WORK REPORT OF BLOCK 'C' AT DIFFERENT FLATS .

DATE : - 09-MAR-2020
DESCRIPTION FLOOR 1
FLAT NO FN 101 FN103 FN102 FN104 FN105 REMARKS
1 balcony floor + 2 balcony floor + Balcony tile work was pending due
1. Tile work done skirting left skirting left done to plumbing work .
2. paint work done done done done
3. Electrical pipe & wiring work done done done done Putting repair at modular box area.
4. plaster and repair work done done done done
5. cistern & divertor fitting . done done done done
6. water proofing at bathroom done done done done
7. MCB DB fitting done done done done
8. Tiles work for servent quarter. done done done done tile skirting work left at ser.quater.
9. Railing of Balcony done done done done
10. water proofing for bathroom. done done done done
11. PCC for flats done done done done
12. PCC for bathroom done done done done
FLOOR 2
FN 201 FN202 FN203 FN204 FN205
1. Tile work done 1 Balcony left 1 balcony left 1 balcony left. done balcony tile work left due to water
supply their at FN202. And Also 1
2. paint work done done done done done bath tile work left due to support
3. Electrical pipe & wiring work done done done done done provided their for outer plaster.
4. plaster and repair work done 1 Balcony left done done done
5. cistern & divertor fitting . done done done done done
6. water proofing at bathroom done done done done done
7.MCB DB fitting done done done done done
8. Tiles work for servent quarter. done done done done done tile skirting work left at ser.quater.
9. Railing of Balcony done done 1 balcony left done done
10. water proofing for bathroom. done done done done done
11. PCC for flats done done done done done
12. PCC for bathroom done done done done done
FLOOR 3
FN 301 FN302 FN303 FN304 FN305
1. Tile work done 1 Balcony left 1 balcony left done done
2. paint work done done done done done
3. Electrical pipe & wiring work done done done done done
4. plaster and repair work done 1 Balcony left done done done
5. cistern & divertor fitting . done done done done done
6. water proofing at bathroom done done done done done
7.MCB DB fitting done done done done done
8. Tiles work for servent quarter. done not done x done not done x done tile skirting work left at ser.quater.
9. Railing of Balcony done done 1 balcony left done done
10. water proofing for bathroom. done done done done done
11. PCC for flats done done done done done
12. PCC for bathroom done done done done done
FLOOR 4
FN 401 FN402 FN403 FN404 FN405
1. Tile work done done 1 balcony left. done done lift side balcony pending.
2. paint work done done done done done
3. Electrical pipe & wiring work done done done done done
4. plaster and repair work done 1 Balcony left done done done
5. cistern fitting for bathroom done done done done done
6. water proofing at bathroom done done done done done
7.MCB DB fitting done done done done done
8. Tiles work for servent quarter. not done x not done x not done x not done x not done x
9. Railing of Balcony done done 1 balcony left. done done
10. water proofing for bathroom. done done done done done
11. PCC for flats done done done done done
12. PCC for bathroom done done done done done
FLOOR 5
FN 501 FN502 FN503 FN504 FN505
1. Tile work 3 balcony left 3 balcony left 3 balcony left 2 balcony left 2 balcony left Balcony tile flooring left due to
scaffolding for outer plaster.
2. paint work done done done done done
3. Electrical pipe & wiring work done done done done done
4. plaster and repair work done 1 Balcony left done done done
5. cistern fitting for bathroom done done done done done
6. water proofing at bathroom done done done done done
7. MCB DB fitting done done done done done
8. Tiles work for servent quarter. not done x not done x not done x not done x not done x
9. Railing of Balcony done done 1 balcony left. done done
10. water proofing for bathroom. done done done done done
11. PCC for flats done done done done done
12. PCC for bathroom done done done done done
FLOOR 6
FN 601 FN602 FN603 FN604 FN605
1. Tile work 3 bathroom left 3 bathroom left 3 bathroom left 3 bathroom left 3 bathroom left
2. paint work done done done done done
3. Electrical pipe & wiring work done done done done done
4. plaster and repair work done done done done done
5. cistern fitting for bathroom done done done done done
6. water proofing at bathroom done done done done done
7.MCB DB fitting not complete not complete not complete not complete not complete
8. Tiles work for servent quarter. not done x not done x not done x not done x not done x
9. Railing of Balcony done done 1 balcony left. done done
10. water proofing for bathroom. done done done done done
11. PCC for flats done done done done done
12. PCC for bathroom done done done done done
FLOOR 7
FN 701 FN702 FN703 FN704 FN705
1. PCC done Done done done done
2. Electric pipe fixing work(Flats) done done done done done
3. Electric pipe fixing work for done done done done done
bathroom
4. Wiring work done done done done done
1 bath left done 2 bath left done done
5. plaster work

6.paint work done done done done done


7. Tile work 3 bath left 3 bath left 3 bath left 3 bath left 3 bath left Bathroom tile work left.
8. Railing of Balcony done done 1 balcony left done done
9. water proofing for bathroom. done done done done done
10. PCC for bathroom
done done done done done
11. cistern fitting work not done x not done x not done x not done x not done x
12. mcb DB fitting not done x not done x not done x not done x not done
FLOOR 8
FN 801 FN802 FN803 FN804 FN805
1. PCC done done done done done
2. Electric pipe fixing work(Flats) done done done done done
3. Electric pipe fixing work for
bathroom 1 bath left not done x done done 1 bath left.

4. Wiring work 1 bath left done done done 1 bath left.


2 bath left 3 bath left 1 bath 3 bath left 2 bath left 805 :-plaster repairing for modular
5. plaster work box .

6.paint work done done done done done 802 - duct wall brickwork left
7. Tile work 3 bath left not done x 3 bath left 3 bath left not done x
8. Railing of Balcony done done 1 Balcony left done done 801- kids room waste removal
9. water proofing for bathroom. (previous lift side )
done done done done done
10. PCC for bathroom not done x not done x not done x not done x done
11. cistern fitting work not done x not done x not done x not done x not done x
12. mcb DB fitting not done x not done x not done x not done x not done
FLOOR 9
FN 901 FN902 FN903 FN904 FN905
1. PCC 2 balcony left 2 bath left done done done
2. Electric pipe fixing work(Flats) done done done done done
3. Electric pipe fixing work for module box not bathroom modular box not fixed.
bathroom not done x fixed done not complete not complete
4. Wiring work done done done done done
5. plaster work 1 bath left done done done done Brickwork left at dressing FN 902
6.paint work done done done done done one brick plaster repair at FN
7. Tile work 901 , 902,903,904.
not done x not done x not done x not done x not done x
8. Railing of Balcony done done 1 balcony left done done
9. water proofing for bathroom. 1 bath left done done done done 902 - duct wall brickwork left
10. PCC for bathroom 1 bath left 1 bath left done done done
11. cistern fitting work not done x not done x not done x not done x not done x
12. mcb DB fitting not done x not done x not done x not done x not done
FLOOR 10
FN 1001 FN1002 FN1003 FN1004 FN1005
1. PCC not done x not done x not done x done not done x FN1001 - Kids room need removal of
not done x not done done done not done x waste ( previous lift side ). Pcc
2. Electric pipe fixing work(Flats) pending.
3. Electric pipe fixing work for
bathroom not done x not done x not done x not done x not done x
4. Wiring work not done x not done x not done x not done x not done x
5. plaster work 1004 - Duct brickwork incomplete.
3 bath left done 3bath+1balcony left incomplete done
6.paint work not started in progress not started not started not started
7. Tile work
not started not started not started not started not started lobby walls plaster left
8. Railing of Balcony done done 1 left done done
9. water proofing for bathroom. 1 bath left done done done done
10. PCC for bathroom not done x not done x not done x not done x not done x
11. cistern fitting work not done x not done x not done x not done x not done x
12. mcb DB fitting not done x not done x not done x not done x not done
FLOOR 11
> plaster work for water tank and lift room done.
> Terrace closing duct walls not plastered.
> steel extra bars of column ( parapet wall ) requires cutting .