PROJECT: SUPPLY, DELIVERY, INSTALLATION, TESTING AND

Package : Building Work


COMMISSIONING FOR THE PROPOSED 33kV SSU BUILDING
Doc Ref No. : TBK-PSSU-JMS-005
Date Issued : 15/04/2020
TAN BOCK KWEE & SONS SDN BHD
PETRON MALAYSIA REFINING AND
MARKETING BHD
Revision : A Page 1 of 4

DOCUMENT TITLE:

METHOD STATEMENT
FOR EXCAVATION, BACKFILLING
AND COMPACTION WORK

A 15-APR-2020 Issue For Approval


Prepared by Review by Approved by
Rev Date Description
TBK PETRON PETRON
   
         

EXCAVATION WORK TBK-PSSU-JMS-005


PROJECT: SUPPLY, DELIVERY, INSTALLATION, TESTING AND
Package : Building Work
COMMISSIONING FOR THE PROPOSED 33kV SSU BUILDING
Doc Ref No. : TBK-PSSU-JMS-005
Date Issued : 15/04/2020
TAN BOCK KWEE & SONS SDN BHD
PETRON MALAYSIA REFINING AND
MARKETING BHD
Revision : A Page 2 of 4

1. SCOPE OF WORK

1.1 General Description


This method statement describing the construction procedures, the equipment,
machinery and manpower required for the excavation works in PETRON
ULSADO Project.

1.2 Plant and Equipment

Item Description Qty Purposes


1 Dewatering pump 1nos Pumping water
2 Plate compactor 3 nos Compaction work
3 Hand tools (shovel, wheel barrow) 4 set Manual excavation work
4 Canvas sheet As required Shoring work
5 Excavator 1nos To excavate
6 Lorry 1nos To transport earth
7 Backhoe 1 nos To excavate

Numbers and quantities of above equipment will be selected to suit the contract
program and available works areas.

1.3 Manpower Resources.

No Description Qty Job Function


1 Site Supervisor 1 pax Coordinating and supervising site activities
Handle technical issues at site.
2 Safety Supervisor 1 pax Monitoring the construction activities related
to safety matters
3 Workers 5 pax Excavation works
4 Machine Operator 1 pax Excavation works
5 Drivers 2 pax Soil movement.

1.4 CONSTRUCTION STEP

1.4.1 General

Prior to the manual and mechanical excavation work, the site supervisor shall carry
out preliminary studies for potential risks involve on the activities area.

The related area shall be hard barricades and proper signage displayed at the sight
to prevent heavy traffic, tripping and potential hazards that maybe found on site and
the site precaution measures are needed. (Please refer to JSA)

1.4.2 Excavation Works

o The area to be excavated shall be properly marked and clear before starting
the works.

EXCAVATION WORK TBK-PSSU-JMS-005


PROJECT: SUPPLY, DELIVERY, INSTALLATION, TESTING AND
Package : Building Work
COMMISSIONING FOR THE PROPOSED 33kV SSU BUILDING
Doc Ref No. : TBK-PSSU-JMS-005
Date Issued : 15/04/2020
TAN BOCK KWEE & SONS SDN BHD
PETRON MALAYSIA REFINING AND
MARKETING BHD
Revision : A Page 3 of 4

o The depth of excavation shall be periodically checked by a supervisor to


avoid over excavation.

o Manual and machine excavation on the require dimension.

o Excavated area shall be hard barricades and with proper signage display to
prevent falling hazards.

o Excavated soil shall be stockpile not closer than 1 m away from the
excavation hole wall and dispose off when achieved required depth.

o When the excavation is completed, trimmed to the required level and


dimension, for inspection purposes.

o Before the compaction starts, it shall make sure that the excavated level is
free from standing water.

o Compaction shall be carried out using plate compactor

o For foundation, as soon as the excavation reaches the required elevation the
surface shall be level and shall be compact.

o Housekeeping to surrounding area on daily basis.

o All excavated area is to be maintained at all times until backfilling.

o Proper access & egress to be provided (Ladder)

1.4.3 Backfilling work

o Prior to backfilling, the compacted surface shall be well prepared without


stagnant of water and debris.

o Sub grade surface shall be well prepared in order to commence backfilling


activities using similar excavated material which have been carry out analysis
at laboratory and approved to use. Care shall be taken to remove bolder,
vegetation and any other deleterious materials.

o Backfilling shall be placed in layers not more than 300 mm thick in loose form,
followed by compaction test (Field Density Test). Subsequence backfill layer
shall carry out with same sequence till the require elevation

EXCAVATION WORK TBK-PSSU-JMS-005


PROJECT: SUPPLY, DELIVERY, INSTALLATION, TESTING AND
Package : Building Work
COMMISSIONING FOR THE PROPOSED 33kV SSU BUILDING
Doc Ref No. : TBK-PSSU-JMS-005
Date Issued : 15/04/2020
TAN BOCK KWEE & SONS SDN BHD
PETRON MALAYSIA REFINING AND
MARKETING BHD
Revision : A Page 4 of 4

1.4.4 Dewatering

o Prior to prevent underground water, rain water stagnant in the surface and will
create disrupted to the progress of whole activities.

o During excavation process, perimeter drainage system with pump sump shall
be provided for dewatering purpose in order to prevent water stagnant on the
excavated surface

2 QUALITY PLAN
N/A

3 SAFETY AND HEALTH

The following safety measures precautions shall be strictly observed.

 Daily toolbox shall be conduct.

 Use of appropriate Personal Protective Equipment (PPE) such as coverall, Safety


Helmets, Safety Glass, Safety Shoes/Boots, Ear Plug, Dust Mask, etc relevant to the
work being carried.

 Ample signboards, warning, safety instruction, etc, shall be made available at all
strategic locations.

 Only authorized personnel are to operating equipment/machinery.

 Signalman shall be placed at busy traffic area to guide traffic.

 All equipments used must be first inspected before operation.

 Daily Housekeeping

EXCAVATION WORK TBK-PSSU-JMS-005