Project: PROPOSED BEACH RESORT

Location: Daanlungsod Alcoy, Cebu


Subject: REMAINING WORK SCHEDULE
Date: October 10, 2022

Duration
Start Date
RETAINING WALL/PERIMETER WALL
CIVIL/SITE WORKS
Earthworks
-Footing Excavation Oct. 10
-Grade beam excavation Oct. 10
-Gravel bedding Oct. 12
-Base Compaction Oct. 12
STEEL REINFORCEMENTS
-Footing Rebar Installation Oct. 12
-Column Rebar Installation Oct. 12
-Wall Rebar Installation Oct. 10
-Grade beam Rebar Installation Oct. 10
CONCRETE WORKS
-Footing Oct. 13
-Column Oct. 17
-Wall Oct. 12
-Grade beam Oct. 12
MASONRY WORKS
-CHB Piling and Plastering Oct. 24
FORMWORKS & SCAFFOLDING INSTALLATION
Formworks and Scaffolding
-Footing Oct. 13
-Column Oct. 17
-Wall Oct. 12
-Grade beam Oct. 12
FORMWORKS & SCAFFOLDING REMOVAL
-Footing siding Oct. 15
-Column siding Oct. 20
-Wall siding Oct. 15
-Grade beam siding Oct. 14

RAMP
CIVIL/SITE WORKS
Earthworks
-Embankment Oct. 17
-Gravel bedding Oct. 17
-Base Compaction Oct. 17
STEEL REINFORCEMENTS
-Slab on grade Rebar Installation Oct. 10
-Suspended slab Rebar Installation
CONCRETE WORKS
-Slab on grade Oct. 14
-Suspended slab
FORMWORKS & SCAFFOLDING INSTALLATION
Formworks
-Slab on grade
-Suspended slab
Scaffolding
-Suspended slab
FORMWORKS & SCAFFOLDING REMOVAL
-Suspended slab Nov. 7

RESTO
STEEL WORKS
Steel Roof Framing
-Full Truss Oct. 10
-Half Truss Oct. 10
-C-purlins Oct. 14
-Sag rod Installation Oct. 17
ROOF WORKS
Under sheeting
-Phenolic board Installation Oct. 24
Roof Installation
-Roofing Felt Installation Oct. 25
-Asphalt Shingles Installation Oct. 27
MASONRY WORKS
Ground Floor
-Chb wall piling
-Plastering Oct. 10
-Second Floor Wall Partition
-Chb wall piling Oct. 20
-Plastering Oct. 24

DIVE SHOP
STEEL WORKS
Steel Roof Framing
-Full Truss Oct. 24
-Half Truss Oct. 27
-C-purlins Nov. 3
-Sag rod Installation Nov. 5
ROOF WORKS
Under
-Phenolic board Installation Nov. 7
Roof Installation
-Roofing Felt Installation Nov. 10
-Asphalt Shingles Installation Nov. 12
MASONRY WORKS
-Chb wall piling
-Plastering Oct. 17

HOTEL
WALL PARTITIONS
-Ground Floor Oct. 17
-Second Floor Oct. 27
-Third Floor Nov. 28
STEEL REINFORCEMENTS
-Column Rebar Installation Oct. 10
-Roof beam Rebar Installation Oct. 24
CONCRETE WORKS
-Column Oct. 17
-Roof beam Oct. 30
-Slab on grade Oct. 12
STEEL WORKS
Bolts & Nuts
-Bolt and Nut Installation
Roof Truss
-Full Truss Nov. 7
-Half Truss Nov. 16
-C-purlins Nov. 28
-Sag rod Installation Dec. 2
ROOF WORKS
Under
-Phenolic board Installation Dec. 5
Roof Installation
-Roofing Felt Installation Dec. 8
-Asphalt Shingles Installation Dec. 8
FORMWORKS & SCAFFOLDING INSTALLATION
Formworks and Scaffolding
-Column Oct. 13
-Roof beam Oct. 24
FORMWORKS & SCAFFOLDING REMOVAL
-Column Oct. 20
-Roof beam Nov. 16

PREPARED BY: GAIN F. LEGARDE


CONFORME:
OWNER
LEGEND
START/ DAY 1
WORK DONE
WORKING DAYS
TO BE DETERMINE
HOLIDAY/ NO WORK

OCTOBER
Duration WEEK 1 WEEK 2
End Date Days 10 11 12 13 14 15 16 17 18 19 20 21 22

Oct. 29 12
Oct. 29 15
Oct. 29 13
Oct. 29 13

Oct. 24 11
Nov. 12 26
Oct. 22 12
Oct. 24 13

Oct. 24 11
Nov. 14 26
Oct. 22 10
Oct. 25 12

Nov. 26 28

Oct. 24 11
Nov. 14 26
Oct. 22 10
Oct. 25 12
Oct. 25 9
Nov. 15 21
Oct. 25 9
Oct. 26 11

Nov. 12 22
Nov. 12 22
Nov. 12 22

Nov. 12 28

Nov. 19 30

Nov. 8 2

Oct. 17 7
Oct. 17 7
Oct. 19 5
Oct. 19 3

Oct. 26 3
Oct. 29 5
Nov. 5 7

Oct. 22 14

Oct. 22 3
Oct. 26 3

Nov. 5 10
Nov. 5 7
Nov. 5 3
Nov. 7 2

Nov. 9 3

Nov. 12 3
Nov. 19 7

Oct. 22 6

Nov. 12 22
Nov. 26 25
Dec. 21 21

Oct. 22 12
Nov. 12 16

Oct. 29 12
Nov. 20 16
Oct. 20 8

Dec. 8 27
Dec. 8 17
Dec. 8 9
Dec. 8 6

Dec. 17 12

Dec. 21 12
Dec. 21 12

Oct. 26 12
Nov. 24 25

Oct. 27 9
Nov. 26 10

ARCHT. MARK PHILLIP F. MONTEROS


OPERATIONS MANAGER (FIELD)
ARCHT. JONATHAN DAVE R. CHUA
OPERATIONS MANAGER (OFFICE)
RT/ DAY 1
K DONE
KING DAYS
E DETERMINE
DAY/ NO WORK

BER
2 WEEK 3 WEEK 4 WEEK 5
23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
NOVEMBER
WEEK 5
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
DECEMBER

26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12
EMBER

13 14 15 16 17 18 19 20 21