WATERPROOFING WORK SCHEDULE FOR URBISHA SITE AS ON 22-01-24

Nozzle
Surface Cleaning Drill & Nozzle Groove Patching Nozzle Pressure VDF Flooring VDF Flooring
Sl no Area of Work Groove Cutting Breaking & T1 Coating T2 Coating
& Preparation fixing Work grouting Start Date End Date
Patching

1 Block-C/Sump Complete Complete Complete Complete Complete Complete Complete Complete

2 Block-F/Sump 3/1/2024 3/4/2024 3/6/2024 3/8/2024 3/10/2024 3/13/2024 3/15/2024 3/17/2024

3 Drain--Block-E 2/10/2024 2/13/2024 2/14/2024 2/16/2024 2/18/2024 2/21/2024 2/22/2024 2/24/2024

4 Drain--Block-D 2/11/2024 2/14/2024 2/15/2024 2/17/2024 2/19/2024 2/22/2024 2/23/2024 2/25/2024

5 Drain--Block-C 3/1/2024 3/3/2024 3/4/2024 3/6/2024 3/8/2024 3/11/2024 3/13/2024 3/15/2024

6 Drain--Block-Club

Retaining Wall- WIP COMP COMP COMP COMP COMP 2/15/2024 2/19/2024
7 Block--E

Retaining Wall- WIP COMP COMP COMP COMP COMP 2/24/2024 2/28/2024
8 Block--D

Retaining Wall- 2/9/2024 2/13/2024 2/15/2024 2/17/2024 2/19/2024 2/21/2024 2/24/2024 2/28/2024
9 Block--C

Retaining Wall- 3/7/2024 3/11/2024 3/15/2024 3/17/2024 3/19/2024 3/21/2024 3/24/2024 3/28/2024
10 Club

11 Floor--Block-D 2/11/2024 2/15/2024 2/19/2024 2/21/2024 2/22/2024 2/26/2024 2/28/2024 3/3/2024 3/5/2024

12 Floor--Block-E W/P 2/24/2024 2/12/2024 2/28/2024

13 Floor--Block-C 2/20/2024 2/28/2024 3/3/2024 3/5/2024 3/7/2024 3/9/2024 3/11/2024 3/15/2024 3/18/2024

14 Floor--Block-F 3/20/2024 3/28/2024 4/3/2024 4/5/2024 4/7/2024 4/9/2024 4/11/2024 4/15/2024 4/20/2024

15 Lift in Block E 4/20/2024

16 Lift in Block D 4/25/2024

17 Lift in Block C 4/30/2024

18 Lift in Block F 5/5/2024