WEEKLY REVIEW (11.1.

19)
AUDITOR HOUSE
REVISED SCHEDULE
DATE OF
S.NO DESCRIPTION REMARKS
COMPLETION
1 SECOND FLOOR
1.1 Brickwork - Balance completed completed
1.2 Wall Plastering work completed completed
1.3 Toilet - Plumbing work completed completed
1.4 Toilet - wall dado work - balance (20%) 15-May-18 completed
1.5 Toilet - Floor tile laying work - balance (10%) 20-May-18 completed
1.6 Main Flooring completed completed
1.7 Kitchen & utility - Plumbing completed completed
1.8 Kitchen & utility - Electrical completed completed
1.9 Balcony - brick jelly laying work 10-May-18 completed
1.10 Utility & Balcony Flooring work 20-May-18 completed
1.11 Utility wall dado work 20-May-18 completed
work to be done
1.12 Kitchen - Cooking platform & sink completed
after interior
work to be done
1.13 Kitchen - wall dado work completed
after interior
1.14 Fenesta Window Fixing work completed completed
1.15 Window Grill Fixing work 28-May-18 completed
Door shutter
1.16 Doors Shutters & Fittings Fixing work interior scope
completed
Electrical Wiring & Switches fixing (after fixing
1.17 21-May-18 completed
temporary main door
1.18 First Coat Primer work 20-May-18 completed
ready for handing
1.19 Handing over to wood work completed
over
after interior work Sanitary Fixing
1.20 CP & Sanitary fittings fixing
completion completed
2 THIRD FLOOR
2.1 Brickwork - Balance (10%) 20-May-18 completed
2.2 Wall Plastering work - Balance (10%) 20-May-18 completed
2.3 Toilet - Plumbing work completed completed
2.4 Toilet - wall dado work - balance (10%) 25-May-18 completed
2.5 Toilet - Floor tile laying work - balance (10%) 25-May-18 completed
2.6 Main Flooring - balance (10%) 25-May-18 completed
2.7 Kitchen & utility - Plumbing completed completed
2.8 Kitchen & utility - Electrical completed completed
2.9 Utility & Balcony Flooring work - balance (10%) 25-May-18 completed
2.10 Utility wall dado work 25-May-18 completed
work to be done
2.11 Kitchen - Cooking platform & sink completed
after interior
DATE OF
S.NO DESCRIPTION REMARKS
COMPLETION
work to be done
2.12 Kitchen - wall dado work completed
after interior
2.13 Fenesta Window Fixing work 25-May-18 completed
2.14 Window Grill Fixing work 30-May-18 completed
Door shutter
2.15 Doors Shutters & Fittings Fixing work interior scope
completed
Electrical Wiring & Switches fixing (after fixing
2.16 31-May-18 completed
temporary main door
2.17 First Coat Primer work 30-May-18 completed
2.18 Handing over to wood work 30-May-18 completed
after interior work Sanitary Fixing
2.19 CP & Sanitary fittings fixing
completion completed
3 FIRST FLOOR

3.1 Brickwork - Balance in living balcony (5%) 15-May-18 completed


Wall Plastering work - Balance in living balcony
3.2 15-May-18 completed
(5%)
3.3 Bed (kids) - ceiling plastering work 20-May-18 completed
3.4 Toilet - Plumbing work completed completed
3.5 Toilet - wall dado work 25-Jun-18 completed
3.6 Toilet - Floor tile laying work 25-Jun-18 completed
3.7 Main Flooring - balance (10%) 30-May-18 completed
3.8 Main Flooring - polishing 31-May-18
3.9 Kitchen & utility - Plumbing completed completed
3.10 Kitchen & utility - Electrical completed completed
3.11 Balcony - brick jelly laying work 10-May-18 completed

3.12 Utility & Balcony Flooring work 25-Jun-18 completed

3.13 Utility wall dado work 25-Jun-18


work to be done
3.14 Kitchen - Cooking platform & sink completed
after interior
work to be done
3.15 Kitchen - wall dado work completed
after interior
3.16 Fenesta Window Fixing work - balance (10%) 25-May-18 completed
3.17 Window Grill Fixing work 28-May-18 completed
to be done after
3.18 Main door frame work completed
pooja
3.19 Balcony door frame work (1no) 20-May-18 completed

3.20 Doors Shutters & Fittings Fixing work interior scope


Electrical Wiring & Switches fixing (after fixing Electrical Wiring
3.21 10-Jun-18
temporary main door completed
3.22 First Coat Primer work 30-Jun-18
DATE OF
S.NO DESCRIPTION REMARKS
COMPLETION
wood work is in
3.23 Handing over to wood work 30-Jun-18
progress
after interior work
3.24 CP & Sanitary fittings fixing
completion

4 Head room Brick work & Plastering - balance completed

5 COMMON AREA WORKS


5.1 External Plastering works - Balance (20%) 31-May-18 completed
5.2 Terrace Weathering course works 25-May-18 completed
5.3 All Floor Lift - Front brick wall & plastering 20-May-18 completed
5.4 Staircase outer wall brickwork (3rd floor) 23-May-18 completed
5.5 Staircase outer wall plastering (3rd floor) 25-May-18 completed
Staircase Flooring works - balance (3rd & terrace
5.6 31-May-18 completed
floor)
5.7 Staircase Handrail fixing work 15-Jun-18
5.8 Lift erection work 30-Jun-18 completed
5.9 Lift Wall Cladding works 30-Jun-18 completed
Outer Plumbing - Duct line works & ring main
5.10 10-Jun-18 completed
system
5.11 Car park Flooring works 15-Jun-18 completed
5.12 Outer scaffolding removing 20-May-18 completed
5.13 Drops - WPC Fixing works 10-Jun-18 completed
5.14 Duct Covering works 15-Jun-18 completed
5.15 Compound wall work 10-Jun-18 completed
5.16 Gate fixing work 15-Jun-18 completed
5.17 Stilt floor additional room
5.18 Paving block work 30-Jun-18 completed
5.19 Landscape work 30-Jun-18
5.20 DG Platform 30-Jun-18 completed
DG platform
5.21 Genset erection
completed
5.22 Elevation Features work 10-Jun-18
5.23 Common area light fittings 30-Jun-18
5.24 External 1st coat painting 30-Jun-18 completed
5.25 Stilt floor - Ceiling Plastering 25-May-18 completed
5.26 Outer Chamber work 25-May-18 completed
C.C Obtained