PORJECT : URVISHA, NEWTOWN

TOPIC : Weekly Review Meeting


DATE : 05.02.2024
TIME : 10:30 AM
Contractor : SM Nirman
PARTICIPENTS
ATTENDEE ATTENDEE
SIGNATURE
(Ambuja Neotia) (SM Nirman Pvt. Ltd.)
Mr. Sankha Bhattacharya. Mr. Alok Sharma
Mr. Rajesh Kumar Arora Mr. Manoj Mishra
Mr. Soumyajit Majumder Mr. Asit Mukherjee
Mr. Biplab Kundu
Mr. Utpal Das
Mr. Prasun Mondal
Mr. Milan Paul
Mr. Arin Ghosh
Mr. Apurbo Patihar
Mr. Subharanjan Das

ACTIONS TO ACTUAL
SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
Schedule Date (R0): IN DAYS (Status Date: 05-02-2024)
BY : DATE

Safety
Block-D
If larva found in any place of SMN working area
Dengue Care & SMN Continue process.
50,000/- will be charged instatntly.
Block-E

Basement de-shuttering work at Block-C 100% completed.


Basement House keeping work
House keeping Block-C SMN Block-C Basement housekeeping done but at some places stagnant water has been
observed.
Block-D and Block- Ambuja requested to warping work need to be
Building Wrapping start from 1st week of Nov. SMN Block E side stagging work started.
E
Quality
Progress Status Block Wise
Block-C
15-12-2023
1st Floor Slab Block-C Civil Activity SMN 6/5/2023 10/29/2023 11/24/2023 1/11/2024 -220 Completed
07-01-2024 (R4)
Status:
Column casting work is in progress.
Column casting status: 29/31.
2nd Floor Slab Block-C Civil Activity SMN 7/6/2023 1/24/2024 1/26/2024 2/8/2024 -215 Beam reinforcement work is in progress.
Required revised schedule

Staging Materials
for double height Block-C Civil Activity SMN 1/7/2024 Completed.
part.
Block-D
PART-01 Civil Activity 1/16/2024 1/24/2024 1/31/2024 2/2/2024 Completed.

PART-01 Fire Slab Civil Activity SMN 11/27/2023 1/7/2024 1/18/2024 Completed.
9TH FLOOR SLAB
PART-02 Civil Activity 1/20/2024 1/28/2024 2/10/2024 Slab reinforcement work is in progress,.

PART-02 Fire Slab Civil Activity SMN 1/14/2024 Not started

Part-01 Civil Activity SMN 2/22/2024 Column reinforcement work is in progress.


10th Floor Slab 12/23/2024
Part-02 Civil Activity SMN
ACTIONS TO ACTUAL
SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
Schedule Date (R0): IN DAYS (Status Date: 05-02-2024)
BY : DATE

Block-E
PART-01 Civil Activity 1/11/2024 1/18/2024 1/22/2024 Done
9th Floor Slab SMN 12/12/2023
PART-02 Civil Activity 1/5/2024 1/9/2024 Done
PART-01 Civil Activity 2/8/2024 2/19/2024 Shuttering at reinforcement work is in progress.
10th Floor Slab SMN 1/12/2024
PART-02 Civil Activity 1/30/2024 2/3/2024 Reinforcement and shuttering work is in progress. Will be casted on 7th February.

Club
Done
Pile Cap and Raft SMN Civil Activity SMN 4/3/2023 02.05.2023 31.05.2023 30-06.2023 11/23/2023 -234

Retaining wall complition date: 05-12-2023


Deck slab : 07-12-2023
If SMN unable to cast deck slab on 07-12-2023 , R2- 07-01-2024
Deck Slab SMN SMN 5/15/2023 11/30/2023 12/7/2023 Shuttering and reinforcement work is in progress.
LD shall be applicable. R3- 07-02-2024

AAC Block Work


Block D Gr. Floor SMN 7/30/2023 Work not started
1st Floor SMN 8/22/2023 95% completed.
2nd Floor SMN 9/13/2023 95% Completed.
3rd Floor SMN 10/5/2023 90% Completed
4th Floor SMN 10/28/2023 90% Completed
5th Floor SMN 11/20/2023 50% Completed.
6th Floor SMN 12/13/2023
7th Floor SMN 1/5/2024

Block-E Gr. Floor SMN 8/14/2023 Work not started


1st Floor SMN 9/6/2023 95% completed
2nd Floor SMN 9/28/2023 95% completed
3rd Floor SMN 10/20/2020 95% Compleetd
4th Floor SMN 11/12/2023 Work done upto band beam level. Sufficient Man Power not available.
5th Floor SMN 12/5/2023 Not started
6th Floor SMN 12/28/2023 Not started
7th Floor SMN 1/18/2024 Not started

Electrical Work at Wall

Block D Gr. Floor SMN 8/30/2023


1st Floor SMN 9/22/2023 Chase cutting done in 4 nos flat out of 8 and box fixing work in progress
2nd Floor SMN 10/14/2023 Done. Handed over to civil team for plaster work
3rd Floor SMN 11/5/2023 WIP

Block-E Gr. Floor SMN 9/14/2023


1st Floor SMN 10/7/2023 only 01 nos of flat completed out off 8 nos.
2nd Floor SMN 10/29/2023 Not done
3rd Floor SMN 11/20/2023 Not done
4th Floor SMN
Other Issues :
ACTIONS TO ACTUAL
SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
Schedule Date (R0): IN DAYS (Status Date: 05-02-2024)
BY : DATE

New Ajenda

Electrical revised
Not submitted
schedule required

Schedule

Waterproofing
revised schedule Not submitted
required

Block Work Sufficient Manpower not avaible


Manpower Block-D 16 nos flats ready for electrical work but only 4nos flats has been checked.
Electrical Work Sufficient Manpower not avaible
Very Slow progress in Block-D and Block-E electrical work.
Safety shoes not
Safety provided to all
workers

Outside scaffolding
material and Work Started at Block-E
building wrapping

Mock up flat Plaster Type-E plaster work Done.


and Construction of Type-G done.
Available
Electrical and ELV Door frame fixing completed.
duct NSW wall casting is in progress.

Note: All Progress Data up to dated 05-02-2024.


Deck Area