Professional Documents
Culture Documents
I. EXCAVATION WORKS
excavation works
hauling 10,000.00
equipment 7,400.00
base course 450 6,750.00
II. CONCRETING WORKS
cement bags 205 10.25 127,428.00
gravel cu.m 450 22.5 39,217.50
sand cu.m 450 22.5 51,502.50
III. REINFORCEMENT WORKS
10mm pcs 110 5.5 85,470.00
G.i wire roll 1600 80 8,400.00
868,953.13
300,000.00
1,168,953.13
116,895.31
1,285,848
material cost
labor
total construction cost
contractors profit (10%)
total project cost
multiplyier( 9 bags /cu.m)
concrete works
lower footing 2x
22.56 0.2 0.3 2.7072 24.3648 2.631398
pavement 10 0.4 25
4.5 0.4 11.25
4.4 0.4 11
7 0.4 17.5
6 0.4 15
25
25
nosing 25 5.4 4.62963 3 13.88889 2
traverse 25 0.3 83.33333 20
wall reinf 25 0.6 41.66667 4 10.41667
22 0.6
area
tile work pool 51 100 0.09
wall 32
6
11
paver 40 66 0.36
26
washout 30 700
setting
er( 9 bags /cu.m) multiplier chb laying (20 pcs/cement) 20
gravel
5.067
8.6
18.5895
11.11361
0.849285
2.6487
5.14188
1.2393
3.70332
2.52234
0.69984
4.528305
1.95858
2.93787
0.88452
CHB 10MM
343.2 2.02 118.8 237.6 6 39.6
760
1103.2
0.788778
0.323676
3.289248
chb
168.792
69.264
351 175.5
85.8
85.8
74.88575 46170.92
760.656
10mm
13.6 5.4 3 150
9.6 5.4 2 60
30.4 5.4 6 54
54
75.5
20
25
25
11.25
11
17.5
15
6
27.77778
4.166667
4.16
4.16
27
27
10
22
tiles 24
674.5144 110 74196.59
1111.111
183.3333
matl
21000
PROJECT TITLE: PROPOSED SWIMMING POOL
LOCATION: Sun Valley Subd.
OWNER: Alma Ritvonen
MATL MATL
DESCRIPTION UNIT QTY UNIT COST MARK UP 5%
I. EXCAVATION WORKS
excavation works cu.m
hauling
equipment
base course 15 450
II. CONCRETING WORKS
cement bags 592 205 10.25
gravel cu.m 83 400 20
sand cu.m 109 450 22.5
III. REINFORCEMENT WORKS
10mm pcs 740 110 5.5
G.i wire roll 5 1600 80
6,750.00
127,428.00
34,860.00
51,502.50
85,470.00
8,400.00
19,320.00
4,252.50
27,300.00
1,575.00
1,575.00
1,050.00
1,050.00
525.00
525.00
525.00
19,782.00
14,931.00
15,120.00
11,088.00
26,460.00
128,205.00
17,640.00
9,862.13
2,310.00
1,575.00
2,520.00
1,050.00
525.00
2,520.00
252.00
47,250.00
35,700.00
26,250.00
11,340.00
5,040.00
7,350.00
10,500.00
5,880.00
6,825.00
15,750.00
6,300.00
8,400.00
1,260.00
4,725.00
6,142.50
7,350.00
8,400.00
6,300.00
2,100.00
1,680.00
850,490.63 material cost
300,000.00 labor
1,150,490.63 total construction cost
115,049.06 contractors profit (10%)
1,265,540 total project cost