Professional Documents
Culture Documents
Materials:
FIXTURES AND APPURTENANCES
Water Closet, Lever-type with complete tank fittings, 1.00 set 8,000.00 8,000.00
angle
1/2"Øvalve, andHose
Flexible 0.00
Stainless Counter Sink 0.50m x 0.80m with Sink 2.00 sets 3,500.00 7,000.00
Stainless-Chrome Faucet 1.00 pcs 550.00 550.00
Stainless Floor Drain 4"x 4" with Strainer (for CR) 2.00 pc 450.00 900.00
Soap and Tissue Holders 1.00 set 480.00 480.00
CLEAN WATER PIPELINE 0.00
PE Pipe 1/2"Ø, sched. 40 80.00 mtrs 18.00 1,440.00
PVC Elbow 1/2"Ø x 90 ⁰ 5.00 pcs 85.00 425.00
PVC Tee 1/2"Ø x 1/2" 5.00 pcs 75.00 375.00
PVC Coupling 1/2"Ø 5.00 pcs 75.00 375.00
End Plug 1/2"Ø 5.00 pcs 30.00 150.00
US PP Gate Valve 1/2"Ø 3.00 pc 450.00 1,350.00
WASTEWATER PIPELINE AND VENT-THRU-ROOF 0.00
PVC Pipe S-1000 4"Ø x 10' 10.00 pcs 750.00 7,500.00
PVC Pipe S-1000 2"Ø x 10' 8.00 pcs 650.00 5,200.00
PVC Wye 4"Ø x 4"Ø 9.00 pcs 95.00 855.00
PVC Wye 2"Ø x 2"Ø 10.00 pc 85.00 850.00
PVC Reducer 4"Ø x 2"Ø 10.00 pc 85.00 850.00
PVC Bend 4"Ø x 90° 4.00 pcs 84.00 336.00
PVC Bend 2"Ø x 90° 10.00 pcs 62.00 620.00
PVC P-Trap 4"Ø 8.00 pcs 95.00 760.00
PVC P-Trap 2"Ø 8.00 pcs 95.00 760.00
PVC Clean-Out 4"Ø w/ Cover 5.00 pcs 72.00 360.00
SEPTIC TANK 0.00
PVC Pipe S-1000 4"Ø x 10' 2.00 lgth 750.00 1,500.00
PVC Tee 4"Ø x 4"Ø 6.00 pcs 95.00 570.00
PVC Clean-Out 4"Ø w/ Cover 1.00 pcs 72.00 72.00
Material Cost 41,278.00
Labor Cost 16,511.20
Total Cost 57,789.20
XII PAINTING WORKS
Scope of Work:
1. Painting of all masonry exposed surfaces (except for
2. Application of top coat paints (at least 2 coats) on
NO Apply putty evenly throughout walls. Apply two (2) topcoat
TE: coatings to even the application on all surfaces.
Materials:
MASONRY SURFACE - application on perimeter walls and
partitions, window
Concrete mouldings, and ceiling
Neutralizer 2.00 gal 450.00 900.00
Premium Acrylic Latex Primer 2.00 tins 2,800.00 5,600.00
Premium Acrylic Latex Gloss 2.00 tins 3,150.00 6,300.00
Power Putty (applied evenly throughout walls and 3.00 gals 453.00 1,359.00
OTHER MISCELLANEOUS ITEMS 0.00
Tinting Color Latex 2.00 pints 85.00 170.00
Tinting Color (Oil) 2.00 pints 95.00 190.00
Sand Paper #120 20.00 pcs 15.00 300.00
Paint Roller w/ Tray 10.00 sets 150.00 1,500.00
Paint Brush 10.00 pcs 30.00 300.00
Material Cost 16,619.00
Labor Cost 6,647.60
Total Cost 23,266.60
PROJECT TITLE: PROPOSED CONSTRUCTION OF 2- STOREY MULTI- PURPOSE BLDG.
SUMMARY OF COST ESTIMATE
PROPOSED CONSTRUCTION OF 2- STOREY MULTI- PURPOSE BLDG.
ITE MATERIAL LABOR
ITEM DESCRIPTION TOTAL
M COST COST
I SITE WORKS 17,530.00 33,899.50 51,429.50
II EMBANKMENT WORKS 22,500.00 9,000.00 31,500.00
III REINFORCED CONCRETE WORKS 567,930.00 227,172.00 795,102.00
IV STEEL TRUSS, ROOF FRAMING & 237,210.00 94,884.00 332,094.00
ROOFING WORKS
V MASONRY WORKS 78,154.00 31,261.60 109,415.60
VI CARPENTRY WORKS 126,475.00 50,590.00 177,065.00
VII DOORS AND WINDOWS 9,000.00 9,000.00
VIII TILE WORKS 45,275.00 18,110.00 63,385.00
IX SEPTIC TANK 19,751.00 7,900.40 27,651.40
X ELECTRICAL WORKS 74,744.00 29,897.60 104,641.60
XI PLUMBING WORKS 41,278.00 16,511.20 57,789.20
XII PAINTING WORKS 16,619.00 6,647.60 23,266.60
1,782,339.90
TOTAL PROJECT COST 1,256,466.00 525,873.90 1,782,339.90
Project
PROPOSED CONSTRUCTION OF 2- STOREY MULTI- PURPOSE BLDG.
Title:
BOQ
IT UNIT
ITEM DESCRIPTION QTY UNIT AMOUNT
E PRICE
I. SITE WORKS
Scope of Work:
1. Includes clearing, layout, and excavation
a. Wall Footings 4.80 cu.m
b. Column Footings 41.00 cu.m
c. Septic Tank 13.95 cu.m
Labor:
Excavation works 59.75 cu.m 450.00 26,887.50
Materials:
Assorted Form Lumber 800.00 bd.ft 21.00 16,800.00
Assorted CW Nails 6.00 kgs 80.00 480.00
Nylon Chord 5.00 rolls 50.00 250.00
Material Cost 17,530.00
Labor Cost 33,899.50
Total Cost 51,429.50
II. EMBANKMENT WORKS
Scope of Work:
1. Embankment for buildable areas
2. Backfilling Works
Materials:
Filling Materials - to elevate the buildable area by 0.20m 90.00 cu.m 250.00 22,500.00
Material Cost 22,500.00
Labor Cost 9,000.00
Total Cost 31,500.00
III. REINFORCED CONCRETE WORKS
Scope of Work:
1. Construction of reinforced concrete works system with deformed bars
and specification, includes the following:
a. Column Footings
b. Column
C. Floor Slab on grade
Slab thickness shall be 0.15m with temperature bars spaced 0.40m
bothways on top of gravel bed throughout.
d.Roof beam
e. Lavatory Counter
f. Lintel beam
Materials:
Portland Cement 120.00 cu.m 950.00 114,000.00
Sand 48.00 cu.m 950.00 45,600.00
Gravel 62.00 cu.m 950.00 58,900.00
GI Tie Wire #16 50.00 kgs 67.00 3,350.00
Deformed Bar 10mmØ x 6m 720.00 lgths 147.00 105,840.00
Deformed Bar 12mmØ x 6m 320.00 lgths 212.00 67,840.00
Deformed Bar 16mmØ x 6m 380.00 lgths 355.00 134,900.00
14" Cut- Off Blade 50.00 pcs 750.00 37,500.00
Material Cost 567,930.00
Labor Cost 227,172.00
Total Cost 795,102.00
IV. STEEL TRUSS, ROOF FRAMING & ROOFING
Materials:
2" x 2" x 6mm THK. Angle Bar 20.00 pcs 1300.00 26,000.00
1-1/2" x 1-1/2" x 6mm THK. Angle Bar 15.00 pcs 950.00 14,250.00
2" x 4" x 1.50mm THK. C- Purlin 40.00 pcs 450.00 18,000.00
2" x 6" x 1.50mm THK. C- Purlin 8.00 pcs 550.00 4,400.00
10mm Round Bar 25.00 pcs 180.00 4,500.00
Welding Rod Special 30.00 kgs 190.00 5,700.00
Epoxy Primer- Gray 4.00 gals 750.00 3,000.00
Lacquer Thinner 10.00 bottles 450.00 4,500.00
Baby Roller 10.00 pcs 65.00 650.00
2" Paint Brush 8.00 pcs 45.00 360.00
3" Paint Brush 10.00 pcs 55.00 550.00
2" x 2" x 1.50mm THK. Tubular, B.I 25.00 pcs 750.00 18,750.00
1-1/2" x 1-1/2" x 1.50mm THK. Tubular, BI 50.00 pcs 600.00 30,000.00
Welding Rod Special 15.00 kgs 190.00 2,850.00
Grinding Disc for Metal 30.00 pcs 250.00 7,500.00
Materials:
Materials:
DOORS
D1 - (0.70m x 2.10m) PVC Door With Fix Louver (with 2.00 sets 2,400.00 4,800.00
WINDOWS
W2 -Sliding Window with powder coated frame 2.00 sets 2,100.00 4,200.00
(0.60 x 0.60m)
Material Cost 9,000.00
Total Cost 9,000.00
VIII. TILE WORKS
Scope of Work:
1. Tiling of Comfort Room
2. Tiling of Lavatory Counters
3. Tiling of 2nd Floor
Materials:
Unglazed Ceramic Tiles 400mm x 400mm (for CR 25.00 pcs 125.00 3,125.00
Glazed Ceramic Tiles 0.30 x 0.60 (for CR Wall and 60.00 pcs 55.00 3,300.00
Granite Tile 60cm x 60cm 150.00 pcs 150.00 22,500.00
Portland Cement 8.00 cu.m 950.00 7,600.00
Fine Sand 3.00 cu.m 1,100.00 3,300.00
Tile Grout (2 kgs) 5.00 packs 40.00 200.00
Tile Adhesive (25 kgs) 20.00 bag 250.00 5,000.00
PVC Tile Trim 9mm x 8' 10.00 lghts 25.00 250.00
Material Cost 45,275.00
Labor Cost 18,110.00
Total Cost 63,385.00
IX SEPTIC TANK
Scope of Work:
1. Construction of Septic Tank 1.70m wide x 3.10m
long
Bothx floors
2.00mofdeep.
Digestive Chamber and Leaching Well shall be cemented,
Provide air space by securing the water table to be
NOT Cement for plastering of interior walls shall be mixed with adequate water-
E: Concrete Covers shall be reinforced with rebars spaced
0.20m, with
Location andmanhole on each
Positioning chamber
of septic tank must be according to
depending on actual site conditions, must be as
instructed by the Inspectorate Engineer
Materials:
Portland Cement 12.00 cu.m 950.00 11,400.00
Sand 2.50 cu.m 900.00 2,250.00
Gravel 2.00 cu.m 900.00 1,800.00
GI Tie Wire #16 4.00 kgs 58.00 232.00
Deformed Bar 10mmØ x 6m 10.00 pcs 147.00 1,470.00
Deformed Bar 12mmØ x 6m 12.00 pcs 212.00 2,544.00
Hacksaw Blade 1.00 pc 55.00 55.00
Material Cost 19,751.00
Labor Cost 7,900.40
Total Cost 27,651.40
X ELECTRICAL WORKS
Scope of Work:
1. Supply and Installation of electrical conduits, wires
2. Supply and Installation of lighting fixtures and switches
3. Supply and Installation of conv.outlets and panel
board
Materials:
WIRES AND CONDUCTORS
3.5 sq.mm THHN Cu. Wire (Stranded), color black 3.00 box/15 4,200.00 12,600.00
2.0 sq. mm THHN Cu. Wire (Stranded), color black 0 m 2,900.00 5,800.00
2.00 box/15
2.0 sq. mm THHN Cu. Wire (Stranded), color green 0 m 2,900.00 5,800.00
2.00 box/15
PANEL BOARD AND DISCONNECTING SWITCH 0m 0.00
Center Main Panel Board (bolt on type) 0.00
Main : 60AT, 40AF, 240V, 2P, 14 KAIC 1.00 assy 8,620.00 8,620.00