INSTRUCTIONS TO CANDIDATES
1. This question paper consists of four (4) questions. Answer ALL questions.
3. The time given includes 30 minutes preparation time before and after assessment time.
4. Please make sure of the following requirements for the Final Assessment
i) Form of Contract PWD 203A(Rev. 1/2010)
ii) Form of Contract PAM 2018
iii) Interim Certificate JKR66 (pin. 4/2000)
5. iv) Final Account Certificate
6. Please make sure to write your FULL NAME, STUDENT ID, COURSE CODE, CLASS GROUP,
LECTURER’S NAME and DATE OF ASSESSMENT on the 1st page of your answer sheet.
7. Ensure that you practice full integrity in doing the assessment. Students are NOT allowed to “cut
and paste” online sources or any other sources directly to your answer. Evidence in plagiarism in
your answer script will result in non-compliance for the assessment.
All submissions are in Google Classroom and/or Email assigned under respective class lecturer.
If you are experiencing difficulties to submit on time due to internet or technical problems, please
contact the lecturer directly BEFORE the assessments end
QUESTION 1
The following are particulars of a contract for the construction and completion of a 4-storey
administration block for the District Police Headquarters of Perak Tengah, Seri Iskandar,
Perak.
a. Form of Contract PWD 203A (Rev. 1/2010)
b. Contract Sum RM 13,154,250.00
c. Date of Possession 2nd January 2021
d. Date for Completion 30th June 2023
g. Advance Payment Disbursement 25% Builders Works on 1st Mac 2021
h. Provisional Sum RM 250,000.00
i. Prime Cost Sum (excluding Profit & RM 2,595,000.00
Attendance)
j Performance Bond 5% Contract sum
k. Date of 1st Site Valuation 28th February 2021
l Amount paid up to Interim Payment No. 2 RM 2,000,550.00
m Deposit Performance Guarantee Sum up
to Interim Payment No. 2 RM 200,000.00
The main contractor has opted for the Performance Guarantee Sum in lieu of the performance
bond and Advance Payment were disbursed.
Preliminaries
The following items in the Preliminaries has been priced and the breakdown agreed upon
are as follows: -
On 28th June 2021 the contractor submitted his progress claim no. 5 to your office and a site
valuation was subsequently carried out with the presence of the Contractor on 5th July 2021.
Sub-Contract % Work
ITEM DESCRIPTION Provision (RM)
value (RM) done
1 Mechanical & Electrical 10
2,350,000.00 2,150,500.00
Installation
Profit 3% 70,500.00 64,465.00
Attendance 70,500.00 70,500.00
2 Plumbing Installation 245,000.00 270,500.00 20
Profit 3% 7,350.00 8,115.00
Attendance 7,350.00 7,350.00
TOTAL 2,750,700.00 2,751,480.00
iv) Materials on site (verified by the Quantity Surveyor and invoices enclosed)
AMOUNT
ITEM DESCRIPTION UNIT QUANTITY RATE (RM) (RM)
Note: Due to certain circumstances, interim payment no.3 and interim payment no.4 are to
be prepared again as directed by the S.O. whereas NSC’s works only commence after interim
payment no.4.
b) Prepare the Interim Certificate for the following interim valuations including the detail
calculation for the amount of Advance Payment recouped.
c) Prepare the Interim Certificate for Interim Valuation No. 5 showing the detail
calculation on every part of the certificate.
(23 marks)
QUESTION 2
The following are particulars of a newly completed Proposed Construction and Completion of
a 10-storey Apartment building in Seberang Perai Tengah for Messr. Bina Development (M)
Sdn Bhd.
A. PARTICULARS OF CONTRACT
D. PROVISIONAL SUMS
E. SUMMARY OF VARIATIONS
1. Building works
2. External works
3. P.C. Sums
2 Air-conditioninq installation
Accepted tender figure:
RM 195,200.00
V. O. No. 1 15,000.00 45,500.00
3 Electrical installation
Accepted tender figure:
RM 172,500.00
V. O. No. 1 16,000.00 5,500.00
V. O. No. 2 12,500.00 19,500.00
4 Lift installation
Accepted tender figure:
RM 580,300.00
No variation 0.00 0.00
© Hak Cipta Universiti Teknologi MARA CONFIDENTIAL
CONFIDENTIAL 7 AP/FEB 2022/BQS606/QSM606
4. Provisional Sums
The following items for provisional sums have been remeasured and agreed upon:-
QUESTION 3
a) An Architect's Instruction was issued for works that were specified under Provisional Sum
to be carried out by a Nominated Sub-Contractor, BB Construction Sdn Bhd. The Main
Contractor, AA Asal Bina Sdn Bhd, argued that works specified under provisional sums
are meant to be given to them. The Architect, however, insisted that the said works be
given to the sub-contractor. Advise the main contractor on the validity of the Architect’s
Instruction and his right in relation to profit and attendance.
(8 marks)
b) Immediately after the nomination of the sub-contractor, the main contractor objected to the
nomination made by the Architect. Discuss the situation where the main contractor could
validly object to the nomination and what are the options available to the Architect if the
objection was accepted?
(6 marks)
c) A few months into the contract, BB Construction Sdn Bhd, the nominated Sub-contractor,
wrote to the Architect complaining that the main contractor has not been paying them for
quite some time and had requested that the Employer pay them directly. Advise the
Architect as to the probable actions that should be taken as provided in the PAM Contract
2018.
(6 marks)
QUESTION 4
A contractor had been appointed to do a massive excavation work to form a man-made lake
in Putrajaya. The contract stated that, the excavated material was to be deposited to an area
provided by the owner. Unfortunately, the disposal of the excavated material to a designated
area was not allowed by the relevant authority. Instruction was issued by the S.O. for the
contractor to deposit the excavated material at an area in the lake to form an island.
The S.O. valued the work for forming the island based on the contract rates. The contractor
disputed by saying that the forming of the island was not within the scope of a variation but a
new contract work. Thus, the contract rates would not be applicable.
a) Determine whether the above variation falls within the scope in the contract and advise
the S.O.
(6 marks)
b) Outline with example/s the procedure for valuing variation under the contract.
(10 marks)