7. PLUMBING WORKS
7.3. Fixtures and fittings
7.3.1. Installation of Floor Drains 5 pcs 90% on-going
7.3.2. Installation of Shower Sets 2 sets 90% on-going
7.3.3. Installation of Faucets 8 pcs 90% on-going
7.3.4. Installation of Kitchen Sink 1 set 90% on-going
7.3.5. Installation of Lavatory Sink 2 sets 90% on-going
7.3.7. Installation of Water Closets 2 sets 90% on-going
7.4. Testing and Commissioning 2 sets 0% pending
8. ELECTRICAL WORKS
8.5. Testing and commissioning 0% pending
9. WOODWORKS AND CARPENTRY
9.2. Installation of Kitchen Modular Cabinet 0% pending
12. PAINTING WORKS
12.1. PAINTING WORKS OF WALL
12.1.1. Exterior Wall
- Painting of downspout 90% on-going
12.1.2. GF Interior Wall (common area)
12.1.3. GF T&B Interior Wall
- Top Coat; semi-gloss white 90% on-going
12.2. PAINTING OF METAL WORKS
12.2.1. Stairs (baluster & flat bar rail guide)
- Top Coat; QDE black paint 50% on-going
12.2.5. Catch basin gratings
- Primer; red oxide 80% on-going
- Top Coat; QDE black paint 80% on-going
12.3. PAINTING WORKS OF DOORS
12.3.2. Bedroom-1 Door
- Door Jamb; primer flat wall enamel white 100% completed
- Door Jamb; top coat QDE white 80% on-going
12.3.3. Bedroom-2 Door
- Door Jamb; top coat QDE white 80% on-going
12.3.4. Master's Bedroom Door
- Door Jamb; top coat QDE white 80% on-going
12.4. PAINTING WORKS FOR CARPENTY (ceilings & cabinets)
12.4.6. Stair thread wood planks
- Base coat; QDE maple brown wood stain 14.00 steps 0% on-going
- Top Coat; clear gloss varnish 14.00 steps 0% on-going
12.4.7. Stair Handrail
- Base coat; QDE maple brown wood stain 0% on-going
- Top Coat; clear gloss varnish 0% on-going
12.4.8. Stair under ceiling and sidings
- Skimcoat; boral joint filler 50% on-going
- Primer; flat latex white 0% on-going
- Top Coat; semi-gloss white 0% on-going
9.3.2. Installation of Cabinet Doors (2-swing type) 100% completed handles to follow
9.4. Bedroom-2 Cabinet
9.4.2. Installation of Cabinet Doors (2-swing type) 100% completed handles to follow
9.5. Master's Bedroom Cabinet
9.5.2. Installation of Cabinet Doors (2-swing type) 100% completed handles to follow
8. ELECTRICAL WORKS
8.2. POWER LINE
10. DOORS
10.2. GF Sliding Door (aluminum framed glass door w/ sealant, framing, bolted and screw 0% pending
to be installed by developer
10.3. GF T&B Door (PVC door jamb and door leaf, cyl
10.3.3. Installation of door knob 0% pending
10.4. 2F T&B Door (PVC door jamb and door leaf, cyli
10.4.3. Installation of door knob 0% pending
10.5. Bedroom-1 Door (hollow core flush door, meta
10.5.3. Installation of door knob 0% pending
10.6. Bedroom-2 Door (hollow core flush door, meta
10.6.2. Installation of door leaf w/ hinges 0% pending
10.6.3. Installation of door knob 0% pending
10.7. Master's Bedroom Door (hollow core flush doo
10.7.2. Installation of door leaf w/ hinges 0% pending
10.7.3. Installation of door knob 0% pending
10.8. 2F T&B sliding door (aluminum framed glass leaf door, w/ sealant, bolted& screwed 0% pending
to be installed by developer
12. PAINTING WORKS
12.1. PAINTING WORKS OF WALL
12.1.1. Exterior Wall
- Primer; flat latex white 95% on-going
- Top Coat; semi-gloss white 90% on-going
- Accent Paint-1; orange semi-glosss 95% on-going
- Accent Paint-2; yellow semi-glosss 95% on-going
- Painting of downspout 0% pending downspout installation
12.1.2. GF Interior Wall (common area)
- Top Coat; semi-gloss white 20% on-going
12.1.3. GF T&B Interior Wall
- Top Coat; semi-gloss white 20% on-going
12.1.4. 2F Hallway Drywall
- Top Coat; semi-gloss white 20% on-going
12.1.5. Bedroom-1 Drywall
- Top Coat; semi-gloss white 20% on-going
12.1.6. Bedroom-2 Drywall
- Top Coat; semi-gloss white 20% on-going
12.1.7. Master's Bedroom Drywall
- Top Coat; semi-gloss white 20% on-going
12.1.8. 2F T&B Interior Wall
- Skimcoat; white 70% pending
- Primer; flat latex white 70% pending
- Top Coat; semi-gloss white 20% on-going
12.2. PAINTING OF METAL WORKS
12.2.1. Stairs (baluster & flat bar rail guide)
- Top Coat; QDE black paint 40% on-going
12.2.2. Stairs framing (2"x2" angle bar)
12.3.2. Bedroom-1 Door
- Door Jamb; top coat QDE white 20% on-going
12.3.3. Bedroom-2 Door
- Door Jamb; top coat QDE white 20% on-going
12.3.4. Master's Bedroom Door
- Door Jamb; primer flat wall enamel white 100% completed
- Door Jamb; top coat QDE white 20% on-going
12.4. PAINTING WORKS FOR CARPENTY (ceilings & cabinets)
12.4.1. Kitchen
- Top Coat; semi-gloss white 30% on-going
12.4.2. GF T&B
- Top Coat; semi-gloss white 10% on-going
12.4.3. Mezzanine ceiling adjacent to stairs
- Top Coat; semi-gloss white 0% pending
12.4.6. Stair thread wood planks
- Base coat; QDE maple brown wood stain 14.00 steps 30% pending
- Top Coat; clear gloss varnish 14.00 steps 30% pending
12.4.7. Stair Handrails
- Base coat; QDE maple brown wood stain 0% pending
- Top Coat; clear gloss varnish 0% pending
12.4.8. Stair under ceiling and sidings
- Skimcoat; boral joint filler 10% on-going
- Primer; flat latex white 10% on-going
- Top Coat; semi-gloss white 0% pending
12.4.9. 2F T&B
- Primer; flat latex white 80% on-going
- Top Coat; semi-gloss white 80% on-going
*
13. FLOOR FINISHES & TILING WORKS
13.2. Second Floor Coverings
13.2.3. Master's Bedroom
- Installation of 200mm x 900mm x 8mm laminated wood flooring 95% on-going
13.2.4. Hallway
- Installation of 200mm x 900mm x 8mm laminated wood flooring 80% on-going
13.2.5. 2F T&B
- Installation of 200mm x 200mm x 6mm vitrified ceramic floor tiles 90% on-going
- Application of tile grout white 90% on-going
Date: As of Aug 14-19, 2023
Project: Raemulan Lands Incorporated
Unit No.: Block 5 Lot 22
Subject: Status of Units Summary
Prepared by: Engr. Mark Anthony F. Baliton - Project-In-Charge
SUMMARY
Total Balance
Item no Scope of works Area/Q Unit Area/ Unit % Status Remarks
TY QTY
7.4. Testing and Commissioning 0% pending
8. ELECTRICAL WORKS
8.5. Testing and Commissioning 0% pending
Housekeeping