2.3.

4: Progress Up to 8th IPC


Villa No ( 191 194 , 63 68, 69 74 )

Sort By Handing Over

18 villas

Internal Works

Tile work Complete


Marble Work Stairs Complete, Threshold in Progress, Kitchen Top & Vanities Remaining
Door Frames are fixed 187-197
Wood Work 187-198 ( 90 % done ) In 198 in Progress
Wire pulling in Progress ( 80 % done )
Garage services ( 5 Villas Complete ) 5 Villas Remaining
Lagging ( 7 Villas Complete ) In villa 198 in Progress
G.I Ducting ( 70 % done ) Inline fans & Necking remaining
False ceiling ( Framing is done ) Due to ducting uncompleted sheets cannot be placed
wall putty & single coat at walls is done
External Paint in Progress at villas 197-200
External Works
Boundary Wall Concrete & Masonry is done ( 80 % ) only partition wall of 2 villas (190 &197 ) Remaining
Plaster & Coping of Boundary wall Remaining
Insulated tiles ( 7 villas complete ) Remaining in Progress
All external developments remaining

These Villas will be ready to handing over by 1st March 2013