Project-Jain Sadguru Image's Capital Park

Delay Register

Contractor: SSTB
Discipline: Civil
Date:22-11-2021
Schedule committed by SSTB
Delay as per
DATE:- 01-11-2021 Actual Completion
SSTB Schedule

S.No. Description Completion date Status as on 22-11-2021


A STRUCTURE(Upton Terrace Slab) Completed
A1 Pour-1 02-09-2021 Completed
A2 Pour-2 29-09-2021 Completed
A3 Pour-3 14-10-2021 Completed
B ABOVE TERRACE
B1 Parapet Wall 06-11-2021 10-11-2021 Completed
B2 Staircase Head Rooms(4 Nos) 24-11-2021 Completed
B3 Water Tank 30-11-2021 -8 Column shuttring work in progress
B4a LMR(1A - Lift - 1No) 11-10-2021 Completed
B4b LMR(3B - Lift - 1No) 25-11-2021 -3 50% Completed
B4c LMR(2B - Lifts - 16 Nos) 25-11-2021 -3 50% Completed
B5 Chillers Bottom Slab(16th Slab) 06-11-2021 Completed
B6 Chillers Top Slab(17th Slab) 21-11-2021 1 60% completed
C BLOCK WORK 31-12-2021 -39
C1 Ground Floor 22 80% Completed
C2 1st Floor 22 90% completed
C3 2nd Floor Completed
C4 3rd Floor Completed
C5 4th Floor Completed
C6 5th Floor 19-11-2021 3 80% completed
C7 6th Floor 01-12-2021 -9 50% completed
C8 7th Floor 10-12-2021 -18 40% completed
C9 8th Floor 10-12-2021 -18 40% completed
C10 9th Floor 31-12-2021 -39 20% completed
C11 10th Floor 31-12-2021 -39 Yet to start
C12 Terrace and above terrace 30-11-2021 -8 5% Completed
D INTERNAL PLASTERING 15-01-2022 -54
D1 Ground Floor 22 80% Completed
D2 1st Floor 22 90% completed
D3 2nd Floor 22 90% completed
D4 3rd Floor 22 95% completed
D5 4th Floor 15-11-2021 7 60% completed
D6 5th Floor 20-11-2021 2 Yet to start
D7 6th Floor 30-11-2021 -8 Yet to start
D8 7th Floor 31-12-2021 -39 Yet to start
D9 8th Floor 31-12-2021 -39 Yet to start
D10 9th Floor 31-12-2021 -39 Yet to start
D11 10th Floor 15-01-2022 -54 Yet to start
E EXTERNAL PLASTERING 30-11-2021 -8
E1 North Side (GF & FF) 12-11-2021 10 90% completed
E2 East Side (GF & FF) 15-11-2021 7 90% completed
E3 East Side (Toilets Area) 30-11-2021 -8 Yet to start
F VDF CLEAREANCE
F1 1st Cellar Floor 10-11-2021 12
F2 2nd Cellar Floor 20-11-2021 2
F3 3rd Cellar Floor 30-11-2021 -8
F4 4th Cellar Floor 10-12-2021 -18
G Lift handing over
Civil Works completed, rectificztion to be done after
18
G1 Fire lift 3 04-11-2021 hitachi survey
Civil Works completed, rectificztion to be done after
16
G2 fire lift 4 06-11-2021 hitachi survey
Civil Works completed, rectificztion to be done after
12
G3 Service lift 2 10-11-2021 hitachi survey
G4 Service lift 1 14-11-2021 8
G5 fire lift 2 16-11-2021 6
G6 fire lift 1 20-11-2021 2
G7 Passenger lift 6no South 25-11-2021 -3
G8 Passenger lift 6no North 30-11-2021 -8
H MEP Shaft handing over
H1 G-4th floor 04-11-2021 26 Electrical room and riser shaft handing over pending
H2 6th floor 04-11-2021 18 Block work plastering still not completed
H3 7th floor 08-11-2021 14
H4 8th floor 10-11-2021 12
H5 9th floor 21-11-2021 1
H6 10th Floor 24-11-2021 -2