PROGRESS REPORT APRIL 2 0 2 3

West Wing - TOW ER-1


Work Description

• 10th Floor – Pour 02– Slab shuttering &


Reinforcement work in progress.

• 10th Floor – Pour 01– Slab Completed

• 9th Floor – Pour 01 & 02 - Slab


Completed.

• Block work – The block work has been


completed up to the 3rd floor, and work
on the 4th floor is currently in progress.

• Internal Plastering - Ground floor


Internal Plastering is currently in
Tower-1: 10th floor Structural Works are in Progress
progress.
West Wing - TOW ER-2
Work Description

• Above Terrace – All structural works has been


completed.

• External Plastering – Completed

• Block work – Completed

• Internal Plastering –Internal Plastering Completed


(Except the Ground Floor).

• Toilet Dado works – Total 120no. Of flats out of 150 flats


are completed.

• Toilet & Flat Flooring - Total 120no. Of flats out of 150


flats are completed.

• Texture: External Texture works under progress.

Tower-2: Finishes and MEP works in


progress
West Wing - TOW ER-3
Work Description

• Above Terrace – All structural works has been


completed.

• External Plastering – Completed (Except


rectification and outside lift area)

• Block work – Completed.

• Internal Plastering –Up to 13th Floor


Completed & 14th Floor in progress.

• Texture Works – Texture works in progress.

Tower-3: Finishes and MEP works in progress


West Wing - TOW ER-4
Work Description

• Above Terrace – Core walls for OHT and slab


concrete works are yet to be completed.

• Block work – Completed

• Internal Plastering –Up to 13th floor


completed & 14th floor in progress.

• External Plastering – Series 6,7 are under


progress.

• Texture Works – Texture works in progress.

Tower-4: Above Terrace Floor & Finishing works are in Progress


West Wing - TOW ER-5
Work Description

• Terrace Floor Pour-01 & 02 – Slab concrete


casting work completed.

• Block work –Up to 9th Floor Completed, 10th


Floor is in progress.

• Internal Plastering – 1st, 2nd ,3rd & 4th floor


plastering completed, 5th floor plastering in
progress.

Tower-5: Above Terrace slab shuttering works in progress


West - TOT LOT Area
Work Description

• Infront of WW T04 - The Totlot area


has been reached up to the podium
level.

• Infornt of Between WW T04 & WW T05


- The Totlot area has been reached up
to the Cellar 01.

• Infornt of WW T05 - The Totlot area has


begun to execute at the Cellar 03 roof
level.

West Totlot: Structural work in progress @ Cellar level


West Wing – Tower 6
Work Description

• Ground floor – Pour 02 Slab shuttering


and Reinforcement fixing works under
progress.

• Ground floor – Pour 01 Slab concrete


casting completed.

• Above Ground floor – Column


reinforcement and shuttering work
under progress.

Tower-6: Ground floor structural works in progress.


West Wing – Tower 7
Work Description

• 10th floor – Pour 02 slab shuttering &


reinforcement work completed.

• 10th floor – Pour 01 slab concrete


casting work completed.

• 9th floor – Pour 01 & 02 slab concrete


casting work completed.

• Block Work: 3rd and 4th floor block


work under progress.

Tower-7: 10th Floor structural works in progress.


East Wing – Tower 6
Work Description

• OHT Wall shuttering and reinforcement in progress

• Block work – Completed.

• Internal plastering – The work has been completed


up to the 13th floor, and work on the 14th floor is
currently in progress.

• External Plastering – Completed (Except rectification


works).

• Texture works - Completed texture up to the 1st floor


(from top to down).

• Internal 1st coat putty works – from 2nd floor to 7th


floor 1st coat putty works has been completed.

Tower-6: Above Terrace Works & Finishing works in progress.


East Wing – Tower 5
Work Description

• OHT Wall shuttering and reinforcement in


progress

• Block work – Completed

• Internal plastering – Completed up to 13th floor ,


14th floor is in progress.

• External Plastering – The flat numbered 03


require external plastering to be done on their
external face.

• External Texture - The flat numbered 03 require


external texture to be done on their external
face.

Tower-5: Above Terrace Works & Finishing works in progress.


East Wing – Tower 4
Work Description

• 7th Floor – Pour 01 slab concrete casting


work completed.

• 6th floor – Pour 01, 02, & 03 slab concrete


casting completed.

Tower-4: 7th floor structural works in progress.


East Wing – Tower 3
Work Description

• 11th floor – P01 & P02 Slab casting works are


completed.

• Block Work – Work on the Ground floor to 5th


floors is currently in progress.

• Internal Plastering - – Work on the Ground


floor to 2nd floors is currently in progress.

Tower-3: Above 11th floor structural and Finishes works in


progress.
East Wing – Tower 2
Work Description

• 4th floor - Pour 01 Slab concrete casting


work completed.

• 4th floor – Pour 02 slab shuttering &


Reinforcement work in progress.

• 3rd floor - Pour 01 & 02 Slab concrete


casting work completed.

Tower-2: 4th floor & Above structural works in progress.


East Wing – Tower 1
Work Description

• The foundation work is currently in progress,


including P.C.C (Plain Cement Concrete) and
R.C.C (Reinforced Cement Concrete) footing
works.

• Column reinforcement and shuttering work in


progress at cellar 04 level.

Tower-1: Foundation P.C.C and R.C.C works in progress


East Wing – TOT LOT and Clubhouse area
Work Description

• East Wing Clubhouse – Excavation of the


West portion of the east wing clubhouse
is in progress.

• Totlot Area – The Totlot area has reached


the podium level/final level.

• EW Clubhouse – P.C.C for foundation


works in progress.

East Totlot and Clubhouse: Structural works in progress @ Cellar level