You are on page 1of 1

OMF PRIORITY COMPLETION SYSTEMS 1-Dec-21

Sl.no Description Commodity UOM Scope Completed Balance Remarks


Civil RCC Concrete M3 396 396 0
1 Rich MEG Feed Tank - A Tank Fab./Blasting MT 231 154 -77 No Manpower
Tank Erection & Welding MT 231 133 -98 No Manpower
BY-PASS LINE Civil RCC Concrete M3 396 396 0
RICH MEG RICH MEG 2 Rich MEG Feed Tank - B Tank Fab./Blasting MT 231 119 -112 No Manpower
TANK - A TANK - B
Tank Erection & Welding MT 231 0 -231 No Manpower
Civil RCC Concrete M3 8 8 0
3 Rich MEG Feed Pump Pump Delivery No 1 0 -1
Pump Erection & Alignment No 1 0 -1
Civil RCC Concrete M3 8 8 0
DEGASSER 4 Rich MEG Transfer Pump Pump Delivery No 1 0 -1
Pump Erection & Alignment No 1 0 -1
RICH MEG Civil RCC Concrete M3 64 64 0
TRANSFER PUMP RICH MEG 5 Lean MEG Tank- A Tank Fab./Blasting MT 124 124 0 No Manpower
FEED PUMP Tank Erection & Welding MT 124 97 -27 No Manpower
Civil RCC Concrete M3 64 64 0
PLR AREA 6 Lean MEG Tank- B Tank Fab./Blasting MT 124 96 -28 No Manpower
HP LEAN MEG Tank Erection & Welding MT 124 80 -44 No Manpower
PRODUCT PUMP Civil RCC Concrete M3 20 0 -20
7 Lean MEG Transfer Pump Pump Delivery No 1 0 -1
8" RICH MEG LINE Pump Erection & Alignment No 1 0 -1
Civil RCC Concrete M3 32 32 0
Structural Fabrication MT 31 0 -31 Under Manufacturing
6" LEAN MEG LINE
8 Degasser Structural Erection MT 31 0 -31 Mat. Not available
Equipment Delivery No 1 0 -1
Equipment Erection No 1 0 -1
LEAN MEG LEAN MEG Civil RCC Concrete M3 14 0 -14
LEAN MEG TANK - A TANK - B 9 Lean MEG Filter Equipment Delivery No 1 0 -1
FILTER Equipment Erection No 1 0 -1
LEAN MEG Civil RCC Concrete M3 110 110 0
TRANSFER PUMP 10 HP Lean MEG Product Pump Pump Delivery No 1 0 -1
Pump Erection & Alignment No 1 0 -1
Civil RCC Concrete M3 0 0 0
11 Lean MEG Tank - VA-51 Tank Fab./Blasting MT 0 0 0
Tank Erection & Welding MT 0 0 0
Piping Delivery ID 3,441 3,441 0 All Pipes available
LEAN MEG
Bal.-90 Flanges, 17 elbow
TANK Flanges, Elbow & Reducer No 443 328 -115
& 8 Reducers
VA-51 12 8" Rich MEG Line Piping Erection (Filed) IM 5,768 0 -5,768
Piping Welding (Shop & Field) ID 3,441 1,314 -2,127 24 ID Painting Completed
Piping Delivery ID 148 148 0 All Pipes available
Piping Erection (Filed) IM 360 0 -360
13 6" Rich MEG Line
Piping Welding (Shop & Field) ID 148 36 -112

Current Status
1- CIVIL
- Sleepers to be completed between tanks ( ---- M3)

2- STRUCTURAL
- All Strectural rection completed
- Balance Degasser platform erection ( 32 MT )

3- AG PIPING WORKS
- All Pipes availabe at site
- Balance to deliver 90 Flanges , 17 elbows and 8 Redures ( ETA - 20-Dec-21)
- Balsting and Painting to be expedited

4- TANK WORKS
- Work front Availabe
- No sub-contractor working since 3 Months
LEAN MEG TANK - B

LEAN MEG TANK - A


RICH MEG TANK - A
Pre-Cast RCC Sleeprs Balance
RICH MEG TANK - B
Pre-Cast RCC Sleeprs Completed

500049_NRP_ONGC_Site Planning

You might also like