VI. PLUMBING WORKS

Water Closet 1 set 3,600.00 3,600.00


Lavatory 1 set 900.00 900.00
Kitchen Sink 1 set 1,800.00 1,800.00
4” Ø x10’ PVC Pipe 2 pcs 600.00 1,200.00
2” Ø x10’ PVC Pipe 3 pcs 290.00 870.00
3” Ø x10’ PVC Pipe 3 pcs 365.00 1,095.00
Floor Drain 1 pc 125.00 125.00
½ “ Ø x 20’ G.I Pipe 4 lgths. 640.00 2,560.00
Plumbing Fittings L.S 3,500.00
Solving Cement 1 can 80.00 80.00
Teflon Tape 2 pcs 35.00 70.00
Faucet 2 pcs 275.00 550.00

TOTAL: ₱ 16,350.00

VII. PAINTING WORKS

Lump Sum Meters Only 8,500.00

TOTAL MATERIALS COST: ₱149,047.00


LABOR COST 40% 59,618.80
TOTAL COST: ₱ 208.665.80

PREPARED BY: APPROVED BY:

______________________ ________________________
CIVIL ENGINEER OWNER