Handing Over Date: 13th June, 2022
Commencement Date: 27th June, 2022
CONTRAC Contract Period: 6 months (26 Weeks)
PROJECT
COST
Contract sum: Kshs. 172,885,038.20
Authorized additional: Kshs. NIL
Revised contract sum: Kshs. NIL
Amount certified to date: Kshs. 102,250,581.20
1st Certificate: Kshs. 59,929,096.00
2nd Certificate: Kshs. 29,633,507.20
3rd Certificate: Ksh. 12,687,978.00
% of contract expended: 59.14%
6
KEY MILESTONES &
DELIVERABLES
Activities in progress:
Plaster to heads of walls and edges
3NO. WHOLESALE BLOCKS
Roof cover installation
Overall progress 75%
Installation of roller shutter doors
Casting of window cills
Floor screeding to receive terrazzo
Activities in planning:
Installation of rainwater goods
Fixing of facia
Painting
7
KEY MILESTONES &
DELIVERABLES
Activities in progress:
Wall finishes-plaster to heads of
4 NO. RETAIL BLOCKS
walls and concrete edges/faces,
Overall progress 80%
Completion of Roof cover gaps
Installation of terrazzo floor
Installation of roller shutter doors
Activities in planning:
Fixing of facia
Installation of rainwater goods
Painting
8
KEY MILESTONES &
DELIVERABLES Activities in progress:
ADMINSTRATION & Completion of internal plaster
REVENUE OFFICE
Floor tiling
Overall progress 90%
Fitting internal doors
Internal plumbing and electrical works
Activities in planning
Glazing
Completion of roof cover and
installation of rainwater goods
Painting
9
KEY MILESTONES
& DELIVERABLES Activities in progress:
Demolition of internal walling as
4NO. MARKET SHEDS
per instructions
Overall progress 80%
Roof cover installation
Activities in planning
Floor finish
Installation of steel gutters and rain
water goods
Painting
10
KEY MILESTONES &
Activities in progress:
DELIVERABLES
Roof truss installation
Windows fabrication
HOME NURSING CENTRE Internal plumbing and electrical installations
Overall progress 68% Activities in planning:
Completion of internal and external wall
finishes
Glazing
Floor finish
Installation of rainwater goods
Painting
Dependencies:
Plaster finish vs fitting of doors, completion of
internal plumbing and electrical works
11
KEY MILESTONES &
DELIVERABLES Activities in progress
Completion of substructure for restaurant-casting
of floor bed
NEW ABLUTION BLOCK,
SEPTIC TANK, SOAK PIT, Completion of walling for septic tank
KITCHEN &RESTAURANT
Formwork to columns for restaurant
Overall progress 40%
Activities in planning:
Setting out and start of new ablution block
Completion of superstructure for restaurant
Casting Suspended floor for septic tank and beams
Dependencies:
Filling and ramming approved around septic tank
walling vs setting out of new ablution block
12 Activities in progress
KEY MILESTONES & Clearance of walkways, driveways and parking
DELIVERABLES areas in readiness for stripping
Setting out and marking for walkways,
driveways and parking
EXTERNAL WORKS
Overall progress 5% Activities in planning:
Culvert works
Drainage pipework installation
Stripping roadways and parking areas
Dependencies:
Setting out and survey works vs clearance of
walkways, driveways and parking areas
Favorable weather vs earthworks
Minimal external activities vs earthworks
Mobilization of adequate equipment
13
16
Creating a baseline:- 17
o Original scheduled start and finish dates,
o Planned efforts,
PROJECT PERFORMANCE o Estimated costs, Budgeted revenue
Forecasting the budget:-consistent reforecasting and
revisiting the budget to prevent things from getting
Performance Against out of hand
Budget Outlining resource usage:-Reviewing the number of
people and ensuring they are fully utilized
Monitoring the project’s schedule:-Informs activity
coordination problems, resource conflicts and cost
overruns.
Managing the scope:-Avoiding scope creep.
Controlling the project instead of the project
controlling us.
18 APPENDIX
SHOWCASE
EXPANSION JOINT
21
FOUNDATION WORKS
23
CONCRETE GUTTER
24
RING BEAM
25
HOT WORKS
26
ELECTRICAL INSTALLATIONS
27
SETTING OUT
28
MASONRY WALLING
30
TERRAZZO FLOOR
31
ROOFING
32