DATE: 22nd January 2021 at 12:00 IST
VENUE: Google Hangouts Conference Call
REQUIRED ATTENDEES
2 External Plastering Manpower to be deployed for external plastering works in Hemasri Dates Mentioned
East & West side by 20th July -20/ 10th Aug 20 / 22nd Aug 20 /
29-Aug-20 / 10-Sep-20 / 15-Sep-20 / 22-Sep-20 / 01-Oct-20 /
13-Oct-20 / 23-Oct-20 / 30-Oct-20 /06-Nov-20/12-Nov-20 / 19-
Nov-20 / 26-Nov-20 / 31-Dec-20 / 15-Jan-21/26-Jan-21.
3 Fire door jamb Hemasri to complete the fire door jambs rectification to 12-Nov-20
rectifications handover Workfront to Fire door team. Hemasri 19-Nov-20
28-Nov-20
11-Dec-20
22-Dec-20
26-Dec-20
10-Jan-21
4 Southside RWP Discussion on Southside RWP shaft Blockwork & Plaster. Hemasri To be discussed
shafts Blockwork Clearance given on 5th November 2020 works to be completed.
5 PHE shaft blockwork PHE Shaft blockwork to be completed from Ground floor to till Hemasri To be discussed
8th floor.
6 Handing over Final Bill closure and Handing Over Documents for closeout to Hemasri To be discussed
Document formats be submit.
for Project Close-out
Payment
Date of Date of No. of Days Certificate
Claimed Certified
Receipt of Type of Bill certification taken for forwarded to Approval Status
Amount(A) Amount(B)
Invoice by KF by KF Certification client for
approval
WMOB30047 RA 01 - Final 331811.90 331811.90 17-Oct-20 0 17-Oct-20 Amount Released
Amount to be
WMOB30065 RA 01 1,89,000.00 1,89,000.00 23-Dec-20 0 23-Dec-20
released