CAR WHEEL WASHER AREA

LOGISTIC LAY OUT FOR CONCRETE POURING SABB P-142 PROJECT Concrete
Check
Point
SITE ROAD

Legend Symbol EXIT


Flagman

Concrete
Check
Point
Concrete
pump

Ready Mix
Truck
Vibrator

Location: ZONE-05 AREA-07


G
Description: 03 Concrete Pumps – UNIBETON Ready Mix A
Pump-01 56 meter Boom Length, T
Pump-02 56 meter Boom Length, E
1
Pump-03 56 Meter Boom Length,
12 Vibrators -03 Power Floats- 05 Tower lights
Stand By Equipments:
01 Concrete Pump (56meter), 05-Vibrators, 02-Power Floats
CONCRETE QUANTITY-900M³
Type of Concrete: C50MPA OPC+35% FLYASH+7%MS
Proposed Pouring will be Afternoon 06TH OCT 2018 Approx. 04:00PM
10-Hours pouring duration.
Traffic Management: 05 number Flagmans to control the traffic movement.
Pouring Area cordon off by Reflective Traffic Cone & PVC barriers and barricade
flasher lights. Stand by Safety Assistant and Safety Inspector.

Concrete Concrete
Pump -01 Pump -02

Concrete
Pump -03 ENTRY OF CONCRETE TRAILERS FROM CHECK POINT TO PUMP
ENTRY OF CONCRETE TRAILERS FROM SERVICE ROAD TO CHECK POINT