ZEOLITE -VBF PROJECT ACTIVITIES REPORT 29-08-2023 11:00 hr.

MANPOWER 29/08/2023
SR.NO. ACTIVITIES AS PER SCHEDULE ACTIVITIES AS PER ACTUAL DEPT REMARKS SRE DELIGHT SS LAGACY M-TECH
works
1 Vacuum pump foundation 1&2 completed civil completed.
2 vacuum pump 1 &2 civil work . completed civil completed.
3 Vacuum Pump 3&4 civil work completed civil concrete foundation work completed.
4 Cooling Water Sump completed Civil bottom and all four wall civil work completed/Top chakkar plate lid and pump bay structure to be done.
5 CW trench Civil Work completed civil 300 mm width x4 inch depth -connecting to cw sump. - trench work completed
6 ZP08 A/B foundation completed civil completed
7 Extended platform 2 columns concrete foundation pile capping completed civil extension 7 mtr concrete foundation pillar with grouting bolt -completed
8 Heat exchanger Platform completed mechanical completed
9 Heat exchanger erection completed mechanical completed
10 Low alkali vessel V08 position and nozzle modification. under progress mechanical nozzle orientation completed but dip pipe from nozzle under progress. 13 14 10 7
11 Wash water vessel V09 erection completed mechanical completed
12 Wash water vessel V09 nozzle modification under progress mechanical nozzle orientation completed but dip pipe from nozzle under progress.
13 ZP08 A/B erection completed mechanical up to pipeline work completed
14 Vacuum pump (1,&2) erection under progress mechanical pipeline work under progress from pump nozzle suction.
15 Wet cake hopper re orientation completed mechanical completed
16 Erection of 30m3 slurry pump completed mechanical pump/motor placed and grouting also done. Discharge line modification completed to join crystallizer area with ZV10B old line.
17 ZV08 & ZV09 dip line from VBF 3x3 no's pipe line nozzle under progress mechanical to be connected to VBF after receiving
18 Moisture separator under progress mechanical fixed in bay structure and nozzle work under progress
19 DCS Modification under progress instrument Graphic work under progress.
20 ZP08 A/B (ZV09) completed mechanical Re-circulation line to ZV09 fixed & Transfer to evaporation ATH Pipe line connecting work completed
21 ZP04 A under progress mechanical Slurry discharge line work in progress.
22 PGL line from ZT02 to ZE01 cooler completed mechanical PGL line to cooler line modification work under progress.
23 ZE01 cooler jacket cooling water line completed mechanical inlet & outlet pipe line work completed.
24 Silicate line from ZT01A/B to ZE02 cooler completed mechanical product line and cooling water line for inlet & outlet completed
25 27.25 MTR level VBF filter elevation outside extension 4th Bay structure work under progress. under progress mechanical under progress
MAJOR PENDING WORK
1 VBF erection pending mechanical receiving pending
2 VBF pipeline work after receiving pending mechanical pending
3 Vacuum pump 1&2 - Vacuum trap and pipeline work pending mechanical pending
4 27.5 meter level VBF elevation- 4th Bay Structure work pending mechanical under progress
5 Cooling Water Sump top lid - checker plate work pending mechanical pending
6 All new pump electrical work pending Electrical pending
7 Electrical Pneumatic panel for VBF pending Electrical pending
8 All new pump Pressure gauge work after pump erection pending instrument pending