Date: 2023/06/08 41°/26°

CONSTRUCTION OF NEW TERMINAL BUILDING AT NEPALGUNJ AIRPORT


DAILY CONSTRUCTION REPORT

Photos Explanation
Block 'A'
• The base formwork of main beam is
being fixed for first floor at level
0+4.9 m.
• Bar bending schedule has also been
provided and is being reviewed.

Block 'B'
• After starting the casting of
fig. Block 'A' (Formwork for main beam-first floor) 0+4.9 m basement floor slab from 4:00 pm
yesterday, the work was halted at
8:45 am today morning after
completion of designated portion.
• Slab within the grids (F12-F17 to
B12-B17) is being concreted from
5:30 in the evening.

Block 'C'
• Similar preparations as block 'A' is
going on in block 'C'.
fig. Block 'B' (Morning) Concreting
Guest House Building
• Work has been halted because of
sub-contractor on leave.

Drainage Location
• Concreting of drain section upto
chainage 0+110 m (starting from
culvert towards hangar) has been
completed as of today.
fig. Block 'C' (Casting of 14 columns-going on) • Earthwork and soling is also going
on simultaneously on further
chainage.

fig. Concreting in drain section