DRAINAE
GF CDP for Split Unit(Concealled) Not Completed 19/08/2020 2" HP pipes are not available,Wall works ongoing-Need Civil Clearence
Riser Works-Part -1 Not Completed Wall works ongoing-Need Civil Clearence
Riser Works-Part -2 Completed
WATER SUPPLY Part -1 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Part-2 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
DRAINAE Piping- High Level completed Wash Basin Piping & Vent Balance.2" Pipes are not available
HEAD QUARTERS Rise Works-Part -1 Not Completed 25/08/2020 CDP Balance
Rise Works-Part -2 Not Completed Wall works ongoing-Need Civil Clearence
FF CDP -High Level for FCU Not Completed 25/08/2020
CDP for Split Unit(Concealled) Not Completed 25/08/2020
WATER SUPPLY Part -1 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
Part-2 Not Completed After Civil Clearence Wall works ongoing-Need Civil Clearence
5 Nos completed out of 7.Balance 2 nos.
Rain Water Roof Drain
After Civil Clearence Civil works ongoing for upper roof
ROOF Piping Not Completed Need Scaffolding outside building
WATER SUPPLY Roof Piping. Not started After Civil Clearence Civil works ongoing