ACTIONS TO ACTUAL
SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN (R1) (R2) COMPLITION
Schedule Date (R0): IN DAYS (Status Date: 05-02-2024)
BY : DATE
Safety
Block-D
If larva found in any place of SMN working area
Dengue Care & SMN Continue process.
50,000/- will be charged instatntly.
Block-E
Staging Materials
for double height Block-C Civil Activity SMN 1/7/2024 Completed.
part.
Block-D
PART-01 Civil Activity 1/16/2024 1/24/2024 1/31/2024 2/2/2024 Completed.
PART-01 Fire Slab Civil Activity SMN 11/27/2023 1/7/2024 1/18/2024 Completed.
9TH FLOOR SLAB
PART-02 Civil Activity 1/20/2024 1/28/2024 2/10/2024 Slab reinforcement work is in progress,.
Block-E
PART-01 Civil Activity 1/11/2024 1/18/2024 1/22/2024 Done
9th Floor Slab SMN 12/12/2023
PART-02 Civil Activity 1/5/2024 1/9/2024 Done
PART-01 Civil Activity 2/8/2024 2/19/2024 Shuttering at reinforcement work is in progress.
10th Floor Slab SMN 1/12/2024
PART-02 Civil Activity 1/30/2024 2/3/2024 Reinforcement and shuttering work is in progress. Will be casted on 7th February.
Club
Done
Pile Cap and Raft SMN Civil Activity SMN 4/3/2023 02.05.2023 31.05.2023 30-06.2023 11/23/2023 -234
New Ajenda
Electrical revised
Not submitted
schedule required
Schedule
Waterproofing
revised schedule Not submitted
required
Outside scaffolding
material and Work Started at Block-E
building wrapping