PROPOSED CONSTRUCTION OF

MAKUENI FRESH PRODUCE MARKET


AT EMALI TOWN

PROJECT STATUS REPORT


PROJECT SUMMARY

 CLIENT: DEPARTMENT OF TRADE, MARKETING, INDUSTRY,


CULTURE AND TOURISM.
 FUNDED BY: GOVERNMENT OF MAKUENI PROJECT CONTRACT
NO: 948610-2021-2022
 SUPERVISION: DEPARTMENT OF INFRASTRUCUTRE, TRANSPORT,
PUBLIC WORKS & ENERGY
 MAIN CONTRACTOR: M/S CITILINK SOLUTIONS LTD P.O. BOX 316-
01001 KALIMONI
 ELECTRICAL SUB-CONTRACTOR: DOMESTIC
 MECHANICAL SUB-CONTRACTOR: DOMESTIC

2
3
 Handing Over Date: 13th June, 2022
 Commencement Date: 27th June, 2022
CONTRAC  Contract Period: 6 months (26 Weeks)

T DETAILS  Intended Completion Date: 27th December,2022


 First Revised Completion Date: 1st January, 2023
 2nd Revised Completion Date: 15th February 2023
 Time extension requested 45 days
 Time Extension Granted YES
PROGRESS
– Contract period: 6 Months (26 Weeks)
– Period elapsed up to 20th January 2023: 30 Weeks 3days
– % of contract period elapsed: 100%
– % of work physically completed: 70%
4  3 NO WHOLESALE BLOCKS comprising of 30no. individual
wholesale stalls
PROJECT  4 NO RETAILS BLOCKS comprising of 96no. individual retail
SCOPE stalls
 4 NO. MARKET SHEDS
 ADMINISTRATION AND REVENUE office
The total amount of  KITCHEN & RESTAURANT
work that is to be done  HOME NURSING/ BREASTFEEDING CENTER
in order to deliver the 
ABLUTION BLOCK, SEPTIC TANK & SOAK PIT
finished product:
 6 NO. WATER TANK BASED & 24NO. 10,000 LITRES WATER
TANKS
 WASTE DISPOSAL BIN & HAND WASHING POINTS
 EXTERNAL WORKS – Cabro Paved Driveways, Walkways and
Parking, Storm water
 Management & Drainage System, Landscaping Works, Water
Harvesting and Water Reticulation, Driveway Street lighting,
 SPECIALIST WORKS- Cold Rooms, Mobile Weigh Bridge.
5

PROJECT
COST
 Contract sum: Kshs. 172,885,038.20
 Authorized additional: Kshs. NIL
 Revised contract sum: Kshs. NIL
 Amount certified to date: Kshs. 102,250,581.20
  1st Certificate: Kshs. 59,929,096.00
  2nd Certificate: Kshs. 29,633,507.20
  3rd Certificate: Ksh. 12,687,978.00
 % of contract expended: 59.14%
6
KEY MILESTONES &
DELIVERABLES
 Activities in progress:
 Plaster to heads of walls and edges
3NO. WHOLESALE BLOCKS
 Roof cover installation
Overall progress 75%
 Installation of roller shutter doors
 Casting of window cills
 Floor screeding to receive terrazzo

 Activities in planning:
 Installation of rainwater goods
 Fixing of facia
 Painting
7
KEY MILESTONES &
DELIVERABLES
 Activities in progress:
 Wall finishes-plaster to heads of
4 NO. RETAIL BLOCKS
walls and concrete edges/faces,
Overall progress 80%
 Completion of Roof cover gaps
 Installation of terrazzo floor
 Installation of roller shutter doors

 Activities in planning:
 Fixing of facia
 Installation of rainwater goods
 Painting
8
KEY MILESTONES &
DELIVERABLES  Activities in progress:
ADMINSTRATION &  Completion of internal plaster
REVENUE OFFICE
 Floor tiling
Overall progress 90%
 Fitting internal doors
 Internal plumbing and electrical works

 Activities in planning
 Glazing
 Completion of roof cover and
installation of rainwater goods
 Painting
9
KEY MILESTONES
& DELIVERABLES  Activities in progress:
 Demolition of internal walling as
4NO. MARKET SHEDS
per instructions
Overall progress 80%
 Roof cover installation

 Activities in planning
 Floor finish
 Installation of steel gutters and rain
water goods
 Painting
10
KEY MILESTONES &
 Activities in progress:
DELIVERABLES
 Roof truss installation
 Windows fabrication
HOME NURSING CENTRE  Internal plumbing and electrical installations
Overall progress 68%  Activities in planning:
 Completion of internal and external wall
finishes
 Glazing
 Floor finish
 Installation of rainwater goods
 Painting
 Dependencies:
 Plaster finish vs fitting of doors, completion of
internal plumbing and electrical works
11
KEY MILESTONES &
DELIVERABLES  Activities in progress
 Completion of substructure for restaurant-casting
of floor bed
NEW ABLUTION BLOCK,
SEPTIC TANK, SOAK PIT,  Completion of walling for septic tank
KITCHEN &RESTAURANT
 Formwork to columns for restaurant
Overall progress 40%

 Activities in planning:
 Setting out and start of new ablution block
 Completion of superstructure for restaurant
 Casting Suspended floor for septic tank and beams

 Dependencies:
 Filling and ramming approved around septic tank
walling vs setting out of new ablution block
12  Activities in progress
KEY MILESTONES &  Clearance of walkways, driveways and parking
DELIVERABLES areas in readiness for stripping
 Setting out and marking for walkways,
driveways and parking
EXTERNAL WORKS
Overall progress 5%  Activities in planning:
 Culvert works
 Drainage pipework installation
 Stripping roadways and parking areas
 Dependencies:
 Setting out and survey works vs clearance of
walkways, driveways and parking areas
 Favorable weather vs earthworks
 Minimal external activities vs earthworks
 Mobilization of adequate equipment
13

 The work objectives are first defined and guidelines


PROJECT for satisfactory performance identified
PERFORMANC  The quantity of work output is measured. Quality
E check is done to ensure it is not compromised in the
face of high productivity.
 Checkpoints are identified to determine whether our
timelines/implementation plans need modification e.g.
the timeline is modified after observing that work
objectives are ahead of schedule.
 Self appraisals- Follow up with employees on the
Performance Against
project on how they are doing with the project by
Objectives having each one of them measure his/her performance.
This helps in highlighting discrepancies between what
the employee and management think are important
performance factors.
 Giving positive feedback to teams and individuals for
their contributions. This boosts morale and sees team
members through to the completion of project goals.
14

 Schedule:-Progress is evaluated as a going concern and


PROJECT PERFORMANCE
updated regularly for reporting to stakeholder group
 Quality:-All standard checks and tests are performed as
a going concern. A quality control plan as established is
adhered to.
Performance Against  Cost:-Actual spend in real time in comparison to what
Outcomes was budgeted and noting variances.
 Stakeholder satisfaction:- Checking in with all the
stakeholder in the course of implementation processes
helps ensuring that they are satisfied with the outcomes
they see.
 Progress, status reports:-
15
o A list of deliverables –completed and outstanding
o An overview of schedule activities that have commenced and those that are
completed
PROJECT o Schedule of activities ongoing and the percentage of work that has been
done
PERFORMANCE
o Estimating the time and /or resources required for in-progress schedule
activities
 Whether and to what extend quality standards are being met
Performance Against
 Total costs authorized and the amount of money spent on a
Outputs
particular activity
 How project resources are being used:-
o Analysis of underutilized resources:-Funds that remained unspent ;
o Underutilization of human labour is simply a waste that we avoid at all
costs.
o The value of unused materials-re-sale, recycling or use in other areas of the
project
 Routine collection of work performance information to be
used as input data for quality control measures.
 Work performance data raw measurement and observations
identified during tasks performed in order to complete the each
project component.
 Directing and managing project activity execution of
PROJECT  The project’s schedule status is assessed by
PERFORMANCE comparing actual activity start/end dates and actual
milestone dates to their planned dates:
 By maintaining a combined activities and
milestones report updated on a progress Gantt
Performance Against chart, we are able to track activities on the critical
Schedule path and ensure that none is lagging.
We regularly monitor the  This also provides less time for small problems to
project’s schedule
go undetected and, thus, suppress them evolving
performance and this provides
early indications of possible
into bigger problems.
activity-coordination problem,  Our project’s schedule status by comparing project
resource conflicts, and start/end dates and actual completion date to the
possible cost overruns.
planned dates didn’t work.

16
 Creating a baseline:- 17
o Original scheduled start and finish dates,
o Planned efforts,
PROJECT PERFORMANCE o Estimated costs, Budgeted revenue
 Forecasting the budget:-consistent reforecasting and
revisiting the budget to prevent things from getting
Performance Against out of hand
Budget  Outlining resource usage:-Reviewing the number of
people and ensuring they are fully utilized
 Monitoring the project’s schedule:-Informs activity
coordination problems, resource conflicts and cost
overruns.
 Managing the scope:-Avoiding scope creep.
Controlling the project instead of the project
controlling us.
18 APPENDIX
SHOWCASE

ROUTINE STAKEHOLDER MEETINGS


19

ROUTINE STAKEHOLDER MEETING


20

EXPANSION JOINT
21

INITIAL SITE BEFORE CONSTRUCTION


22

FOUNDATION WORKS
23

CONCRETE GUTTER
24

RING BEAM
25

HOT WORKS
26

ELECTRICAL INSTALLATIONS
27

SETTING OUT
28

FLOOR BED WORKS


29

MASONRY WALLING
30

ROLLER SHUTTER DOORS

TERRAZZO FLOOR
31

ROOFING
32

EXTERNAL KEY TO WALLS


33