Nozzle
Surface Cleaning Drill & Nozzle Groove Patching Nozzle Pressure VDF Flooring VDF Flooring
Sl no Area of Work Groove Cutting Breaking & T1 Coating T2 Coating
& Preparation fixing Work grouting Start Date End Date
Patching
6 Drain--Block-Club
Retaining Wall- WIP COMP COMP COMP COMP COMP 2/15/2024 2/19/2024
7 Block--E
Retaining Wall- WIP COMP COMP COMP COMP COMP 2/24/2024 2/28/2024
8 Block--D
Retaining Wall- 2/9/2024 2/13/2024 2/15/2024 2/17/2024 2/19/2024 2/21/2024 2/24/2024 2/28/2024
9 Block--C
Retaining Wall- 3/7/2024 3/11/2024 3/15/2024 3/17/2024 3/19/2024 3/21/2024 3/24/2024 3/28/2024
10 Club
11 Floor--Block-D 2/11/2024 2/15/2024 2/19/2024 2/21/2024 2/22/2024 2/26/2024 2/28/2024 3/3/2024 3/5/2024
13 Floor--Block-C 2/20/2024 2/28/2024 3/3/2024 3/5/2024 3/7/2024 3/9/2024 3/11/2024 3/15/2024 3/18/2024
14 Floor--Block-F 3/20/2024 3/28/2024 4/3/2024 4/5/2024 4/7/2024 4/9/2024 4/11/2024 4/15/2024 4/20/2024