You are on page 1of 9

JOB NO: SAMPLE TAKER OFF:

IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL
Drawing No: CERWK/PD/101/01-05

Taking off list


Unit MySMM
ROADS, DRIVEWAYS AND CARPARKS
1 Bulk excavation m2 23 01 01 01 01 00
2 Subgrade m2 23 01 01 02 01 00
3 Sub-base, sand blinding m2 23 01 01 03 01 00
4 Road base Crusher run m2 23 01 01 04 01 00
5 Asphaltic concrete binder course m2 23 01 01 06 01 00
6 Asphaltic concrete wearing course m2 23 01 01 08 01 00
7 Thermoplastic reflective paint, edge line m 23 01 01 09 01 00
8 Thermoplastic reflective paint, stop line m 23 01 01 09 02 00
9 Thermoplastic reflective paint, centre line, double line m 23 01 01 09 03 00
10 Thermoplastic reflective paint, centre line, intermitten m 23 01 01 09 03 00
11 Thermoplastic reflective paint, lane line, intermitten line m 23 01 01 09 00 00
12 Thermoplastic reflective paint, turning direction arrow; rightmturn
23 01 01 09 06 00
13 Thermoplastic reflective paint, slow down line m 23 01 01 09 00 00
14 PC concrete kerb m 23 01 01 09 01 00
15 Concrete edging m3 09 01 01 16 01 00
16 Concrete edging m3 09 01 01 16 01 00
17 Road signage, 'BERHENTI' nr 23 02 01 01 01 01

RC RETAINING WALL

EXCAVATION
1 Excavate for retaining walls and bases m3 04 03 01 05 01 00
2 Excavate for retaining walls and bases m3 04 03 01 05 01 00
3 Extra over excavation in rock m3 04 03 01 05 01 00
4 Filling with imported selected material m3 04 04 01 01 01 01
5 Filling with granular material m3 04 04 01 01 01 01
6 Filling with excavated material m3 04 04 01 00 01 01
m2 04 05 02 01 01 00
WALL
7 Reinforced con. in wall m3 09 01 02 12 01 00
8 Formwork to sides of walls m2 09 03 01 05 01 00
9 T16 Reinforcement bar high tensile steel kg 09 04 02 08 01 00
10 T12 Reinforcement bar high tensile steel kg 09 04 02 08 01 00
11 uPVC weep pipes nr 09 06 02 01 01 00
12 Porous pipe m 09 06 00 00 00 00
13 Waterproofing laid on concrete surface m2 04 05 02 01 01 00
SLAB
14 Concrete in blinding m3 09 01 01 02 01 00
15 Concrete in slab m3 09 01 02 08 01 00
16 Formwork to edge of slab m2 09 03 01 16 01 00
17 T16 Reinforcement bar mild steel kg 09 04 01 05 01 00
18 T12 Reinforcement bar high tensile steel kg 09 04 02 05 01 00
19 T10 stirrup reinforcement bar mild steel kg 09 04 01 05 02 00
20 Waterproofing laid on concrete surface m2 04 05 02 01 01 00

Page 1
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

Roads, driveways and carpark


Asphaltic concrete binder
Bulk excavation; to road course;laid on crusher run to
formation level to form subgrade; gradient and crossfall, well
get out, load and cart away rolled and compacted, 60mm
surplus excavated material from thick bitumen macadam
site, oversite; average 460mm 23 01 01 06 01 00
deep
1785.00 (Qty same as exc
23 01 01 01 01 00
Depth
sub-base = 50 Asphaltic concrete wearing
crusher run = 300 course; laid on binder course to
base course = 60 gradient and crossfall, well rolled
waering course = 50 and compacted; including a layer
of approved prime coat , 40mm
Total depth = 460mm thick dense bitumen macadam

½ Length 23 01 01 08 01 00
238.00 Trapezium 1785.00 (Qty same as exc
15.00 1,785.00 L1 = 140.00
L2 = 143.00
Overall l = 283 Prepare and apply thermoplastic
Height/width = 15.00 reflective paint on the surface
ofpremix; as shown in Drawing
CERWK/PD/101/03-04, 150mm
wide edge line
Grade road formation level to
gradient and crossfall; well
rolled, on subgrade 23 01 01 09 01 00
23 01 01 02 01 00 (Straight shape top side -scale
140.00
1785.00 (Qty same as exc
143.00 (Straight shape bottom side -
283.00 scale
Sand blinding; spread and
levelled to fall, well rolled and Prepare and apply thermoplastic
compacted, 50mm thick reflective paint on the surface
23 01 01 03 01 00 ofpremix; as shown in Drawing
CERWK/PD/101/03-04, 300mm
1785.00 (Qty same as exc wide stop line

23 01 01 09 02 00

Crusher run; spread and levelled 7.00 (scale


to fall, well compacted, 300mm
thick
23 01 01 04 01 00
1785.00 (Qty same as exc

Page 2
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

Prepare and apply thermoplastic Prepare and apply thermoplastic


reflective paint on the surface if odd shape like reflective paint on the surface
ofpremix; as shown in Drawing chevron, can be ofpremix; as shown in Drawing
CERWK/PD/101/03-04, 150mm measure in area CERWK/PD/101/03-04, 300mm
wide centre line wide slow down line at 600mm
(m2) - apply the
spacing
rules for painting to
23 01 01 09 03 00 surfaces
2 142-8.00 = 134 23 01 01 09 00 00
134.00 268 (straight line (scale 1 slow down line
25

Prepare and apply thermoplastic 7.00 175.00


reflective paint on the surface
ofpremix; as shown in Drawing Precast concrete kerbs with one
CERWK/PD/101/03-04, 150mm side battered and rounded on
wide lane line at 2000m spacing one edge cost inconvenient
length and jointed in cement and
sand mortar (1:3); lain on and
including plain in-situ concrete
23 01 01 09 00 00 Grade C 20P bed; forming outlet
141.00 top (scale lane line) opening at centre; painting with
142.00 bottom (scale lane line) approved black and white
emulsion paint in layers on
283.00 exposed surface; as shown in
Drawing CERWK/PD/101/02,
overall size 600 length x 200
Prepare and apply thermoplastic wide x 300 mm high
reflective paint on the surface
ofpremix; as shown in Drawing
CERWK/PD/101/03-04, 150mm
wide centre line at 1200mm
23 01 01 09 01 00
spacing
283.00 (Qty same as edge line

2 23 01 01 09 03 00
8.00 16.00 (intermitten centre
Mass in-situ concrete Grade
C20 P, in kerbs, including
assume concrete kerb
formwork; finished fair to
Grade C20
Prepare and apply thermoplastic exposed surfaces, 100 x
reflective paint on the surface 300mm dimension as shown
ofpremix; as shown in Drawing in Drawing
CERWK/PD/101/03-04, turning CERWK/PD/101/02
directional arrow; right
2.00 2.00 09 01 01 16 01 00

283.00 (Length of kerb


23 01 01 09 06 00 0.10
0.30 8.49

Page 3
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

Mass in-situ concrete Grade REINFORCED CONCRETE


C20 P, in kerbs, including RETAINING WALL
formwork; finished fair to
exposed surfaces, 100 x EXCAVATION
100mm dimension as shown
in Drawing Excavation for retaining walls
CERWK/PD/101/02 and bases, not exceeding
09 01 01 16 01 00 2.00m total depth
283.00 (Length of kerb 04 03 01 05 01 00
0.10 Depth
0.10 2.83 FL - GL = 40.00-39.00 =1.00
add below ground = 0.45
add slab = 0.25
Road signage add blinding = 0.05
Total depth = 1.75m

Length of rc wall = 140.00m


Supply and install road (scale)
signage, supported by mild
steel post with one end Width = 1.50m
embedded in mass concrete 140.00
footing; including all 1.50
necessary excavation, 1.75 367.50
formwork, welding and
fittings; painting to exposed
surfaces, the other end Excavation for retaining walls
mounted with non-illuminated and bases, not exceeding
retro-reflective aluminium 2.00m total depth
sheet; as shown in Drawing 04 03 01 05 01 00
CERWK/PD/101/04 and in Depth of slab projection = 0.25
accordance to Local
Authority's requirement for add blinding = 0.05
'BERHENTI' sign Total depth = 0.30m
140.00
1 1.50
23 02 01 01 01 01 0.30 63.00

Excavation for extra over for


assume 5% rock by breaking up rock at any
pneumatic tools depth, using pneumatic tools;
to Authorities approval and by
licenced specialist; removing
from site
5 04 03 01 05 01 00
100 430.50 21.53 total exc volume = 367.5 +
63.0
Page 4
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

Filling with imported selected


Filling with excavated material
material to the S.O approval,
to the S.O approval, compact
compact to the required levels
to the required levels
including the formation of
including the formation of
slopes, 225 x 225 x 225
slopes
crushed aggregate wrapped
round with geotextiles 04 04 01 00 01 01
membrane earth side
04 04 01 01 01 01 140.00 Length = 140.00
number of boxes for 0.75 Width = 1.50-0.50-0.25
horizontal length @ 3000 1.45 152.25 Depth = 40.00-39.00+0.45

(wall length/ spacing) + 1 ddt sand volume


(140.00/3.00) + 1 = 48no 140.00 Length = 140.00
48 0.30 width = 0.30
0.23 1.15 48.3 depth = 40.00-39.00+0.45-0.30
0.23
0.23 0.58 road side
140.00
0.50
0.45 31.5
Filling with granular material, 135.45
to the S.O approval, compact
to the required levels
including the formation of
slopes, 300mm thick sand
filter
04 04 01 01 01 01
Height of sand filling
(G-FL) + below ground wall
height - 300mm top earth
(40.00-39.00) + 0.45 -0.30
= 1.15m

140.00
0.30
1.15 48.30

48 ddt crushed aggregate box


0.23
0.23
0.23 0.58
47.72

Page 5
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL
CONCRETE WALL
T16 -150 main bar in wall
no of main bar in wall
Vibrated reinforced in-situ
concrete; Grade C25 P in wall (wall length - cc both sides ) + 1
09 01 02 12 01 00 spacing
Length = 140.00 (scale) (140.00-0.025-0.025) + 1
0.15
Width = 250mm = 934 nos

Height = top of wall until the top of bases slab = 2.258m x 934nos x 2sides
Height = (GL-FL)+ underground 1.579kg/m
wall + above FL =6660.13kg
= 40.00-39.00m+ 0.45 + 0.30 (all the calculation insert in
140.00 =1.75m reinforcement schedule
0.25
1.75 61.25

High tensile steel bar


reinforcement, in walls, 16mm
diameter;straight and bent
Formwork; sawn class F1 to
09 04 02 08 01 00
faces of walls, vertical
2 09 03 01 05 01 00 6660.13 (qty from rebar schedule
140.00 both sides
1.75 490.00 09 04 02 08 01 00

2 T12-150 distribution bar in wall


0.25 both end Length of distribution bar
1.75 0.88 add 40 Ø overlapped
490.88 every 12m horizontal wall length = 140.00
bar length
(140.00/12.00 )- 1 = ddt concrete cover both side
11no 2/0.025 = 0.05
40 x 0.012 x 11no = 5.28 add bend both side
T16 -150 main bar in wall 2/10/0.012 = 0.24
Length add 40 Ø overlapped every 12m
40 x 0.012 x 11 nos = 5.28
Height GL-FL 40.00-39.00 = 1.00 Total length = 145.47m
Add wall above ground = 0.30
Add bar underground = 0.45 no of distribution bar in wall
assume concrete cover
25mm Add bar in slab = 0.25
bend 10d Ddt cc top and bottom (wall height - cc both sides ) + 1
overlapped over 12m 2/0.025 = 0.05 spacing
length is 40d Ddt slab distribution bar = 0.012
Add bend top and bottom wall height as before
2/10/0.016 = 0.32 GL-FL + wall above ground +
Total length = 2.258 wall below ground
40.00-39.00+0.30+0.45 = 1.75m

Page 6
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

no of main bar in wall


Moisture barrier, 2 coats of
(wall height - cc both sides ) + 1 damp proofing bituminous
spacing coating on earth face of
(1.75-0.025-0.025) + 1 concrete surface of retaining
0.15 wall
12 nos 04 05 02 01 01 00
Wall length
= 145.47m x 12nos x 2sidesx 0.888kg/m Height = surface that face with
=3100.26kg earth
Internal surface = (GL-FL) +
(all the calculation insert in underground wall height
reinforcement schedule =40.00-39.00 +0.45 = 1.45
External surface = underground
wall = 0.45
140.00 Internal
High tensile steel bar 1.45 203
reinforcement, in walls, 12mm
diameter;straight and bent 140.00 External
09 04 02 08 01 00 0.45 63
3100.26 (qty from rebar schedule
2 0.25 Edge wall
09 06 02 01 01 00 1.45 0.73
266.73
uPVC weep pipes with
splayed end, cast into in-situ CONCRETE SLAB
concrete structures, 100mm
diameter assume concrete
09 06 02 01 01 00 blinding C15 Mass in-situ concrete; Grade
number will same as crushed C15 P in blinding
aggregate box filling 140.00 09 01 01 02 01 00
number of boxes for 1.50
horizontal length @ 3000 0.05 10.50

(wall length/ spacing) + 1


48 (140.00/3.00) + 1 = 48no
assume concrete 25 Vibrated reinforced in-situ
concrete; Grade C25 P in
slab
Porous pipe wrapped round 09 01 02 08 01 00
with geotextile membrane and 140.00 main slab
extend to edge of 1.50
embankment or nearest drain 0.25 52.50
09 06 00 00 00 00
(laid along the wall length, 140.00 bottom slab
140.00 horizontally 0.25
0.30 10.50
63.00
Page 7
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

(all the calculation insert in


reinforcement schedule
Formwork ; sawn class F1 to
edges of slab
09 03 01 16 01 00 High tensile steel bar
slab edge A = 250 + 50 mm reinforcement, in slabs,
lean = 300mm 16mm diameter;straight and
bent
slab edge B = 250 + 50 mm 09 04 01 05 01 00
lean + 250 + 50= 600mm
5029.02 (qty from rebar schedule
140.00 side A
0.30 42.00 T12-150 distribution bar in slab
Length of distribution bar
140.00 side B add 40 Ø overlapped
0.60 84.00 every 12m horizontal slab/wall length = 140.00
bar length
2 (140.00/12.00 )- 1 = ddt concrete cover both side
1.50 front/back face 11no 2/0.025 = 0.05
0.30 0.90 40 x 0.012 x 11no = 5.28 add bend both side
2/10/0.012 = 0.24
2 0.25 projection edge add 40 Ø overlapped every 12m
0.30 0.15 40 x 0.012 x 11 nos = 5.28
127.05 Total length = 145.47m

09 04 01 05 02 00 no of distribution bar in slab

T16 -150 main bar in slab (slab width - cc both sides ) + 1


Length spacing
slab width = 1.50
ddt end slab = 0.25 (1.50-0.025-0.025) +1
ddt cc one side 0.15
0.025 = 0.025 11 nos
add projection bar 10d
10 / 0.016 =0.16 = 145.47m x 11nos x 2sidesx
add bend both end (10d) 0.888kg/m
2/10/0.016 = 0.32 2841.90kg
Total length = 1.71m (all the calculation insert in
reinforcement schedule
no of main bar in slab

(wall length - cc both sides ) + 1 High tensile steel bar


spacing reinforcement, in slabs,
(140.00-0.025-0.025) + 1 12mm diameter;straight and
0.15 bent
= 934 nos 09 04 02 05 01 00
2841.9 (qty from rebar schedule
= 1.71m x 934nos x 2sides x 1.579kg/m
5029.02kg
Page 8
JOB NO: SAMPLE TAKER OFF:
IBTISAM
JOB TITLE: DATE : MAY
JAN
ELEMENT:
WORK SECTION 23: SITE WORK ( ROADWORK, DRIVEWAYS AND CARPARKS)
WORK SECTION 04 & 09 : RC RETAINING WALL

T10 -150 stirrup in slab


Length
Girth - 8 concrete cover + hook Moisture barrier, 2 coats of
12d damp proofing bituminous
coating on earth face of
sides 0.550 x 2 = 1.10 concrete surface of retaining
top bottom 0.25 x 2 = 0.50 bases
assume hook 12d
ddt 8/0.025 = 0.20
add hook 12/0.01 = 0.12 04 05 02 01 01 00
Total stirrup length = 1.52 edge of slab will be same with
edge of formwork
no of stirrup in slab 140.00 side A
0.30 42.00
(wall/slab length - cc both sides ) + 1
spacing 140.00 side B
(140.00-0.025-0.025) + 1 0.60 84.00
0.15 2
= 934 nos 1.50 front/back face
0.30 0.90
= 1.52m x 934nos x 0.617kg/m
875.94kg 2 0.25 projection edge
0.30 0.15
(all the calculation insert in
reinforcement schedule 140.00 top of slab
1.25 175.00 width - wall thick = 1.5-0.25
302.05

High tensile steel bar


reinforcement, in slabs,
10mm diameter; links,
stirrups, binders and the like
09 04 02 05 02 00
875.94 (qty from rebar schedule

Page 9