LIN INTERNATIONAL SDN BHD Form TYL/IF10


Sheet No: 1 of 2
TO: Kiaramas Development Sdn Bhd

cc : T.Y.Lin (HQ) & Urusreka Architect

WEEKLY SITE REPORT

CONTRACT PERIOD : 24 Weeks


PROJECT:
Kiaramas deDaun- Tower A (P1196-P5) COMMENCEMENT DATE : 12.6.2023

CONTRACTOR: COMPLETION DATE : 27.11.2023


CONSTRUCTION WEEK NO: DATE
HAB Construction Sdn Bhd
6 FROM: 24/7/2023
TO: 30/7/2023
WORK FORCE / PLANT & EQUIPMENT PLANT & MATERIALS
DAY M T W T F S S ON SITE SHORTAGES
PROJECT MANAGER 1 1 0 1 1 1 0
SITE ENGINEER 0 0 0 0 0 0 0
SITE SUPERVISOR 1 1 1 1 1 1 0
SAFETY OFFICER 0 0 0 0 0 0 0
SURVEYOR 0 0 0 0 0 0 0
GENERAL WORKERS 4 4 4 4 4 4 0
CARPENTER 14 13 13 13 13 13 0
BARBENDER 6 6 6 6 6 6 0
CONCRETOR 3 3 3 3 3 3 0
SCAFFOLDER WORKERS 0 0 0 0 0 0 0

BARBENDING MACHINE 1 1 1 1 1 1 0
BAR CUTTING MACHINE 1 1 1 1 1 1 0
AIR COMPRESSOR 1 1 1 1 1 1 0

OPERATORS 2 2 2 2 2 2 0
CRAWLER CRANE 1 1 1 1 1 1 1
EXCAVATOR 1 1 1 1 1 1 1
WEATHER Reasons For delay
TOTAL HOURS OF RAIN
DELAY (HRS) DUE TO RAIN
DELAY (HRS) - OTHERS

STATUS ON MATERIAL TESTING

SAFETY ISSUE

Rev.: 4 Effective Date: 1 February 2009


T.Y.LIN INTERNATIONAL SDN BHD Form TYL/IF10
Sheet No: 2 of 2
REPORT ON WORK IN HAND AND PROGRESS
MONDAY: Level P4 - Install rebar at Zone 1
24-Jul Level P4 - Install column rebar G/L A-B/1-3
Level P5 - Install scaffolding for slab at Zone 1
Level P5 - Casting Lift wall at Zone 1
Level P3 - Install beam at zone 1A and 1B

TUESDAY: Level P4 - Continue install rebar slab at Zone 1


25-Jul Level P3 - Intall beam rebar at Zone 1B,1A at G/L E-D/4-10
Level P4 - Install column formwork at WA1, WA2 at zoen 3
Level P5 to Level P3 - erect DOKA scaffold at Zoen 2
Casting wash tough entrance

WEDNESDAY: Level P4 - Casting slab at Zoen 1


26-Jul Level P4 - Casting column WA1, WA2 at Zone 3
Level P3 - Install rebar slab / colunb at Zone 1B
Level P4 - Install fomwork for slab support at Zone 2

THURSDAY Level P4 - Install slab rebar at G/L A-E/4-7


27-Jul Level P3 - Install rebar beam at Zone 1A & 1B
Level P4 - Install coumn rebar at Zone 1
Level P3 - Install formwork beam at Zone 1B

FRIDAY: Level P4 - Installed formwork to beam and slab at Zone 2, G/L A-D/7-11
28-Jul Level P3 Installed beam rebar to Zone 1B and 1A
Level P4 - Installed scaffolding for beam support P3 slab at Zone 1 and 2
Level P3 - casting column at Zoen 1, G/L B-D/6-8
Level P4 - Install rebar column at zone 1 lift wall

SATURDAY: Level P4 - Casting column Zone 3 at G/L D-E/4-5


29-Jul Level P3 - Backfilling slab at G/L D-F/9-11
Level P4 - Install rebar coumn at G/L B-E / 4-8
Level P4 - Install rebar beam at G/L A-B/8-11
Level P4 - casting slab at G/L A-E/4-5
Level P3 - casting beam zone 1A and 1B

SUNDAY:
30-Jul No Activiteis

Site
Memo Description Drawing Received Source

Prepared By : Verified By :
Name : Au Koon Yew Name : Au Koon Yew
Signature : Signature :
Date : 31.7.23 Date : 31.7.23