Work Plan : Project Start Date

Project Start 15-Sep-20

Dashti Khan Debris and Flood Flow 15-Sep-20 22-Sep-20 29-Sep-20 6-Oct-20 13-Oct-20 20-Oct-20 27-Oct-20 3-Nov-20

Nooshakh Pamir Construction company 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
S.No. Task Start End

Site Preparation and Moblization

Moblization and Demoblization 15-Sep-20 20-Sep-20

Site Preparation 20-Sep-20 21-Sep-20

Soil excavation

Channel excavation and cleaning


21-Sep-20 7-Nov-20

Project handover and Complation


7-Nov-20 7-Nov-20