 1.0 TRUSS AND ROOFING LABOR AND MATERIALS QUOTATION

I. TRUSS FRAMING AND ROOFING

i. Mobilization and Demobilization


ii. Fabrication and Installation of Roof Framing Works for BLDG. A&B.
iii. Painting Works for Roof Framing (Applying Epoxy Primer and Topcoat).
iv. Installation of Rib-type Roof Sheet for BLDG A&B.
v. Installation of Gutter and Downspout, End Flashing, and Wall Flashing.
vi. Fabrication and installation of Wall Cladding.
vii. Housekeeping

II. SERVICE FEE

For our Proposed Services mention above, our fee shall be a lump sum amount
equivalent to FIVE MILLION, ONE HUNDRED AND TWO THOUSAND PESOS ONLY (PHP
5,102,000.00) vat exclusive. (See attached detailed estimates below for breakdown.)

III. TERMS OF PAYMENT


i. 30% - Down payment - 7days after receiving of P.O
ii. 65% - Progress Billing
iii. 5% - Retention 3-6months upon turn-over

IV. MODE OF PAYMENT


i. Cash, Check or Bank Transfer
V. COMPLETION TIME

Contact no. : (0977) 231 4217


Email : saiko.builders@gmail.com
i. 3 months upon receipt of NTP/PO
VI. PROPOSAL VALIDITY
i. 30 days from the date of offer, which is subject to our written confirmation
VII. CANCELLATION OF P.O.
i. Charges shall apply to recover the actual cost incurred.
VIII. OUT OF SCOPE
i. Supply of Electricity and Water during construction.
ii. Covid-19 Protocol Requirement.
iii. Security Service.
iv. Staging Area/Warehouse/Fabrication Area.

We hope that you find our foregoing proposal satisfactory and within your requirements.

Thank you for this opportunity to quote and we look forward to serving you in this project.

Should you find the foregoing terms and conditions acceptable, we shall be glad to receive a copy of this
proposal with your signature on the space provided for below and on the other pages of this proposal
which we will consider as your acceptance of this proposal and notice to proceed to work.

Very truly yours,

ENGR. RIZA JORDAN


Founder Saiko Builders

ENGR. JOHN MARK EVANGELISTA


CO – Founder Saiko Builders

Approve and accepted by,

General Contractor/Client
Contact no. : (0977) 231 4217
Email : saiko.builders@gmail.com
PROGRAM OF WORK

Name of Project : Aviation Concepts Technical


Service Facility
Location : SUBIC BAY AIRPORT

Appropriation : Php 5,102,000.00 No. of Calendar Days : 90

ITEM TYPE OF WORK TO BE DONE % OF


NO. FOR ALLOTMENT TOTAL
I. General Requirements 8.88%
II. Roofing Works 91.12%

TOTAL 100.00%
DETAILED ESTIMATE OF PROPOSED WORK
ITEM
DESCRIPTION QUANTITY AMOUNT
NO.
I. General Requirements SEE ATTACHED ESTIMATE SHEET P 390,500.00
II. Roofing Works SEE ATTACHED ESTIMATE SHEET P 4,007,643.82

TOTAL P 4,398,143.82

Estimated Direct Cost P 4,398,143.82


OCM (9% of EDC) P 395,832.94
Profit (7% of EDC) P 307,870.07

TOTAL P 5,101,846.83
SAY P 5,102,000.00

Programmed by: Checked by: Approved by:

ENGR. JOHN MARK EVANGELISTA ENGR. RIZA JORDAN


CO – Founder Saiko Builders Founder Saiko Builders
10/25/21 10/25/21
Project : Aviation Concepts Technical Service Facility
Subject : TRUSS AND ROOF LABOR AND MATERIALS QUOTATION
Location : SUBIC BAY AIRPORT

Item no. Description Quantity Unit Unit Price Total Price


I. General Requirements
A. Mobilization & Demobilization
1.0 Within 68KM (Office to Site)' 3 Months PHP 10,000.00 PHP 30,000.00
2.0 Barracks 1 lot PHP 110,000.00 PHP 110,000.00
B. Implementation of Construction of Safety and Health Program
Health and Safety Program PHP -
1.0 First Aid Kit 2 set PHP 750.00 PHP 1,500.00
2.0 Safety Officer 3 Months PHP 18,000.00 PHP 54,000.00
3.0 Site Engineer 3 Months PHP 25,000.00 PHP 75,000.00
4.0 Workers PPEs 15 person PHP 2,500.00 PHP 37,500.00
5.0 Scaffoldings 1 lot PHP 30,000.00 PHP 30,000.00
C. Communication
1.0 Communication (Telephone, Cellphone, Internet) 1 lot PHP 2,500.00 PHP 2,500.00
D. Tools and Equipment 1 lot PHP 50,000.00 PHP 50,000.00
Sub-total (General Requirements) PHP 390,500.00
II. Roofing Works
A. Roof Frame
1.0 L-Bar 60mm x 60mm x 6mm 9523.04 kg PHP 70.00 PHP 666,612.65
2.0 C-Purlins 2" x 6" x 1.5mm (Including 12mm Sag Rod) 7428.65 kg PHP 70.00 PHP 520,005.26
3.0 Anchor Plates (including bolts) 1238.10 kg PHP 70.00 PHP 86,666.67
4.0 Painting Works 1.00 lot PHP 80,000.00 PHP 80,000.00
5.0 Consumables (Paint Thinner, Paint Roller, etc) 1.00 lot PHP 20,000.00 PHP 20,000.00
B. Long-Span
1.0 Pre-painted - Rib-type GA 24 Roofing Sheet 1996.50 sq.m PHP 900.00 PHP 1,796,846.11
2.0 Pre-painted - Wall Flashing GA 24 119.68 lnm PHP 890.00 PHP 106,515.20
3.0 Pre-painted - Edge flashing GA 24 63.31 lnm PHP 890.00 PHP 56,347.77
4.0 Pre-Painted - Roof Gutter with Metal Frame Support 119.68 lnm PHP 950.00 PHP 113,696.00
5.0 PVC Downspout 1.00 lot PHP 80,000.00 PHP 80,000.00
6.0 Consumables (Sealant, Text Screw, Blind Rivet) 1.00 lot PHP 23,000.00 PHP 23,000.00
C. Wall Cladding
1.0 C-Purlins on Metal Wall Frame 247.54 sq.m PHP 1,550.00 PHP 383,691.32
2.0 Painting Works 495.09 sq.m PHP 150.00 PHP 74,262.84
3.0 Consumables (Paint Thinner, Paint Roller, etc) 1.00 lot PHP 12,000.00 PHP 12,000.00
Sub-total (Roofing Works) PHP 4,007,643.82

Sub-total : PHP 4,398,143.82

Prepared by: Checked by :


ENGR. Vidal Aquino ENGR. JOHN MARK EVANGELISTA
Project Estimator CO – Founder Saiko Builders
10/25/21 10/25/21