ANNEXURE G : STAGES OF PAYMENT

Annexure G - PAYMENT SCHEDULE / MODE OF PAYMENT

% of
Sr. No Work Completed Work
  Payment Schedule for RCC, BBM, ECT. & Int. & Ext. Plaster  
  Per sq. ft. BUP area on Completion of RCC Work). (1250.00/-) Rs. 40%  
1 RCC Slab Columns Beams Work 1st to 24 th Slab (2.50 % of Each Slab) 60%
2 On Completion up to U.G. Tank - W/Water Tank 5%
3 On Completion of Waterproofing Work 5%
4 On Completion of 0/H Tanks 5%
5 On Completion of Brick Work Internal 4” & 6” Thick 10%
6 On Completion External Plasters 10%
7 On Site Clearance & Remaining Balance Work 5%
  TOTAL 100%

% of
Sr. No Work Completed Work
  Payment Schedule for Finishing Items. (850.00 /-) Rs. 35%  
1 Internal Plaster Work 8%
2 Floor Tiles & Wall Dado Tiles 8%
3 Kitchen Granite with Marble Frame Platform 8%
4 Plumbing & Drainage Work Complete. 8%
5 P.O.P. Gypsum Work (Living, Bed Room, Kitchen) 8%
6 Door/Window Cells, etc. 8%
7 Door / Shutters of All Kind 8%
8 Electrical works with Wiring & Switches & Socket 8%
9 Aluminum Sliding Windows of all kind. 8%
10 Sanitaryware & UPVC Fitting on Completion 8%
11 Painting Internal Plastic Paints 8%
12 Painting External on Coemption Waterproofing Texture Paints 8%
13 Site Clearance & Complete Handing Over of Site 4%
  TOTAL 100%

EXTERNAL DEVELOPMENT 25%


CIVIL SUPERSTRUCTUER Work - 900.00 /- Rs. Per Sq. Ft.
ESCAVATION, FOUNDATION, R.C.C. WORK, BRICK WORK & EXTARNAL PLASTER WORK,
WATERPROFFING WORK

Finishing Work – 650.00 /- Rs. Per Sq. Ft.


INTERNAL PLASTER & CLEANING WORK
P.O.P. & PAINTING (EXTRNAL & INTERNAL) WORK
PLUMBING & ELECTRICAL WORK
TILES & KITCHEN PLATFROM WORK
DOOR FRAME & DOOR SHUTTER WORK
ALUMINIUM SLIDEDING WINDOW & DOOR WORK
S. S. & M. S. RAILING WORK

EXTERNAL DEVELOPMENT WORK: 550/- PER SQFT

Annexure H- CONSTRUCTION SCHEDULE

To be Provided by the
Contractor