Lift wall reinforcement & Double Lift 1 5 31/03/2024 06/04/2024
Casting +00 to 2650 mm
Lift wall reinforcement & Double Lift 1 5 07/04/2024 13/04/2024
Casting +2650 to 5100 mm
Lift wall reinforcement & Single Lift 1 5 14/04/2024 20/04/2024
Casting +00 to 2650 mm
Lift wall reinforcement & Single Lift 1 5 21/04/2024 27/04/2024
Casting +2650 to 5100 mm
Stair -01 2 15 16/03/2024 02/04/2024
Note : IF STAGING MATERIALS IS AVAILABLE (THIS MONTH) THEN WING -5 1ST FLOOR SLAB CASTING
WILL BE DONE 15-04-2024.