Professional Documents
Culture Documents
BARBENDING MACHINE 1 1 1 1 1 1 0
BAR CUTTING MACHINE 1 1 1 1 1 1 0
AIR COMPRESSOR 1 1 1 1 1 1 0
OPERATORS 2 2 2 2 2 2 0
CRAWLER CRANE 1 1 1 1 1 1 1
EXCAVATOR 1 1 1 1 1 1 1
WEATHER Reasons For delay
TOTAL HOURS OF RAIN
DELAY (HRS) DUE TO RAIN
DELAY (HRS) - OTHERS
SAFETY ISSUE
FRIDAY: Level P4 - Installed formwork to beam and slab at Zone 2, G/L A-D/7-11
28-Jul Level P3 Installed beam rebar to Zone 1B and 1A
Level P4 - Installed scaffolding for beam support P3 slab at Zone 1 and 2
Level P3 - casting column at Zoen 1, G/L B-D/6-8
Level P4 - Install rebar column at zone 1 lift wall
SUNDAY:
30-Jul No Activiteis
Site
Memo Description Drawing Received Source
Prepared By : Verified By :
Name : Au Koon Yew Name : Au Koon Yew
Signature : Signature :
Date : 31.7.23 Date : 31.7.23