You are on page 1of 4

Saawariya Premium Sweets & Snacks

Aawa Road, Bhairahawa, Rupandehi District

Work schedule & completed work


Contract Identification No.
Project Name: Construction of G+1 Composite Steel Structure
Site:-Bhairahawa, Rupandehi
Date 2080/04/09

Year 2079 Year 2080


Remaining
Asoj Kartik Mangshir Poush Magh Falgun Chaitra Baishah Jestha Asar Shrawan Bhadra Asoj Remarks
SN Description Work
1 Excavation completed 100%
2 RCC upto plinth completed 100%
3 foundation wall completed 100%
4 ISMC Column & ISMB work Ground Floor completed 100%
5 ISMC Column & ISMB work First Floor completed 100%
6 Truss Work with Puff Panel work completed 100%
7 Ground floor AAC Masonry & Brick work completed 100%
8 First Floor AAC Masonry & Brick work completed 100%
9 Second floor Brick work completed 100%
10 Ground floor plaster completed 100%
11 First Floor plaster completed 100%

13 Doors and Windows Aluminium Series type completed 100%


14 Flooring completed 100%
15 False Ceiling Work completed 100%
16 painting completed 100%
17 Railing work completed 100%
18 Steel & iron work completed 100%
19 electrical works completed 95%
Main Panel Work 75% 75%
Backup Generator install 0%
20 Sanitary works completed 100%
21 Front Glass Work GF,FF completed 100%
22 Outer Verandah and Passsge work completed 100%
Interior Furniture and Furnishing work
23 Miscellaneous works 100%