Site clearance, mobilazation, demobilization, setting


1 alingment and levelling to start the works and leaving the 1.00 L.S. Three thousand and seventy-eight dollars
site clean after completion all complete.
3078.00 3078
Earthwork in excavation in foundation in all kind of soil,
ramming the bottom, stacking the excavated materials at
2 1482.69 Cum. Four point nine two dollars
least 3m. clear from the edge of the excavation all
complete. 4.92 7301.95

Providing and filling with soil in 150mm. layers, watering and


3 1061.03 Cum. Four point foure two dollars
ramming all complete.
4.42 4694.36
Exploding rock and cleaning debris from the site all
4 54.00 Cum. Sixteen point Zero one dollars
complete. 16.01 864.30
5 Dewatering works all complete. 1.00 L.S. One thousand eight hundred and twenty-four dollars 1824.00 1824.00

6 River diversion works all complete. 1.00 L.S. One thousand and six hundred point five six dollars
1600.56 1600.56

Providing and soling boulder stone (Stone pitching)


7 70.10 Cum. Twenty point six nine dollars
including filling the voids with sand all complete.
20.69 1450.43

Providing and laying plain cement concrete 1:3:6 on base of


foundation including centering & shuttering work where
8 33.23 Cum. Eighty-four point five dollars
necessary, in perfect line & level with proper compaction,
curing all complete. 84.5 2809.54

1
Sl. Description of work Quantity Unit Rate Amount
No. In Words In Figure (USD)

Providing and laying plain cement concrete 1:2:4 (M15)


including centering & shuttering work where necessary, in
9 19.30 Cum. One hundred six point two four dollars
perfect line & level with proper compaction, curing all
complete.
106.24 2049.96

Providing and laying reinforced cement concrete 1:1.5:3


(M20) in Kerb, Approach slabs, bearing stopper etc. in
10 perfect line & level with proper compaction using vibrator 66.90 Cum. One hundred and thirty point one five dollars
and curing all complete excluding cost of the centering &
shuttering and the reinforcement.
130.15 8707.83

Providing and laying reinforced cement concrete 1:1:2


(M25) in Girder base & backwall, Girders, beams, slabs,
diaphragm, Abutment etc. in perfect line & level with proper
compaction using vibrator and curing all complete excluding
11 214.22 Cum. One hundred and sixty-two point two eight dollars
cost of the centering & shuttering and the reinforcement.
Weepholes (75mm. Pipe) at 2.0 meter intevals (in staggered
position) vertically and horizontally in the Abutments should
be provided.
162.28 34763.65

Supplying and fixing reinforcement steel (Fe 415) with


12 bending, placing in position and binding with GI wire 35.19 Ton. One thousand one hundred and sixty dollars
including cost of the binding wire all complete.
1160.01 40825.20

Providing and fixing centering & shuttering of


steel/plywood/wood including strutting, propping etc. for
13 287.13 Sqm. Eleven point nine six dollars
RCC works in Abutment,Girder base, Backwall, Bearing
stopper etc. and removal of shuttering all complete
11.96 3433.67

Providing and fixing centering & shuttering of


steel/plywood/wood including strutting, propping etc. for
14 274.48 Sqm. Seventeen point nine nine dollars
RCC works in girder, beams, slab etc. and removal of
shuttering all complete.
17.99 4937.68

2
Sl. Description of work Quantity Unit Rate Amount
No. In Words In Figure (USD)

Providing and fixing MS angle iron and MS plate in


15 expansion/construction joint in perfect line and level all 20.00 Rm. Twenty-five dollars
complete.
25.00 500.00

Providing and laying Stone masonry Wing walls, Retaining


walls in 1:4 cement mortar in perfect line & level and curing
16 including placement of weepholes (75mm. Pipe) at 2 meter 1217.01 Cum. Fifty-five point five four dollars
intevals (in staggered position) vertically and horizontally all
complete.
55.54 67593.67

Cement sand pointing (1:3 ) on stone masonry work on


17 exposed surface including racking the joints, wetting the 414.22 Sqm. Three point zero four dollars
surface and curing all complete.
3.04 1261.26
Providing and fixing elastrometric bearing (50 x 25 x 5.5cm)
with steel plates at base of girders including 2.5cm thick
18 4.00 Sets. Three hundred and eighty point zero three dollars
bearing plinth (1:2 cement mortar) in perfect line and level
all complete. 380.03 1520.12

Providing and fixing rain water drainage pipe 75mm


19 12.00 Nos. Seven point Zero one dollars
diameter including floor trap all complete.
7.01 84.13

Providing and fixing Hand rail of I-beam and 3" GI pipe all
20 37.40 Rm. Fifty-eigth point four six dollars
complete. 58.46 2186.52
Two coats of approved colour oil paint with one coat of
21 49.37 Sqm. Four point four six dollars
primer on handrail all complete. 4.46 220.17
Providing and filling with coarse aggregate sub-base,
22 25.00 Cum. Twelve dollars
watering and ramming under approach slab all complete. 12.00 300.11
Providing and laying dry stone wall for protection of River
23 338.24 Cum. Nine point three eight dollars
side as per drawing all complete. 9.38 3171.51
Providing and fixing Regulating Metallic gate having the
size 0.5m width and 1.05m height (including handle wheel,
bearing plates, C channels, Spindles etc. as per drawing)
24 1.00 No. Two hundred and thirty dollars
including RCC support structure both sides with breast wall ,
application of one coat red oxide and two coat oil paint as
per drawing all complete . 230.00 230.00

Providing and fixing 3 inch dia GI pipe (heavyduty) for


25 crossing existing water supply with all necessary 20.00 M Ten point zero three dollars
accessories material all complate.
10.03 200.64
Providing and fixing PE pipe th:250mm dia for canal all
26 7.00 M Fifty-six dollars
complete. 56.00 391.98

Total Project Cost (USD) 196001.23

3
‫شرکت ساختمانی و سرک سازی نوشاخ پامیر‬
Rate Analysis For Bridge
Province : Badakhshan
District :Mai-Mai Darwaz Balla
Village Name:Rawand

No Title
Site clearance, mobilazation, demobilization, setting alingment and levelling to start the works and leaving the site
clean after completion all complete.
Name of activity Qty Unite Rate Amount
1 Prepration of site Project 1 LS 600.00 600
Setting of alingment 1 LS 500.00 500
Moblization 1 LS 900.00 900
Cleaning of Project site 1 LS 700.00 700

Total amount without Campany Profit and Tax Contract 2700


Total amount Including (10%) Campany Profit and(4%) Tax Contract 378.00
Total 3078.00
Rate For L.S 3078.00

No Title
Earthwork in excavation in foundation in all kind of soil, ramming the bottom, stacking the excavated materials at
least 3m. clear from the edge of the excavation all complete.
2 Name of activity Qty Unite Rate Amount
Unskilled Labour 0.8 M3 5.40 4.32
0

Total amount without Campany Profit and Tax Contract 4.32


Total amount Including (10%) Campany Profit and(4%) Tax Contract 0.60
Total 4.92
Rate For 1 M3 4.92

No Title
Providing and filling with soil in 150mm. layers, watering and ramming all complete.

Name of activity Qty Unite Rate Amount


3 Filling materials 1.1 M3 1.00 1.1
Unskilled Labour 0.5 5.40 2.7
Equipment 3% of Labour cost 0.081

Total amount without Campany Profit and Tax Contract 3.881


Total amount Including (10%) Campany Profit and(4%) Tax Contract 0.54
Total 4.42
Rate For 1 M3 4.42

No Title
Exploding rock and cleaning debris from the site all complete.

Name of activity Qty Unite Rate Amount


4 Dynamite, detonator 1 L.S 96.00 96
Skilled Labour 0.60 M/d 15.00 9
Unskilled Labour 1 M/d 5.40 5.4
Equipment for drilling 1 Set 30.00 30

Total amount without Campany Profit and Tax Contract 140.4


Total amount Including (10%) Campany Profit and(4%) Tax Contract 19.66
Total 160.06
Rate For 1 M3 16.01
No Title
Dewatering works all complete.

5 Name of activity Qty Unite Rate Amount


Pump and labour for dewatering 1 L.S 1600.00 1600

Total amount without Campany Profit and Tax Contract 1600


Total amount Including (10%) Campany Profit and(4%) Tax Contract 224.00
Total 1824.00
Rate For 1 L.S 1824.00

No Title
River diversion works all complete.

6 Name of activity Qty Unite Rate Amount


Excavator and labour for diversion 1 L.S 1404.00 1404

Total amount without Campany Profit and Tax Contract 1404


Total amount Including (10%) Campany Profit and(4%) Tax Contract 196.56
Total 1600.56
Rate For 1 L.S 1600.56

No Title
Providing and soling boulder stone (Stone pitching) including filling the voids with sand all complete.

Name of activity Qty Unite Rate Amount


7 Stone 1.10 m3 10.00 11
Sand 0.25 m3 7.00 1.75
Skilled Labour 0.18 M/d 15.00 2.7
Unskilled Labour 0.50 M/d 5.40 2.7

Total amount without Campany Profit and Tax Contract 18.15


Total amount Including (10%) Campany Profit and(4%) Tax Contract 2.54
Total 20.69
Rate For 1 M3 20.69

No Title
Providing and laying plain cement concrete 1:3:6 on base of foundation including centering & shuttering work
where necessary, in perfect line & level with proper compaction, curing all complete.

Name of activity Qty Unite Rate Amount


8 Cement 220.00 Kg. 0.19 41.8
Coarse aggregate 0.90 M3 7.75 6.975
Sand 0.45 M3 8.00 3.6
Skilled Labour 0.30 M/d 15.00 4.5
Unskilled Labour 3.20 M/d 5.40 17.28

Total amount without Campany Profit and Tax Contract 74.155


Total amount Including (10%) Campany Profit and(4%) Tax Contract 10.38
Total 84.5
Rate For 1 M3 84.5

No Title
Providing and laying plain cement concrete 1:2:4 (M15) including centering & shuttering work where necessary,
in perfect line & level with proper compaction, curing all complete.

Name of activity Qty Unite Rate Amount


9 Cement 320.00 Kg. 0.19 60.8
Coarse aggregate 0.88 M3 7.75 6.82
Sand 0.440 M3 8.00 3.52
Skilled Labour 0.30 M/d 15.00 4.5
Unskilled Labour 3.25 M/d 5.40 17.55

Total amount without Campany Profit and Tax Contract 93.19


Total amount Including (10%) Campany Profit and(4%) Tax Contract 13.05
Total 106.2
Rate For 1 M3 106.2
No Title
Providing and laying reinforced cement concrete 1:1.5:3 (M20) in Kerb, Approach slabs, bearing stopper etc. in
perfect line & level with proper compaction using vibrator and curing all complete excluding cost of the centering
& shuttering and the reinforcement.

Name of activity Qty Unite Rate Amount


10
Cement 410.00 Kg. 0.19 77.9
Coarse aggregate 0.84 M3 7.75 6.51
Sand 0.420 M3 8.00 3.36
Skilled Labour 0.50 M/d 15.00 7.5
Unskilled Labour 3.50 M/d 5.40 18.9

Total amount without Campany Profit and Tax Contract 114.17


Total amount Including (10%) Campany Profit and(4%) Tax Contract 15.98
Total 130.2
Rate For 1 M3 130.15

No Title
Providing and laying reinforced cement concrete 1:1:2 (M25) in Girder base & backwall, Girders, beams, slabs,
diaphragm, Abutment etc. in perfect line & level with proper compaction using vibrator and curing all complete
excluding cost of the centering & shuttering and the reinforcement. Weepholes (75mm. Pipe) at 2.0 meter
intevals (in staggered position) vertically and horizontally in the Abutments should be provided.

11
Name of activity Qty Unite Rate Amount
Cement 570.00 Kg. 0.19 108.3
Coarse aggregate 0.85 M3 5.00 4.25
Sand 0.425 M3 8.00 3.4
Skilled Labour 0.50 M/d 15.00 7.5
Unskilled Labour 3.50 M/d 5.40 18.9

Total amount without Campany Profit and Tax Contract 142.35


Total amount Including (10%) Campany Profit and(4%) Tax Contract 19.93
Total 162.3
Rate For 1 M3 162.28

No Title
Supplying and fixing reinforcement steel (Fe 415) with bending, placing in position and binding with GI wire
including cost of the binding wire all complete.

Name of activity Qty Unite Rate Amount


12 Steel 1.05 T. 778.00 816.9
Binding wire 15.00 Kg. 1.58 23.655
Skilled Labour 10.00 M/D 15.00 150
Unskilled Labour 5.00 M/D 5.40 27
0

Total amount without Campany Profit and Tax Contract 1017.555


Total amount Including (10%) Campany Profit and(4%) Tax Contract 142.46
Total 1160.01
Rate For 1 Ton 1160.01

No Title
Providing and fixing centering & shuttering of steel/plywood/wood including strutting, propping etc. for RCC works
in Abutment,Girder base, Backwall, Bearing stopper etc. and removal of shuttering all complete

Name of activity Qty Unite Rate Amount


13 Wooden timber for formwork 0.08 Cum. 255.00 20.4
Nail 2.50 Kg. 2.00 5
Skilled Labour 3.50 M/D 15.00 52.5
Unskilled Labour 5.00 M/D 5.40 27
0

Total amount without Campany Profit and Tax Contract 104.9


Total amount Including (10%) Campany Profit and(4%) Tax Contract 14.69
Total 119.6
Rate For 1 Sqm 11.96
No Title
Providing and fixing centering & shuttering of steel/plywood/wood including strutting, propping etc. for RCC works
in girder, beams, slab etc. and removal of shuttering all complete.

Name of activity Qty Unite Rate Amount


14 Wood for formwork 0.08 Cum. 255.00 20.4
Nail 2.50 Kg. 2.00 5
Steel Plate/wooden Plank 1.00 L.S. 76.00 76
Skilled Labour 2.50 Nos. 15.00 37.5
Unskilled Labour 3.50 Nos. 5.40 18.9

Total amount without Campany Profit and Tax Contract 157.8


Total amount Including (10%) Campany Profit and(4%) Tax Contract 22.09
Total 179.9
Rate For 1 Sqm 17.99

No Title
Providing and fixing MS angle iron and MS plate in expansion/construction joint in perfect line and level all
complete.

Name of activity Qty Unite Rate Amount


15 MS Angle 1.10 m. 8.30 9.13
MS plate 1.10 m. 7.00 7.7
Skilled Labour 0.25 M/D 15.00 3.75
Unskilled Labour 0.25 M/D 5.40 1.35
0

Total amount without Campany Profit and Tax Contract 21.93


Total amount Including (10%) Campany Profit and(4%) Tax Contract 3.07
Total 25.00
Rate For 1 RM 25.00

No Title
Providing and laying Stone masonry Wing walls, Retaining walls in 1:4 cement mortar in perfect line & level and
curing including placement of weepholes (75mm. Pipe) at 2 meter intevals (in staggered position) vertically and
horizontally all complete.

Name of activity Qty Unite Rate Amount


16 Stone 1.00 Cum. 5.90 5.9
Bond stone 0.10 Cum. 5.00 0.5
Cement 128.00 Kg. 0.19 24.32
Sand 0.340 cum. 15.00 5.1
Skilled Labour 0.50 Nos. 15.00 7.5
Unskilled Labour 1.00 Nos. 5.40 5.4

Total amount without Campany Profit and Tax Contract 48.72


Total amount Including (10%) Campany Profit and(4%) Tax Contract 6.82
Total 55.54
Rate For 1 M3 55.54

No Title
Providing and laying Stone masonry Wing walls, Retaining walls in 1:4 cement mortar in perfect line & level and
curing including placement of weepholes (75mm. Pipe) at 2 meter intevals (in staggered position) vertically and
horizontally all complete.

Name of activity Qty Unite Rate Amount


17 Stone 1.00 Cum. 5.90 5.9
Bond stone 0.10 Cum. 5.00 0.5
Cement 128.00 Kg. 0.19 24.32
Sand 0.340 cum. 15.00 5.1
Skilled Labour 0.50 Nos. 15.00 7.5
Unskilled Labour 1.00 Nos. 5.40 5.4

Total amount without Campany Profit and Tax Contract 48.72


Total amount Including (10%) Campany Profit and(4%) Tax Contract 6.82
Total 55.54
Rate For 1 M3 55.54
No Title
Cement sand pointing (1:3 ) on stone masonry work on exposed surface including racking the joints, wetting the
surface and curing all complete.

Name of activity Qty Unite Rate Amount


18 Cement 282.00 Kg. 0.19 53.58
Sand 0.560 cum. 17.00 9.52
Skilled Labour 10.00 M/D 15.00 150
Unskilled Labour 10.00 M/D 5.40 54
0

Total amount without Campany Profit and Tax Contract 267.1


Total amount Including (10%) Campany Profit and(4%) Tax Contract 37.39
Total 304.49
Rate For 1 Sqm 3.04

No Title
Providing and fixing Hand rail of I-beam and 3" GI pipe all complete.

Name of activity Qty Unite Rate Amount


I-beam 12mm(14x10 cm) 36.00 Rm 11.00 396
19 3"GI pipe 108.00 Rm 12.00 1296
Equipment and welding materials 1.00 L.S. 22.00 22
Skilled Labour 10.00 M/D 15.00 150
Unskilled Labour 10.00 M/D 5.40 54
0

Total amount without Campany Profit and Tax Contract 1918


Total amount Including (10%) Campany Profit and(4%) Tax Contract 268.52
Total 2186.52
Rate For 1 Rm 58.46

No Title
Two coats of approved colour oil paint with one coat of primer on handrail all complete.

Name of activity Qty Unite Rate Amount


20 Primer 8.00 Lt. 7.00 56
Oil paint 16.00 Lt. 7.00 112
Skilled Labour 12.00 M/D 15.00 180
Unskilled Labour 8.00 M/D 5.40 43.2

Total amount without Campany Profit and Tax Contract 391.2


Total amount Including (10%) Campany Profit and(4%) Tax Contract 54.77
Total 445.97
Rate For 1 Rm 4.46

No Title
Providing and fixing elastrometric bearing (50 x 25 x 5.5cm) with steel plates at base of girders including 2.5cm
thick bearing plinth (1:2 cement mortar) in perfect line and level all complete.
21
Name of activity Qty Unite Rate Amount
Elastrometric Bearing 4.00 Sets 83.34 333.36
0

Total amount without Campany Profit and Tax Contract 333.36


Total amount Including (10%) Campany Profit and(4%) Tax Contract 46.67
Total 380.03
Rate For 1 Sets 380.03

No Title

Providing and fixing rain water drainage pipe 75mm diameter including floor trap all complete.

22 Name of activity Qty Unite Rate Amount


75mm. Dia PVC pipe 1.00 Set 5.40 5.4
Skilled Labour 0.05 M/D 15.00 0.75
0

Total amount without Campany Profit and Tax Contract 6.15


Total amount Including (10%) Campany Profit and(4%) Tax Contract 0.86
Total 7.01
Rate For 1 M 7.01
No Title
Providing and fixing 3 inch dia GI pipe (heavyduty) for crossing existing water supply with all necessary
accessories material all complate.
23 Name of activity Qty Unite Rate Amount
GI Pipe Dia 3" 1.00 m 8.80 8.8
0

Total amount without Campany Profit and Tax Contract 8.8


Total amount Including (10%) Campany Profit and(4%) Tax Contract 1.23
Total 10.03
Rate For 1 M 10.03

No Title
Providing and fixing Regulating Metallic gate having the size 0.5m width and 1.05m height (including handle
wheel, bearing plates, C channels, Spindles etc. as per drawing) including RCC support structure both sides with
breast wall , application of one coat red oxide and two coat oil paint as per drawing all complete .
24
Name of activity Qty Unite Rate Amount
Metalice Gate 1.00 sets 201.75 201.75
0

Total amount without Campany Profit and Tax Contract 201.75


Total amount Including (10%) Campany Profit and(4%) Tax Contract 28.25
Total 230.00
Rate For 1 Sets 230.0

No Title
Providing and fixing PE pipe th:250mm dia for canal all complete.

25 Name of activity Qty Unite Rate Amount


PE Pipe Dia 250mm 1.00 M 49.12 49.12
0

Total amount without Campany Profit and Tax Contract 49.12


Total amount Including (10%) Campany Profit and(4%) Tax Contract 6.88
Total 56.00
Rate For 1 M 56.00

No Title

Providing and filling with coarse aggregate sub-base, watering and ramming under approach slab all complete.

Name of activity Qty Unite Rate Amount


26 Coars aggregate 1.20 m3 6.18 7.41
Skilled Labour 0.10 M/D 15.00 1.5
Unskilled Labour 0.30 M/D 5.40 1.62
0

Total amount without Campany Profit and Tax Contract 10.53


Total amount Including (10%) Campany Profit and(4%) Tax Contract 1.47
Total 12.00
Rate For 1 M3 12.00

No Title

Providing and laying dry stone wall for protection of River side as per drawing all complete.

Name of activity Qty Unite Rate Amount


Excavetor For Collectiuon Big Boulder stone 1.00 m3 1.50 1.5
27 Excavetor For Boulder Loading 1.00 m3 1.50 1.5
Excavatoer For Boulder Placing 1.00 m3 2.00 2
Track for Transportation of Big Boulder 1.70 m3 1.70 2.89
other light equipment and labour cost(5%) 0.05 LM 6.70 0.335
0

Total amount without Campany Profit and Tax Contract 8.225


Total amount Including (10%) Campany Profit and(4%) Tax Contract 1.15
Total 9.38
Rate For 1 M3 9.38