Current Status
1- CIVIL
- Sleepers to be completed between tanks ( ---- M3)
2- STRUCTURAL
- All Strectural rection completed
- Balance Degasser platform erection ( 32 MT )
3- AG PIPING WORKS
- All Pipes availabe at site
- Balance to deliver 90 Flanges , 17 elbows and 8 Redures ( ETA - 20-Dec-21)
- Balsting and Painting to be expedited
4- TANK WORKS
- Work front Availabe
- No sub-contractor working since 3 Months
LEAN MEG TANK - B
500049_NRP_ONGC_Site Planning