AUDITOR HOUSE
REVISED SCHEDULE
DATE OF
S.NO DESCRIPTION REMARKS
COMPLETION
1 SECOND FLOOR
1.1 Brickwork - Balance completed completed
1.2 Wall Plastering work completed completed
1.3 Toilet - Plumbing work completed completed
1.4 Toilet - wall dado work - balance (20%) 15-May-18 completed
1.5 Toilet - Floor tile laying work - balance (10%) 20-May-18 completed
1.6 Main Flooring completed completed
1.7 Kitchen & utility - Plumbing completed completed
1.8 Kitchen & utility - Electrical completed completed
1.9 Balcony - brick jelly laying work 10-May-18 completed
1.10 Utility & Balcony Flooring work 20-May-18 completed
1.11 Utility wall dado work 20-May-18 completed
work to be done
1.12 Kitchen - Cooking platform & sink completed
after interior
work to be done
1.13 Kitchen - wall dado work completed
after interior
1.14 Fenesta Window Fixing work completed completed
1.15 Window Grill Fixing work 28-May-18 completed
Door shutter
1.16 Doors Shutters & Fittings Fixing work interior scope
completed
Electrical Wiring & Switches fixing (after fixing
1.17 21-May-18 completed
temporary main door
1.18 First Coat Primer work 20-May-18 completed
ready for handing
1.19 Handing over to wood work completed
over
after interior work Sanitary Fixing
1.20 CP & Sanitary fittings fixing
completion completed
2 THIRD FLOOR
2.1 Brickwork - Balance (10%) 20-May-18 completed
2.2 Wall Plastering work - Balance (10%) 20-May-18 completed
2.3 Toilet - Plumbing work completed completed
2.4 Toilet - wall dado work - balance (10%) 25-May-18 completed
2.5 Toilet - Floor tile laying work - balance (10%) 25-May-18 completed
2.6 Main Flooring - balance (10%) 25-May-18 completed
2.7 Kitchen & utility - Plumbing completed completed
2.8 Kitchen & utility - Electrical completed completed
2.9 Utility & Balcony Flooring work - balance (10%) 25-May-18 completed
2.10 Utility wall dado work 25-May-18 completed
work to be done
2.11 Kitchen - Cooking platform & sink completed
after interior
DATE OF
S.NO DESCRIPTION REMARKS
COMPLETION
work to be done
2.12 Kitchen - wall dado work completed
after interior
2.13 Fenesta Window Fixing work 25-May-18 completed
2.14 Window Grill Fixing work 30-May-18 completed
Door shutter
2.15 Doors Shutters & Fittings Fixing work interior scope
completed
Electrical Wiring & Switches fixing (after fixing
2.16 31-May-18 completed
temporary main door
2.17 First Coat Primer work 30-May-18 completed
2.18 Handing over to wood work 30-May-18 completed
after interior work Sanitary Fixing
2.19 CP & Sanitary fittings fixing
completion completed
3 FIRST FLOOR