Professional Documents
Culture Documents
SCOPE OF WORKS
1. The works cover the requirements for the fabrication, installation, painting,
cleaning, testing and commissioning of water line at Kuantan Bulking
Installation (KBI) in accordance with the drawings and specifications
provided.
v. GENERAL
1
vi. DELIVERY PERIOD
To be advised by Supplier. Preferably not more than one (1) month from
date of order.
After the pumpsets installed by the employer the supplier must testing
and commissioning the pumpsets at the employer sites to the satisfaction
of the employer.
viii. GUARANTEE
1. The works cover the requirements for supply of labour, materials, hand
tools and all else necessary equipments to carry out supply and install
work of two (2) unit vertical multistage centrifugal pumpset in KBI area.
The works shall be completed with the modification and installation of
new piping, fittings, y-strainer, expansion joints and valves as per
drawings attached and engineer’s instruction.
1. Scope of works:
3
e. Installation of one (1) nos. 75mmØ sch10 stainless steel water
pipelines from header to Pumphouse B at Kuantan Bulking
Installation (KBI) complete with fittings, valves, pipe supports,
concrete footing, etc as shown in the Drawing No:
KBI/WATERLINE/01/2021, KBI/WATERLINE/02/2021,
KBI/WATERLINE/03/2021 and KBI/WATERLINE/04/2021.
j. All the necessary pipe shoes, supports and materials required for the
complete installation of the above system shall be provided by the
Contractor.
2. All piping works including valves, fittings and supports indicated on the
drawings shall be installed. Pipe supports are to be provided in
accordance with the Employer’s specifications as shown in the drawings
or if not specified to be specified by the Contractor. The Contractor is
to supply details of pipe supports specified by them for approval by the
Employer.
4
4. The Contractor shall then test and commission the water pipeline. The
work is including of proper handover, manpower support until
completion.
7. Stainless steel panel box are include stainless steel panel lock.
8. Tagging, labeling and numbering of panel box, cables and etc. with
appropriated material are included in this quotation.
10. The Contractor shall provide all welding materials, bolts and nuts,
jointings and gasket, plants and all other materials such as pipes,
valves, fittings, nipples, unions, etc. which are required for the
completion of the works as stated above.
11. The Employer shall supply the Contractor with the sizes and quantity of
material i.e. pipes, valves, fittings and etc.
12. The Contractor is advised to measure and check the quantity of pipes,
fittings and materials required as the quantity of materials to be supplied
by the Employer is only an estimate of the actual requirement. The
Contractor is also advised to visit the site to check for himself the extent
of works required and to clarify with the Employer all doubts and
uncertainties before submitting his quotation.
13. The Contractor shall provide all the other necessary materials, tools,
plant and any other equipment which would be required for proper
execution and completion of the Works as stated in Clause 1.
16. Once the Contractor has taken delivery of the material, he shall be
responsible for the material and shall, in the joint name of the employer
and Contractor insure with an insurance Company the material up to
the value of its market price against loss, damage or destruction by fire,
5
lightning, earthquake and theft from the date of delivery to the date on
which the Works is accepted by the Employer.
17. The Contractor shall be responsible for the handling and delivery of the
material to site once he has taken delivery of the materials from the
Employer.
18. The Contractor shall bear all expenses in the cutting of materials
supplied by the Employer to suitable lengths for transportation from the
Employer’s designated stored to the site.
19. After completion of site work, the Contractor shall clean up the site and
remove all debris resulting from his work and leave the area in a
condition that is acceptable to the Engineer.
20. The contractor should visit the site in his own interest and seek any
clarification he needs to enable him to submit a realistic offer, as once
the quotation has been accepted, no variation from the drawing will be
considered, unless specifically authorized in writing by the Engineer and
no claims for extras will be entertained.
1.1. Standards
The ends of the pipes shall be beveled for joining and butt welding in
accordance to the relevant standards for pipe installation.
6
1.3. Welding Seam of Stainless Steel Pipes and Fittings
The height of the internal welding seams for the welded pipes and fittings
shall not exceed 0.3mm.
The internal welding seams shall be factory rounded off and smoothened if
their height exceeds 0.3mm as pigging operation of pipes are required.
All pipes and fittings that do not comply with the above specification will be
rejected.
1.4.1 All standards and related specifications shall be of the latest issue
date and shall include all addenda, revisions and supplements
thereto.
1.4.2 U-bolts for pipe sizes 75mm N.B. and below shall be fabricated from
8mm dia. solid round rods and hot-dipped galvanized.
2.1 Pipeline shall be erected in as neat and orderly a manner (in groups or banks
wherever applicable) as is consistent with satisfactory supporting
arrangements for easy operation and maintenance. All piping equipment and
fittings requiring regular attention of the operating and maintenance
personnel shall be made readily accessible. Also, adequate clear working
spaces shall be provided around the equipment which requires frequent
servicing.
2.2 The fabrications and erection of the pipes and fittings shall be in accordance
with the following standards :-
2.3 All standards and related specifications shall be of the latest issue date and
shall include all addenda, revisions and supplements thereto.
7
2.4 All conflicts between requirements for this specifications and related
standards and drawings shall be referred to the Employer for clarification in
writing prior to the purchasing and processing of materials and the
installation of the materials.
2.5 Unless otherwise indicated on the Drawings, all pipe to pipe joints shall be
butt welds. Single fillet weld sleeve joints are not permitted. All pipe ends
shall be properly prepared for butt joinings.
2.6 Branches provided by the Employer shall either be screwed or butt welded
fittings. The Contractor shall grind the internal bores of the branches and
tees to a taper to match their bores with those of the adjoining pipes prior to
joining. Where the branches are not supplied for the construction of pipeline
where pigging operations are not carried out, the Contractor shall fabricate
the branches with pipes supplied by the Employer. Those fabricated
branches shall be properly reinforced in accordance with the requirements of
applicable standards and shall be the “set on” type. The branch pipe shall be
prepared so as to permit full penetration welds. Preparation of welding
technique and cutting shall be in accordance with applicable standards. The
minimum angle of branches shall be 45 degrees but angles of 90 degrees is
preferred.
On 200mmØ and 250mmØ pipelines used for handling vegetable oil where
pigging operations are carried out, branches shall only be fabricated from
standard butt-welding fittings.
2.8 Slip-on flanges shall have their bores machined to match the external
diameter of the pipe. Flange bolt holes shall not exceed 1/32” of the bolt
diameter. Welding neck flanges shall have their bores machined to match the
nominal inside diameter of the pipe and shall have ends prepared suitable for
welding.
2.10 The Contractor shall ensure that before all pipes to pipes or pipes to fittings
are welded together, the butt welding ends are properly beveled. Where end
beveling is required, the bevel shall be shaped by machine or other approved
shaping methods to obtain a reasonably smooth surface suitable for welding
and free from tears, shear drags, scale and grease. All welding faces and
adjoining surfaces for the distance of at least ¼” from the edge of the
welding groove shall be thoroughly cleaned before jointing.
2.11 After fabrication, all loose scales, weld spatter, slag, sand and other foreign
material shall be removed from the piping.
8
2.12 Weld defects may only be repaired with the written permission of the
Engineer. All defects shall be removed by flame or arc grouting, grinding,
chipping or machinings. All repair welds shall be preheated and postheated
as originally required and the basic principle of the same welding procedure
initially used shall be employed as far as possible. All repairs shall be at the
Contractor’s expense and the defective piece shall be retested in accordance
with the provision of these specifications.
2.13 Should any pipe be required to be bent or formed, it shall be done by any hot
or cold method permissible by radii and material characteristics of the pipe
being bent. It may be bent to any radius which will result in a bent arc
surface which is free of cracks and substantially free of buckles. Pipe bends
shall have a smooth curve with a minimum ovality of thinning. Differences
between diameter measured on major or minor axes shall not exceed 5% of
the outside diameter of the pipe. Wall thickness of the pipe after bending
shall not be less than 87½% of the nominal wall thickness.
2.14 For screwed pipework, extreme care shall be taken to avoid overtightening of
screwed joints during installation.
2.15 All sections of welded pipe shall be closed by use of a night cap when not
being worked on or at the end of each day’s work or on the occasion of any
stoppage of work to prevent entrance of small animals or foreign matter and
shall not be re-opened until work has resumed.
2.16 Oil resistant gasket such as Tombo No. 1000 or equivalent approved type
shall be used. The gaskets shall be able to withstand services temperature up
to 150 deg F and pressures up to 150 psi saturated steam. Nicks, dents or
gouges on the flange surfaces are to be avoided to enable the gasket to
provide a good seal.
2.17 Basket strainers with stainless steel screen fabricated from stainless steel
perforated sheet shall be supplied as per drawing provided. The strainer shall
have baskets which are easily removable for cleaning. The maximum clear
opening of the screens shall be 3mm.
3. Weldings
3.1 Unless otherwise ordered, welding and heat treatment shall be in accordance
with BS 2971 as appropriate for the pressure and temperature to which the
pipe will be subjected to. Best quality electrodes with filler material suitable
for the pipe material joints shall be used at all times and their makes shall be
employed and shall have previously undertaken selected tests as described in
BS 2971. Quality welding requirements shall be maintained throughout the
contract.
3.3 The following requirements and dimension shall apply to preparation and
weld runs :-
3.3.1 In all cases, the fusion passes shall be smooth, free from defects and
together with the adjoining pipes shall be thoroughly cleaned, free
from all scale, rust, oil, grease, paint or other foreign matter.
9
3.3.2 Butt welding reinforcement shall be uniform and not less than 1/16”
or more than 1/8” in heights and shall merge smoothly into the pipe
surface without undercut.
3.3.4 Root penetration shall not exceed 1/16” for all pipes.
3.3.5 Initial root runs shall not show lack of penetration or non fusion.
3.4 Parts to be jointed together shall be carefully aligned and tack welded
together so that the final welded assembly will conform to the required
dimensions within reasonable tolerances. Tack welds of sufficient number
and suitable proportions to hold the parts in space during ordinary handling
shall be made. Small tack welds i.e. between ½” to ¾” in length penetrating
to the bottom of the groove and free from cracks and other deposition faults
may be included in the first pass provided they have been made by a qualified
welder with electrodes of the same quality required for the first pass.
3.5 The Contractor shall ensure the weld soundness on all layers of weld. All
welds shall be visually examined externally for faults and irregularities.
3.6 The Contractor shall exercise care in ensuring that successive layers of weld
are uniformly distributed around the joints to avoid excessive stress
concentration. Each layer of deposited weld shall be thoroughly cleaned
prior to the deposition of the following weld metal layer. Surface defects
found shall be chipped or ground out.
4.1 The internal bores of butt welded fittings, bends and tees used on the pipes
that require pigging shall be ground to a taper of 1 : 4 to ensure that the
bores of the fittings match the bores of the pipes at the joints.
4.2 On the pipes that require pigging, all equal tee and branch connections over
100mm NB are to have internal guide bars welded over the branch opening as
indicated on Drawing No. BPT/03/025. Guide bars shall be spaced not more
than 65mm apart.
4.3 Every weld in the pipes that require pigging shall be hand gauged. After each
additional length of pipe has been welded, it shall be gauged over its entire
length including the preceding circumferential and branch welds with a gauge
consisting of 2 steel discs rigidly fixed to a shaft of the following
dimensions:-
10
Diameter of Distance Between
Size
Steel Disc Disc
300mm NB 295mm 610mm
250mm NB 247mm 510mm
200mm NB 196mm 410mm
150mm NB 148mm 300mm
4.4 Pigging
4.4.2 The pipes shall be flushed with water until it is flowing from
the lines in a clean state.
4.4.3 A cleaning pig shall be passed through the water filled lines
using compressed air as the driving medium for at least three
passes with the cleaning pig bypass plug open, after which
the plug shall be closed and a minimum further three passes
made or until such time as the water being displaced shall be
in a clean condition and the foreign matter immediately
preceding the cleaning pig shall not exceed 25 gm.
4.4.4 The gauging pig shall then be passed through the water filled
lines using compressed air as the driving medium for at least
3 passes. The gauging pig shall pass through the line on 3
consecutive passes with not more than 10% variation on the
time taken from launching to receiving.
5. Threading
5.1 Unless specified to the contrary, pipe threads shall be male taper
threads. Threading of the pipes or attachments shall be done after
bending, forging or heat treatment but before testing. Threads shall
be concentric with the outside of the pipe and shall conform to BS21.
5.2 Threads shall be cut with new sharp dies to ensure good quality form
and finish.
11
5.3 Threaded joints shall be made up with Teflon (PTFE) jointing tape.
15mm wide tape shall be used for pipe sizes up to and including
50mm NB and 25mm wide for pipe sizes over 50mm NB.
6.1 All piping tests shall be witnessed and approved by the Engineer or
his representative.
6.5 The Engineer shall be responsible for the approval of all tests and in
addition, he may exercise his discretion in calling for any further
tests as may be required from time to time.
6.6 Where prefabricated piping has been shop tested and approved,
further system tests may be required in accordance with this
specification, at the discretion of the Engineer.
6.7 Prior to testing pipework, all loose foreign material such as scale,
sand, weld spatter, etc. shall be removed and all lines flushed clean.
6.8 All shop hydrostatic tests shall be made with clean water. Salt or
brackish water must not be used.
6.10 Steel piping generally shall be tested with water in accordance with
the code and test pressure of 1.5 times the designed operating
pressure subject to a maximum of 225 psig.
6.11 The compressed air system shall also be tested with water in
accordance with the above procedure.
6.12 The Contractor may, if he chooses, to carry out a preliminary air test
at not more than 25 psig pressure prior to the hydrostatic test to
locate major leaks.
12
6.13 The hydrostatic pressure test shall be maintained for a sufficient time
at the discretion of the Engineer to determine the leaks in the system.
6.15 All gaskets used as spades for closing off piping or equipment for the
testing or erection purpose shall be replaced by new materials for
commissioning.
7. Painting
7.2 Systems may be shop or site painted. However, for shop painted
system, all defects shall be touched up before handling over.
7.3 Any fees necessary for Statutory Approval e.g. Scaffolding, shall be
the Contractor’s responsibility.
7.4 All paint supplied and used by the Contractor shall be of good
quality and shall be stored in a dry place. No defective paint shall be
used.
7.5 Surfaces to be painted shall be dry and free from oil, grease, dirt and
rust and suitably prepared for application of paint to avoid any
likelihood of adhesion problems. Paint shall not be applied when the
Relative Humidity is 85% and above.
7.6 In all cases where parts will be inaccessible after shop assembly,
they shall be prepared and full system applied before assembly.
7.8 Where the shop painted coat has been damaged exposing the metal
surface, the Contractor carrying out the site painting shall rectify
same before handing over. The affected area shall be scraped and
edges of the damaged paint shall then be beveled with sandpaper.
The patches of new paint shall overlap the old by at least 50mm all
round.
7.9 All surfaces prior to painting shall be hand and power tool cleaned.
13
7.10 All deposits of oil, grease, dirt and foreign matters, fluxes and fume
deposits adjacent to weld runs, shall be removed by solvent cleaning
or fresh water washing.
7.12 Tools shall be used in such a way as to leave no burrs, sharp edges or
cuts on the surface. Excessive power wire brushing shall be avoided
as detrimental burnishing of the surface may occur.
7.13 All pipes and fittings shall be painted in accordance with the colour
scheme to be provided by the Engineer.
7.14 All pipes, fittings and supports shall be given two (2) coats of
epoxymastic paints of an approved quality at 100 DFT per coat,
followed by one (1) coat of polyurethane of an approved quality of
50 - 60 DFT per coat.
7.15 For underground pipings, in addition to two (2) coats of coal tar
epoxy paints of an approved quality at 125 DFT per coat, these
underground pipings shall be wrapped with one layer of DENSO
TAPE at all underground sections and up to a height of 0.5 metre
above ground level at both ends of the pipes when they exit from the
ground.
7.16 The following brands of paint is approved for usage in the above works
:-
KCC (Korea) - Koremastic 500/Koretane 300
Jotun (Sweden) - Jotamastic 87/Hardtop AS
Nippon (Japan) - Copon 8048/Nippon Polyurethane
7.18 In addition to visual inspection, each paint coat shall be tested for its
film thickness by means of a wet and/or dry film thickness gauge.
The tests shall be carried out at points nominated by the Engineer.
14
(E) SPECIFICATIONS OF VALVES AND GAUGES FOR TANKS AND
PIPELINES
1.1 Full Bore Stainless Steel and Cast Steel Gate Valves
Other specifications :
Stainless Steel 304 valve trim materials
Outside screw rising stem type
Solid wedge type
Maleable iron or steel handwheel
Other specifications :
Floating ball
Lever operation
Seat material shall be reinforced PTFE
Service rating of 100 psig compressed air at 50°C
15
Other specifications :
Valves operation with lever handle for 6ӯ size and below
and gear-operated for 8ӯ size and above
Seat material shall be reinforced PTFE
Full bore and suitable for pigging operation
Other specifications :
Stainless Steel 304 valve trim materials
Approved Brand : KITZ
Other specifications :
Other specifications :
Stainless Steel 304 gauge materials
Fluid medium – Palm Oil, vegetable oils & Biodiesel
Size ½” BSPT end connection
16
5.0 General
5.1 The valves specified and described under Clause 1.0, 2.0 & 3.0
above will be fitted in line pipes for conveyance of palm oil and
other vegetable oils. Line pipes will be of API 5L Grade ‘B’
Schedule 40 (STD) grade or ASTM A312 Grade 304 Schedule 10.
5.2 Bodies
All parts in contact with the fluid medium to be conveyed shall not
be made of copper or its alloy.
1. GENERAL
2. GENERAL CONSTRUCTION
All the switchboards indicated on the relevant drawings shall be suitable for
floor-mounting, free-standing or wall mounting as the case may be, dead-
fronted type, metalclad, cubicle board, fitted with the required number of
circuit breakers, isolators, switch fuses, fuse-switches, necessary instruments,
protection devices, indicating lamps, contactors, current transformer,
busbars, internal interconnected wiring, transformers, cable end-boxes and
all other items necessary to effect completion of the switchboards.
The switchboards shall each consist of the required number of sheet steel
enclosures for mounting all the items of electrical equipment and
components as required. The structural work of the cubicles shall comprise
welded or module type M.S. angles with boxes, cable glands, terminal blocks
and other relevant items. Each cubicles shall be enclosed on the front, sides,
rear and top with removable M.S. sheet panels of not thinner then the
following gauges :-
17
Front Panel : No. 12 SWG
Rear, Side & Top Panel : No. 14 SWG
3. BUSBAR
18
5. EARTH CONTINUITY
6. TERMINATIONS
7. LABELS
Black ivoring labels with white lettering engraved thereon (PVC, adhesive-
type labels shall not be accepted) shall be provided and fixed immediately
below or on panels of switching devices, stating details of the circuits
controlled by such devices. In addition, a main label with 25mm high
lettering engraved thereon and stating the designation of the switchboard
concerned, shall be provided and fitted on the top panel of each switchboard.
8. TROPICALISATION
Each switchboard with all its components shall be fully tropicalised and
suitable for used in an ambient temperature of 90 deg. Fahrenheit under very
humid, tropical conditions.
9. PAINTING
Each switchboard shall be well cleaned and derusted, after which it shall be
treated internally and externally with two (2) coats of an approved-type anti-
corrosive paint. The switchboard shall be finished with two (2) coats of
stove-enameled paint in matt-finish, dark battleship grey. After each
switchboard is delivered to the site and installed in position with the
connection of all incoming and outgoing feeder cables completed, all
scratched or chipped portions of paint work shall be resprayed with the same
colour finish in such manner as to present a clean surface, free from patches
or blemishes.
Prior to the delivery of each switchboard to the site, the switchboard shall be
tested at the Manufacturer’s Workshop in accordance with the requirements
of Jabatan Bekalan Elektrik Malaysia. The results of such tests shall be
submitted by the manufacturer to them for registration. The Contractor is
required to submit four (4) copies of the Manufacturer’s Tests Results,
together with four (4) copies of the Jabatan Bekalan Elektrik Malaysia letter
of registration of each switchboard, to the Engineers for distribution to the
various parties concerned. It shall be the responsibility of the Contractor to
ensure that each switchboard is properly registered and accepted by the
Jabatan Bekalan Elektrik Malaysia before commissioning into service same
19
and no claims for compensation from the contractor resulting from
modification works required by the Jabatan Bekalan Elektrik Malaysia on
such switchboards before acceptance is given, shall be entertained.
c) The ACBs shall match the current and voltage ratings stated
on the relevant Schematic Diagrams and be manufactured in
accordance with B.S. 862 : 1959 or B.S. 4752 : 1971. The
rupturing capacities (in MVA) or symmetrical interrupting
ratings (in KA.) stated against each ACB on the relevant
schematic Diagrams shall be based on a 415V, 3-phase, 4-
wire, 50H, A.C. supply rating and all ACBs supplied for the
contract works shall be not less than the rupturing capacities
or interrupting ratings stated on the said diagrams.
20
a) Each MCCB and MCB shall be of the all-insulated,
moulded, T.P. or D.P. or S.P. (where stated on the relevant
Schematic Diagrams), non-withdrawable type, suitable for
flush-mounting in the switchboards, distribution boards or
controls panels.
c) The MCCBs and MCBs shall match the current and voltage
ratings of the circuits they control and as stated on the
relevant schematic Diagrams. In additional, the MCCBs and
MCBs shall be suitable for the symmetrical interrupting
rating as stated on the relevant Schematic Diagrams in
Kiloamperers (KA.) at 415V., 50H., A.C.
11.4 Isolators
12.2 HRC fuse-links used for 13A fused plug tops complying with B.S.
1363 : 1967 shall be of 13A current rating and manufacturing to
B.S. 1362 : 1953.
Where earth fault (E/F) relays are to be provided for earth-fault protection of
electrical circuits and feeders as shown on the Schematic Diagrams, the
Contractor shall supply and install such units conforming to the following
requirements :-
13.1 The E/F or IDMT relay shall operate in conjunction with circuit
breakers controlling the electrical feeders or circuits concerned.
13.4 Every E/F or IDMT relay shall be fitted with a hand-reset type,
mechanical flag indicator and provided with adjustable settings
having a range of 10% to 40% of the secondary current rating of its
relevant current transformer.
23
tripping devices of circuit breakers, shall be of the type with
appropriate current ratios, burdens and classes as indicated on the
Schematic Diagrams.
15.1 All instruments shall be provided with square dials and be flush-
mounted in their respective switchboards and control panels.
15.3 Voltmeters
15.4 Ammeters
24
16. INDICATOR LAMPS
Where indicator lamps are shown on the Schematic Diagrams for installation
on switchboards and control panels, the Contractor shall supply and install
such lamps to meet the following requirements :-
16.1 All indicator lamps shall be of the transformer operated type and
be suitable for flush-mounting in their respective boards or panels.
16.2 Lenses for indicator lamps shall be of durable quality glass and
coloured to suit the colours stated on the relevant Schematic
Diagrams (for “Phase” indication of the electricity supply, “Red”,
“Yellow” and “Blue” coloured lenses shall be used to indicate
“Red”, “Yellow” and “Blue” phase of the electricity supply,
respectively.
17. CONTACTORS
Where contactors are indicated in the Schematic Diagrams for the Contract
Works, the Contractor shall provide and install such contactors to meet the
following requirements :-
17.3 The operational life for the contactors shall not be less than 9
Million (9,000,000) operations and be mechanical duty or
utilization shall be Class IV, with a Making and Breaking Category
of A4 as specified under B.S. 775 : Part I : 1969.
25
the constant presence of water or dampness, they shall be
accommodated in cast-metal casing of weatherproof construction.
All casings for contactor units shall have provision for the entry
and exit for circuit cables wired in conduit or cables of the
armoured multi-core type, as the case may be.
Where time switches are required in the Contract Works for automatic time-
controlled operation of lighting and other circuits, the Contractor shall
provide and fix such switches in switchboards or control panels, or
distribution boards (wherever as indicated on the Schematic Diagrams) to
conform to the following requirements :-
18.1 The time switches shall be of the synchronous type, fitted with 36-
hours spring reserves and 24 hours dial switches (switches to be
provided with adjustable levers for two “ON” and two “OFF”
operation.
18.3 The operation D.P. contacts of the time switches shall be rated at not
less than 10A, for operation in circuit with operating coils of
switching contractors. Means shall also be provided for test or
manual operation of the time switches.
19.1 The Contractor shall supply and install and automatic power factor
correction panel at the main M.V. switchboards. The panel shall
from part of the Main M.V. switchboards, with its cubicle
construction, arrangement of busbars, internal components,
interconnections, small wiring and paint finish generally conforming
to the requirements of the Main M.V. switchboards.
26
which shall be built-in with the cubicle of the Automatic
Power Factor Correction Panel. Each capacitor unit shall be
manufactured to BS comprising a vertically-arranged stack
of flattened roll capacitor elements of high purity aluminium
foil, separated with multiple layers of high grade dielectric
tissue. The steel container shall be internally lined with a
high-grade insulating board. Each capacitor unit is to be
fitted with a built-in discharge resistance network which
shall ensure that the capacitor is fully discharged in not more
than a minute after the electricity supply is de-energized.
The terminals of the capacitor unit shall be of glade ceramic
or other approved insulating material. The capacitor’s
element shall be impregnated with a suitable non-
inflammable impregnate and the whole shall be hermetically
sealed within the container.
27
d) 1 set “AS FITTED” schematic Diagrams of the electrical
installation for the entire complex, to be hung in a prominent
position on the wall of the switchroom.
For each of these rooms, the contractor shall supply and install on
the outside face of the room’s door a Regulation-type “NO
ADMITTANCE” and “DANGER” notice boards.
1. ELECTRICAL SUPPLY
1.1 The electrical supply to the DB will be a nominal 415-Volt, 4-wire, 3-phase
and neutral service.
2. RATINGS
The DB shall have a certified busbar system and incomer switch rated for a
fault level of 43K Amp for one second or better.
2.2 The busbar system shall be rated to carry the full load current, based on the
maximum rating ALL outgoing compartments as per drawing.
2.3 The main switch shall be rated to break the full load current of DB, based on
the maximum rating of ALL outgoing compartments.
2.4 Individual compartment switches shall be rated to break the full load current,
based on the maximum rating of that compartment.
2.5 All cables shall be rated to carry continuously the full current value of their
protective devices.
3. MATERIAL
3.3 There shall be no deviation from the nominated manufacturers and type of
equipment referred to in this specification.
28
4. DB ARRANGEMENT
4.1 The DB shall be self supporting, free standing with provision made from
securing to the floor.
4.2 The DB shall be arranged for both front and rear access to compartments and
for cabling to compartments.
4.3 The DB shall be suitable for top and bottom cable entry.
4.4 The DB shall be arranged such that additional tiers may be readily added to
at least one end, for future extension.
4.5 The DB manufacturer shall offer the option of providing the Main incomer,
Switch and metering at either end of the unit to suit the customer’s
requirement.
4.6 The DB shall have a removable plinth.
4.7 The busbars shall run along the top section of the DB with vertical droppers
at each tier.
The busbar system shall be fully shielded from other section of DB.
5. DB CONSTRUCTION
5.2 The plinth shall be demountable and may a single assembly to provide a rigid
and straight base for the mounting of the DB sections.
The plinth shall be provided with suitable securing holes for floor fixing.
The outer faces of the plinth shall provide a flush face, to match the outer
faces of the DB.
The DB shall be of welded construction with flush front design and radiuses
corners and edges.
5.4 Removable gland plates of minimum thickness 3mm shall be provided on top
of the DB to accommodate all cabling requirements.
5.5 Provision shall be made within the DB for the termination of bottom entry
cables.
29
5.6 Each compartment, whatever its function, shall be fully segregated from
adjacent compartments, to confine damage due to an internal fault.
5.7 The DB shall be provided with lifting eye bolts to facilitate handling. A set
of blanking bolts, to replace the eye bolts, shall be supplied by the DB.
Manufacturers for fitting by the Electrical Contractor.
5.8 Where provisions are made for extending busbars and cable ways, for future
additions to the DB, cutouts shall be fitted with screw-fixed cover plates.
5.9 Between each tier of starter compartments, a front access cable way shall be
provided, adequately sized to permit the installation of cables to all
compartments. Access between cable ways and equipment compartments
shall be made via adequately-sized openings fitted with blind grommets.
5.10 Provision shall be made for the routing of wiring between compartments in
different tiers.
5.11 Each compartment containing equipment shall have an access door.
Doors shall have exposed chrome hinges or concealed hinges, which permit
the door to open through 90 or greater.
Door fitted with interlocked switches shall have quick-release catches. Other
doors shall be secured by door handles.
All doors shall be fitted with locks, which shall have the same key differ.
5.12 All other access openings shall be fitted with removable covers fixed by
chrome screws.
6. FINISH
6.3 All external steelwork shall be finished semi-gloss paint approved by the
Engineer.
Note : That a high quality pigment is required for this colour to ensure a
good cover.
7. BUSBARS
7.1 In addition to the requirements of Section 3.0 and 5.0 the following shall
apply :-
(i) The busbar system shall consist of air-insulated single copper bars for
three phases and neutral and shall be suitable for extension at one or
both ends.
30
(ii) Barriers shall be fitted to all horizontal and vertical busbar
intersections.
(iii) The busbars are to be fully shielded from all other sections of the
panel.
(iv) All bars are to be fitted with colour-coded markers for easy
identification of phases and neutral.
8. EARTHING
8.2 External earthing studs suitable for the connection of an earthing tape shall
be provided on top of the DB, at both ends. These earthing studs shall be
directly bonded to the DB main earth bar.
8.3 From the main earth bar in the DB, vertical earth bars shall be installed and
bonded to each individual equipment compartment. An earthing stud shall
be provided in each compartment.
8.4 At each equipment compartment the door and removable equipment plates
are to be bonded to the compartment earthing stud by means of suitably-sized
greed/yellow PVC insulated flexible copper cable.
8.5 All gland plates are to be bonded to the main earth bar in each DB by means
of suitably-sized greed/yellow PVC insulated flexible copper cable.
9. MAIN INCOMER
9.1 The DB shall have a main isolating switch with 3-phase double break action,
rated to break a load in excess of the sum of the rating of all outgoing
compartments. A solid bolted neutral link of like rating shall be mounted in
the same compartment.
9.2 The main incoming power supply to the DB shall be wired via the main
contacts of the isolating switch. All terminals shall be fully shrouded.
9.3 Adequate provision shall be made for installing the incoming supply cables
to the isolating switch. All terminals shall be fully shrouded.
9.4 The main outgoing terminals of the isolating switch shall be bolted directly
to the busbar system.
9.5 The door for the main isolating switch compartment shall be mechanically
interlocked to prevent the switch being closed with the door open and the
door being opened with the switch closed.
9.6 The “ON” and “OFF” positions of the isolating switch shall be clearly
marked and the switch shall be pad-lockable in the “OFF” position.
31
10. INSTRUMENT COMPARTMENT
10.1 The DB shall have an instrument compartment located adjacent to the main
isolating switch compartment.
10.3 The ammeter shall be ranged to the maximum load plus overscale.
10.4 The voltmeter shall be ranged 0 – 500 volts with red indicator lines on the
scale at 240 volts and 415 volts.
The voltmeter supply shall be derived from primary fuse carriers, bolted to
the main busbars via secondary fuse carriers located in the instrument
compartment.
The phase fuse carriers shall be black and shall be fitted with HRC fuse
links, with suitable discrimination between primaries and secondaries.
The neutral carriers shall be white and shall be fitted with solid copper links.
11. STARTERS
11.3 The starting arrangement for standard starters shall be decided by the
Engineer.
11.4 Clearing working space shall be allowed in all starter compartments for
wiring, maintenance and replacement of parts. In particulars, full allowance
shall be made for the installation and termination of field wiring at the
terminal blocks. With all wiring complete, each item of equipment shall
remain fully accessible.
11.5 Starter equipment shall be mounted within the compartment housing. Only
“through the door” equipment shall be located on doors.
11.6 Starter compartment shall have a double break, 3-phase, MCCB complete
with rotary handle.
The switch shall be sized to break the maximum load for which the
compartment can be rated.
32
The main incoming terminals of the switch shall be bolted directly to the
supply busbars.
The “ON” and “OFF” positions of the isolating switch shall be clearly
marked and the switch shall be pad lockable in the “OFF” position.
11.7 Starter shall have a Contactor and Contactors to suit the starting
arrangements for which it is designed.
Contacts shall be suitable for AC3 Class II operation and shall be sized to the
maximum rating of the compartment.
The overload relay shall be the directly-connected thermal type or the C/T
operated thermal type as recommended by the manufacturer.
All thermal relays shall be 3-phase combined thermal overload and single
phasing preventor type, with manual reset.
Thermal overloads shall be arranged for hand resetting after opening the
compartment door.
Operation of the overload relays shall de-energize the starter contactor and
illuminate trip indication lamp.
11.9 Starter compartments with which ever specified shall have a thermistor
protection relay.
33
A red pointer, adjustable from the front, shall be incorporated in the ammeter
design.
All ammeters shall operate from the yellow phase, via current transformers
having lamp secondary windings where applicable.
Current transformer shall have a minimum burden rating of 2.5 VA and shall
be arranged for the connection of an external current indication circuit.
11.11 Starter compartment shall have a red, door-mounted, stop push button and a
green, door-mounted starter push button for local operation of the drive
motor.
11.12 Starter compartment shall have a door mounted, 3 position selector switch
for local manual and remote manual selection.
11.13 Starter compartment shall have a red door mounted indicator light,
illuminated when the motor is running and a clear door mounted indicator
light, illuminated when the starter control circuit is in a trip condition.
11.14 Starter compartment shall have a terminal rail for the connection of outgoing
and incoming wiring.
When sizing terminals full allowance shall be made for field wiring sized to
accommodate volt drop.
11.15 Additional equipment associated with motor control may be housed in the
M.C.C. i.e. Variable Speed Control Units, Transformers for Auto-
Transformer Starting.
When separate compartments are used door interlocking or full shielding and
warning labels shall be fitted.
Full allowance shall be made for heat output from additional equipment
when designing the M.C.C.
12.1 Each switch provided for the purpose of feeding a supply to an external load
shall have a separate compartment.
12.2 Each switch compartment shall be designated with a maximum rating value.
34
All equipment and wiring within a compartment shall be sized to the
maximum rating of that compartment, with the exception of the fuses, which
shall be sized to suit the rating of the load.
12.3 Each switch compartment shall have a double break, 3 phase, MCCB.
The switch shall be sized to break the maximum load for which the
compartment can be rated.
The main incoming terminals on the switch shall be bolted directly to the
supply busbars.
The “ON” and “OFF” positions of the switch shall be clearly marked and the
switch shall be pad-lockable in the “OFF” position.
12.4 Each switch compartment shall have a door mounted ammeter, ranged to the
maximum rating of the fuse switch.
All ammeters shall operate from the yellow phase via current transformers
having 1 amp secondary windings where applicable.
12.5 Each switch compartment shall have a terminal rail for the connection of
outgoing wiring.
Terminals shall be of the screw clamp type for cables up to 50 sq.mm and
stud type for cables over 50 sq.mm.
When sizing cables full allowance shall be made for field wiring sized to
accommodate volt drop.
The terminals shall be cabled to the fuse switch and neutral link.
a) Internal Wiring
(i) Wiring shall be carried out in single core flexible copper, PVC
insulated cable, rated for operation at 600 volts.
35
equipment inside the cubicle with the door in the “open” and
“closed” positions.
b) Labels
(ii) Each DB shall have a main identification label of uniform size and
engraved in 12mm high lettering with the DB title.
In the case of terminal rails, the warning label may also from the
protective shield.
(ix) Exact wording of all labels shall be agreed with the customer
before label manufacture.
d) Manufacturers Drawings
(i) Two weeks after order, a comprehensive list of the quantities and
type of equipment items proposed for each panel, together with a
priced list of recommended spares.
1.3 All road-crossing pipe cable ducts, cable-entry pipe ducts to and cable
distribution pipe ducts away from the buildings shall each be provided with a
non-corrodable draw-wire for the easy drawing-in of cables.
1.4 All cable-entry, cable distribution and cable road-crossing pipe ducts,
whether provided by the other Contractor or the Contractor, shall be
effectively sealed by the Contract (after all cables are laid in position) in
such a manner as to prevent the ingress of water, mud or dirt through the
ducts.
1.5 The Contractor shall closely liaise with the other Contractor in the laying of
all cable-entry, cable distribution and road-crossing ducts, so as to avoid any
breaking-up of concrete walls, floors, aprons and completed road surfaces at
38
a later date due to such items being installed or laid incorrectly or in wrong
locations.
2. CABLES
2.1 Cables for the internal wiring of the buildings and the external cabling
distribution sub-mains, shall be supplied and installed by the Contractor.
The Contractor shall supply and install all cables for internal and external
building as specified in the specification and drawings.
2.2 All electric cables supplied by the Contractor for the Contract Works shall be
provided with high conductivity, stranded annealed copper conductors.
2.3 Where PVC cables are specified in the contract such cable shall be
600/1,000V. grade and manufactured to B.S. 6004 : 1969 for metric sizes.
3. TYPE OF CABLE
3.1 For single-phase and 3-phase or 3-phase 4-wire, final sub-circuit wiring,
PVC insulated (PVC) cables of 600/1,000V. grade and manufactured to B.S.
6004 : 1969 shall be used. Where PVC cables are used for L.V. single-phase
or 3-hase, 4-wire sub-mains or rising mains installed on cable trays, such
cables shall be of the PVC insulated and sheathed (PVC/PVC) type of the
same voltage grade as specified above.
3.2 Where Mineral Insulated Copper Covered and PVC sheathed (MICC/PVC)
cables or Mineral Insulated Copper Covered (MICC) cables are specified on
the drawings for use in the Contract Works, such cables shall be of
600/1000V. grade and manufactured to B.S. 627 : Part I : 1969.
3.3 Wherever PVC-insulated single wire armoured and PVC Served Overall
(PVC/SWA/PVC) cables are specified on the drawings for use on the
Contract Works, such cables shall be 600/1,000V. grade for Metric Sizes and
manufactured to B.S. 6346 : 1969.
3.4 Where Paper Insulated Lead Covered and Served (PILC.&S) cables, or Paper
Insulated Lead Covered Double Steel Tape Armoured and Compounded Jute
Hessein Tape Overall (PILCDSTA.&S) cables are specified for use on this
sub-contract, such cables shall be of the M.I.N.D. type, manufactured to B.S.
6480 : Part I : 1969 and of 600/1,000V grade for all L.V. circuits.
3.5 Flexible cords used for the suspension or lampshades, connection of lighting
fittings to their wiring points and for connection of electric appliances, shall
be of the 3-core or 4-wire or 5-core, PVC-insulated type with white colour
sheaths, of Metric Sizes (300/300V) grade for single-phase circuits and
300/500V. grade for 3-phase or 3-phase, 4-wire circuits) and manufactured to
B.S. 6500 : 1969.
39
4. INTERNAL ELECTRICAL WIRING INSTALLATION & UNDERGROUND
OR UNDERFLOOR CABLING
e) Where conduits are installed directly on walls and concrete work, they
shall be fastened by means of galvanized, spacer-bar saddles and
rawlplugs at appropriate intervals in accordance with standard wiring
practice. Rawl plugs shall be drilled into walls and concrete works and
the use of hardwood plugs for installing spacer-bar saddles shall not be
permitted. Spacer-bar saddles shall be fastened by means of ground-head
brass screws and washers.
f) In the case where conduits are installed on-perforated cable trays, they
shall be fastened by means of suitable galvanized metal saddles, round-
head brass bolts, nuts and washers.
g) The Contractor shall paint all surface-run conduit with two (2) coats of
an approved type of paint after erection is completed. All conduits shall
be painted orange colour.
40
a) Where conduits are to be concealed in the plasterwork of brickwork
walls, the Contractor is required to cut the necessary chases in the walls
for the installation of the conduits. Initial plastering of chases shall be
undertaken by the Contractor after conduits have been erected in position
by the final plastering of chases shall be undertaken by the other
Contractor.
e) All conduit risers shall be painted in the same manner as described under
Sub-Clauses below of this Section.
b) Where such cables are laid in pre-cast concrete trenches, the cables shall
be nearly laid at the bottom of the trenches without crossing each other
except where they rise from the trenches to their respective terminal
boxes or cable end-boxes. Cables laid in concrete trenches shall be
spaced a part of each other in the manner prescribed of this section.
Where more than one layer of cables are to be laid in the same trench,
then the upper layers shall be neatly spaced and held in position by
purpose-made, hardwood cleats installed on M.S. brackets along the
walls of the trench. The spacing of cables of brackets shall be in
accordance with of the I.E.E. Wiring Regulations. For cable diameters
exceeding 40mm dia. (overall), reference shall be made to the
Manufacturers of such cables for spacing of supports. In any case,
however, the spacing of supports shall be such that there is no sag in the
cables between supports.
c) Where such cables are laid on trays, they shall be held in position by
means of purpose-made non-corrodable, non-magnetic, metal saddles of
appropriate sizes and mechanical strength. The cables shall be spaced
apart in the manner prescribed under Sub-clause 5 of this section.
Saddles shall be bolted to the trays by means of non-corrodable nuts,
bolts and washers. Only one layer of cables may be installed one each
tray and under no circumstances may two or more layers of cables be
installed on a single cable tray.
The cable trenches shall then be filled up with earth in layers of 150mm
each, every layer being properly tamped before another layer is placed
over. The procedure shall continue until the trenches have been
completely reinstated.
h) The Contractor shall provide and connect-up all necessary brass glands
for the termination of PVC/SWA/PVC or XLPE insulated cables. In the
cast of PILCDSTA &S cables, the Contractor shall provide the necessary
cable end-boxes, black insulating compound for their respective cable
end-boxes and all such compound shall be suitable for the voltage grades
of the cables to be terminated. All other jointing materials necessary to
complete the termination of the cables shall also be provided by the
Contractor.
j) The type of gland that the Contractor proposes to use shall be approved
by the Engineer before any termination is carried out.
k) All glands shall be weather and moisture proof complete with PVC
shrouds.
o) Crimped cable lugs shall be used throughout for the jointing of the
conductors of PVC, armoured cables. Lugs shall be affixed to the cable
by means of a crimping tool as recommended by the manufacturer, using
the correct pressure.
43
q) The cable cores shall be taken direct into the equipment terminals,
jointed tails shall not be permitted unless with the permission of the
Engineers.
b) Flexible cables shall be kept to a minimum and shall comply with this
specification where applicable.
4.5 Grouping of Cables on Trays and Cables Laid in Closed Precast Concrete
Trenches
(i) Not less than 6 times the overall diameter of an individual cable
and not less than the overall width of an individual circuit except
that the horizontal clearance need not in any case exceed
150mm.
(ii) The vertical clearance between circuits is not less than 150mm.
c) Where multi-core cables of the trays stated above and circuits of single-
core cables stated above are installed in Precast closed concrete trenches,
the dispositions of the cables or circuits of single-core cables shall follow
the requirements laid out in the I.E.E. Wiring Regulations and multi-runs
of cables in trenches shall be de-rated in accordance with the Rating
Factors stated in the I.E. Wiring Regulations.
44
(G) GENERAL SPECIFICATIONS
All prices shall be inclusive of all Government duties, surtax and sales.
All valves, connectors, gauges, etc. shall be properly protected to prevent any
possible damage during transportation and storage.
3. Catalogue
4. Test Certificates
Manufacturer’s Test Certificate for the seamless steel pipes, fittings and door
closure shall be submitted at the time of delivery of the pipes.
5. References
6. Drawings
45
7. Completion Schedule
The liquidated damages for late completion of work shall be calculated at the
rate of RM2,000.00 per day subject to a maximum of 20% of the Contract Price.
46