Sr.

Component This month Targets as claimed in Achieved During this month This Month Targets Missed New Targeted Micro Milestones for next
No Previous MPR month

1 GIRLS HOSTEL • Granite for ground floor will be • Granite for ground floor completed 90% • Ground floor granite 10 • Granite flooring in first floor will be
completed • Parapet wall completed % Pending completed
• Parapet wall will be done • Inner plastering completed for first floor • Water tank pending • Mumty room brick work will be
• Inner plastering will be completed for • Mumty slab casting concrete done • Ground floor plumbing completed
first floor • Only chase cutting for Plumbing for ground pending • External plastering will be completed
• Mumty slab will be done floor done
• Plumbing for ground floor will be done • Connecting corridor f3 level completed
• Connecting corridor f3 level will be
done
• Water tanks will be done

2 BOYS HOSTEL • F3 level 100% brick work will be done • F3 level 70% brick work done • 30% F3 level brick works • Granite flooring in ground floor will be done
• Mumty slab will be done . • Mumty slab will be done pending • Mumty room brick work will be done
• Ground floor inner plastering will be • Ground floor inner plastering completed • Connecting corridor F3 • Internal plastering for both ground floor and
done pending first floor will be done
• Connecting corridor f3 slab will be done • Water tank pending
• Water tanks will be done
Sr. Component This month Targets as claimed in Previous Achieved During this month This Month Targets Missed New Targeted Micro Milestones for next
No MPR month

3 PRINCIPAL • Flooring will be done including toilets wall • Flooring will be done • water proofing will be completed
RESIDENCE: tiles including toilets wall tiles

4 Type III Quarters • F3 brick will be completed • F3 brick completed • 25% parapet wall pending • Brick work for mumty room will be done
(Block -1) • F3 level inner plastering will be done • F3 level inner plastering completed • External plastering will be done
• Parapet wall will be done • Parapet wall completed 75% • Plumbing in ground floor will be completed
• Mumty slab will be done • Mumty slab done
• Flooring for both ground floor and first floor
70 % completed

5 Type III Quarters • F3 brick will be completed • F3 brick completed • Parapet wall pending • Brick work for mumty room will be done
(Block -2) • F3 level inner plastering will be done • F3 level inner plastering completed • External plastering will be done
• Parapet wall will be done • Mumty slab done • Plumbing in ground floor will be completed
• Mumty slab will be done • Flooring for both ground floor 70 % • Flooring of First floor to be completed
completed

6 Type II Quarters • F2 level slab reinforcement and concrete • F2 level slab reinforcement and concrete • Ground floor brick work will • F3 slab shuttering and reinforcement with
will be done completed be done concrete will be done
• Ground floor brick work will be done • F3 level columns completed • F4 level columns casting will be done
• Ground floor ceiling and brick work will be
completed

7 External • Connecting paths residential Qtrs • Connecting paths residential Qtrs


Development • Connecting paths Hostels • Connecting paths Hostels
• Sewer lines
• Septic tank