Date : 31-01-2024

WING -04 PROGRAM SCHEDULE PROJECT SCHEDULE


Description Work
Sl.No Level Number of set Days Start date End date Remarks
Of Item Status
WING -04
1 Part-01 9 16/01/2024 Done
2 Part-02 8 2 17/01/2024 19/01/2024 Done
3 Column +00 to 2650 mm Part-03 10 2 20/01/2024 22/01/2024 Done
4 Part-04 10 2 23/01/2024 26/01/2024 Done
5 Part-05 10 2 27/01/2024 30/01/2024 Done

Total 47

6 Part-01 9 3 02/02/2024 06/02/2024


7 Part-02 8 3 07/02/2024 10/02/2024
8 Column +2650 to 5100mm Part-03 10 3 11/02/2024 15/02/2024
9 Part-04 10 3 16/02/2024 20/02/2024
10 Part-05 10 3 21/02/2024 25/02/2024

Total 47

11 Part-01 9 2 08/02/2024 10/02/2024


Part-02 8 2 12/02/2024 14/02/2024
Column +5100 to 5400mm
12 Part-03 10 2 17/02/2024 19/02/2024
13 Part-04 10 2 22/02/2024 24/02/2024
Part-05 10 2 27/02/2024 29/02/2024
Total 47
14 Lift wall reinforcement & Double Lift 1 5 31/01/2024 06/02/2024
Casting +00 to 2650 mm
15 Lift wall reinforcement & Double Lift 1 5 07/02/2024 13/02/2024
Casting +2650 to 5100 mm
16 Lift wall reinforcement & Single Lift 1 5 14/02/2024 20/02/2024
Casting +00 to 2650 mm
17 Lift wall reinforcement & Single Lift 1 5 21/02/2024 27/02/2024
Casting +2650 to 5100 mm
18 Stair -01 2 15 06/02/2024 23/02/2024

19 Beam Bottom Fixing 10 15/02/2024 25/02/2024


20 Slab Shuttering 10 18/02/2024 28/02/2024
21 Beam Reinforcement 6 26/02/2024 03/03/2024
22 Slab Bottam Reinforcement 4 04/03/2024 08/03/2024
23 Electrical work 1 08/03/2024 09/03/2024
24 Top Reinforcement 3 09/03/2024 12/03/2024
25 Out Side Boad Fixing 1 13/03/2024 14/03/2024
26 Slab Casting for Wing-04 15/03/2024 15/03/2024
Date : 31-01-2024
WING -05 PROGRAM SCHEDULE PROJECT SCHEDULE
Description Work
Sl.No Level Number of set Days Start date End date Remarks
Of Item Status
WING -05
Part-01 10 3 25/02/2024 28/02/2024
Part-02 10 3 29/02/2024 03/03/2024
Column +00 to 2650 mm
Part-03 10 3 04/03/2024 07/03/2024
Part-04 10 3 08/03/2024 11/03/2024

Total 40

Part-01 10 3 12/03/2024 16/03/2024


Part-02 10 3 17/03/2024 20/03/2024
Column +2650 to 5100mm
Part-03 10 3 21/03/2024 25/03/2024
Part-04 10 3 26/03/2024 30/03/2024

Total 40

Part-01 10 3 19/03/2024 23/03/2024


Part-02 10 3 24/03/2024 27/03/2024
Column +5100 to 5400mm
Part-03 10 3 28/03/2024 31/03/2024
Part-04 10 3 01/04/2024 04/04/2024

Total 40
Lift wall reinforcement & Double Lift 1 5 31/03/2024 06/04/2024
Casting +00 to 2650 mm
Lift wall reinforcement & Double Lift 1 5 07/04/2024 13/04/2024
Casting +2650 to 5100 mm
Lift wall reinforcement & Single Lift 1 5 14/04/2024 20/04/2024
Casting +00 to 2650 mm
Lift wall reinforcement & Single Lift 1 5 21/04/2024 27/04/2024
Casting +2650 to 5100 mm
Stair -01 2 15 16/03/2024 02/04/2024

Beam Bottom Fixing 8 14/04/2024 23/04/2024


Slab Shuttering 8 17/04/2024 25/04/2024
Beam Reinforcement 5 23/04/2024 28/04/2024
Slab Bottam Reinforcement 3 29/04/2024 02/05/2024
Electrical work 1 02/05/2024 03/05/2024
Top Reinforcement 3 03/05/2024 06/05/2024
Out Side Boad Fixing 2 07/05/2024 09/05/2024
Slab Casting for Wing-05 10/05/2024 10/05/2024

Note : IF STAGING MATERIALS IS AVAILABLE (THIS MONTH) THEN WING -5 1ST FLOOR SLAB CASTING
WILL BE DONE 15-04-2024.