UNICO VINA JSC

ID Task Task Name Duration Start Finish 2024 2025


Mode H2 H1 H2 H1 H2
1 RGB- COCA 221 days 4/1/2024 12/13/2024
2 Onsite survey 16 days 4/1/2024 4/18/2024
3 Situation of each machine 16 days 4/1/2024 4/18/2024
4 Clarify spare parts for each 16 days 4/1/2024 4/18/2024
machines in line
5 Check/ backup software for 6 days 4/15/2024 4/20/2024
machines in line
6 Check price 16 days 4/22/2024 5/9/2024
7 Check price Labeller 11 days 4/22/2024 5/3/2024
8 Check price for Bottle washer 11 days 4/22/2024 5/3/2024
9 Check price for spare parts 16 days 4/22/2024 5/9/2024
10 Calculation for related works 6 days 4/22/2024 4/27/2024
11 Quotation 4 days 5/13/2024 5/16/2024
12 Preparation for a quotation 3 days 5/13/2024 5/15/2024
13 Quotation submitted 1 day 5/16/2024 5/16/2024
14 Biding result notifications 1 day 5/31/2024 5/31/2024
15 Contract 11 days 6/3/2024 6/14/2024
16 Contract negotiated 6 days 6/3/2024 6/8/2024
17 Contract signed 1 day 6/10/2024 6/10/2024
18 Contract deposit 1 day 6/17/2024 6/17/2024
19 Material orders 10 days 6/18/2024 6/28/2024
20 Contract negotiation for Labeller 5 days 6/18/2024 6/22/2024
21 Contract negotiation for Bottle 5 days 6/18/2024 6/22/2024
washer
22 Contract negotiation for spare 10 days 6/18/2024 6/28/2024
parts and accessories
23 Preparation for overhaul works 15 days 7/1/2024 7/17/2024
24 Dismantling conveyors at Dry 3 days 7/1/2024 7/3/2024
parts area (after marking)
25 Remove existing washer out of the 12 days 7/1/2024 7/13/2024
line
26 Dismantling of platform of washer 3 days 7/1/2024 7/3/2024
27 Dismantling accessories of washer 6 days 7/1/2024 7/6/2024
(label remover, infeed table,
pump, ....)
28 Take out bottle carriers fro washer 2 days 7/8/2024 7/9/2024
(just 01 set remained between 15
sets)
29 Take out chain from washer 1 day 7/10/2024 7/10/2024
30 Separated washer body into 4-5 3 days 7/11/2024 7/13/2024
pcs (check onsite again) for
transportation

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Unico Vina - Project team
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
UNICO VINA JSC
ID Task Task Name Duration Start Finish 2024 2025
Mode H2 H1 H2 H1 H2
31 Move separated housing of 3 days 7/12/2024 7/15/2024
washer out of the line to specific
location by Coca decision
32 Dismantling of all conveyors in line 4 days 7/17/2024 7/20/2024
(after marking)
33 Spare parts received & overhaul 76 days 9/16/2024 12/12/2024
works started
34 Install equipment & conveyors at 7 days 11/1/2024 11/8/2024
Wet parts area (Filler area)
35 Install equipment & conveyors at 8 days 11/11/2024 11/19/2024
Dry parts area (Palletizer area)
36 Upgraded proggram upload 3 days 11/21/2024 11/23/2024
37 Install new Labeller, related 6 days 1/6/2025 1/11/2025
devices and accessories
38 Install new Bottle washer, related 11 days 1/6/2025 1/17/2025
devices and accessories
39 Electrical works 26 days 12/16/2024 1/14/2025
40 Commissioning 11 days 1/20/2025 1/31/2025
41 Acceptance 1 day 2/3/2025 2/3/2025

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Unico Vina - Project team
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2