BUILDING AREA SCOPE DESCRIPTION STATUS COMPLETION DATE REMARKS

Under ground piping completed


CDP -High Level for FCU completed
DRAINAE CDP for Split Unit(Concealled) Not Completed 2" HP pipes are not available
GF Riser Works-Part -1 Not Completed 19/08/2020 One balance out of 2.Will be completed by 19/08/2020
Riser Works-Part -2 Completed Vent Connection Balance - 2" pipes are not available.
WATER SUPPLY Part -1 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Part-2 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Piping- High Level completed
Rise Works-Part -1 Not Completed 19/08/2020 One balance out of 2.
ADMIN 1 DRAINAE Soil and Waste Completed.Vent piping balance.Pipes for vent are not available
Rise Works-Part -2 Not Completed
FF at site
CDP -High Level for FCU Not Completed 25/08/2020
CDP for Split Unit(Concealled) Not Completed 25/08/2020
WATER SUPPLY Part -1 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Part-2 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
5 Nos completed out of 7.Balance 2 nos. Civil
Roof Drain Ongoing After Civil Clearence
RAINWATER works ongoing for upper roof
ROOF
Piping Not Completed Need Scaffolding outside building
WATER SUPPLY Roof Piping. Not started After Civil Clearence Civil works ongoing
Under ground piping completed
CDP -High Level for FCU Not Completed 25/08/2020
DRAINAE CDP for Split Unit(Concealled) Not Completed 2" HP pipes are not available.Civil works ongoing
GF Riser Works-Part -1 Not Completed After Civil Clearence Civil works ongoing(Wall)
Riser Works-Part -2 Not Completed After Civil Clearence Civil works ongoing(Wall)
WATER SUPPLY Part -1 Not Completed After Civil Clearence Civil works ongoing(Wall)
Part-2 Not Completed After Civil Clearence Civil works ongoing(Wall)
Piping- High Level completed After Civil Clearence Civil works ongoing(Wall)
Rise Works-Part -1 Not Completed After Civil Clearence Civil works ongoing(Wall)
ADMIN 2
DRAINAE Rise Works-Part -2 Not Completed After Civil Clearence Civil works ongoing(Wall)
FF CDP -High Level for FCU Not Completed After Civil Clearence Civil Works.Need to remove shutter
CDP for Split Unit(Concealled) Not Completed After Civil Clearence Civil works ongoing(Wall)
WATER SUPPLY Part -1 Not Completed After Civil Clearence Civil Works.Need to remove shutter
Part-2 Not Completed After Civil Clearence Civil Works.Need to remove shutter
Roof Drain After Civil Clearence Civil Works.Need to remove shutter
RAIN WATER Piping Not Completed After Civil Clearence Civil Works.Need to remove shutter
ROOF WATER SUPPLY Roof Piping. Not started After Civil Clearence Civil Works.Need to remove shutter

Under ground piping completed


CDP -High Level for FCU completed

DRAINAE
GF CDP for Split Unit(Concealled) Not Completed 19/08/2020 2" HP pipes are not available,Wall works ongoing-Need Civil Clearence
Riser Works-Part -1 Not Completed Wall works ongoing-Need Civil Clearence
Riser Works-Part -2 Completed
WATER SUPPLY Part -1 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Part-2 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
DRAINAE Piping- High Level completed Wash Basin Piping & Vent Balance.2" Pipes are not available
HEAD QUARTERS Rise Works-Part -1 Not Completed 25/08/2020 CDP Balance
Rise Works-Part -2 Not Completed Wall works ongoing-Need Civil Clearence
FF CDP -High Level for FCU Not Completed 25/08/2020
CDP for Split Unit(Concealled) Not Completed 25/08/2020
WATER SUPPLY Part -1 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Part-2 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
5 Nos completed out of 7.Balance 2 nos.
Rain Water Roof Drain
After Civil Clearence Civil works ongoing for upper roof
ROOF Piping Not Completed Need Scaffolding outside building

WATER SUPPLY Roof Piping. Not started After Civil Clearence Civil works ongoing