Project : PROPOSED TWO STOREY BUILDING - Roofing Works

Location: Kalye Kawayan, Malangas Zamboanga Sibugay


Owner : Ms. Apple Cortez

SUBJECT: BILL OF MATERIALS AND COST ESTIMATES

MATERIALS/ITEM QNTY. UNIT COST AMOUNT


I. MOBILIZATION: Staking & Layout, 5,000.00
Temp. Connections Elect'l & Water
III.CONCRETE WORKS:
B. Column- Above 2nd Floor : (Class A Mix)
Portland Cement 16 bags 285.00 4,560.00
River Sand 1 cu.m. 800.00 800.00
3/4 Gravel 1.5 cu.m. 1200.00 1,800.00
16mm rebars 27 pcs. 640.00 17,280.00
10mmÆ rebars 30 pcs. 245.00 7,350.00
#16 tie wire 5 kls. 75.00 375.00
P 32,165.00
E.2nd FLOOR ROOF BEAM:
Portland Cement 19 bags 285.00 5,415.00
River Sand 1.15 cu.m. 700.00 805.00
3/4 Gravel 1.71 cu.m. 800.00 1,368.00
12mm rebars 38 pcs. 275.00 10,450.00
10mm rebars 40 pcs. 245.00 9,800.00
#16 tie wire 10 kls. 75.00 750.00
P 28,588.00
IV. FORMWORKS AND SCAFFOLDINGS
A.Column
Bamboo Scaffolds 20 pcs. 85.00 1,700.00
2X2X12 coco lumber 30 pcs. 80.00 2,400.00
1/4 ordinary plywood 15 pcs. 485.00 7,275.00
Assorted CW Nail 10 kls. 80.00 800.00
P 12,175.00
V. Roof Works (0.4mm thk. Prepainted Coloroof)

2" x 4" x 12' Good Lumber 240 bd.ft 40.00 9,600.00


2" x 3" x 12' Good Lumber 360 bd.ft 40.00 14,400.00
1" x 10" x 12' Good Lumber 100 bd.ft 40.00 4,000.00
Assorted Nails 15 kg. 80.00 1,200.00
0.4mm thk. Prepainted Roofing 60 sq.m 800.00 48,000.00
0.4mm thk. Prepainted Gutter 32 m 450.00 14,400.00
0.4mm thk. Prepainted Ridge roll 39 m 330.00 12,870.00
0.4mm Thk. Prepainted Fascia cover 32 m 330.00 10,560.00
2-1/2 Wooden Tex Screw 2000 pcs 3.00 6,000.00
Vulcaseal 1 li. 350.00 350.00

P 121,380.00

X. TOTAL MATERIAL COST P 199,308.00


XI. LABOR P 71,654.20
XII. CONTINGENCIES,OVERHEAD & EQUIPMENT
RENTAL,CLEARING P 13,548.11
PROFESSIONAL FEES

XIII. TOTAL CONSTRUCTION COST P 284,510.31