PROPOSED INDUSTRIAL SHED OF MODULE 3 AND OTHER CONNECTED UTILITY BUILDINGS, ROAD & DRAINS @

GROWTH CENTER, ORAGADAM, KANCHIPURAM DISTRICT, NEAR CHENNAI (PHASE

RAIN WATER HARVISTING POND ABSTRACT ESTIMATE FOR CIVIL W

S.No. Description of works

Best Construction practices as per NBC 2016 to be followed. Implement an soil erosion
Leed Points and sedimentation control plan including top soil preservation and for all construction
activities associated with the project with photographic and documentary evidence.

Excavation for Rain Water Pond with hydraulic excavator including cutting and loading
in tipper, trimming bottom and side slope, in accordance with requirements of line,
grades and cross sections, and transporting to the location (as identified by client)
1.00 within all lift and lead ypto 1000m as per the MORTH specification no.301, the rate
includes compaction of the embankment using the appropiate compactor including
trimming the extra earth to bring it to the drawing level and grade and slope - In all
clasess of soil.

Providing and laying random rubble stone pitching of 150mm thick set in CM 1:6 over
bed of coarse gravel of 100mm thick for embankments and for storm water drains or
other locations as specified. The rate shall include for cost of materials, labour, tools &
2.00 plant, consumables, curing, leads and lifts at all levels, loading and unloading charges,
transportation, scaffolding, all other incidental charges, etc. complete and as directed
by Engineer-in-charge
Providing and Laying of Filter media with granular materials/stone crushed aggregates
3.00 satisfying the requirements laid down in no.2504.2.2. of MORTH Specification to the
thickness of not less then 200mm on the bed of the canal.
Carrying out empty boring for 600mm dia perforated PVC pipe in all type of strata
4.00 including all tools & plants , machinery, disposal of excavated material upto lead of
1000m etc. complete and as directed by engineer incharge.
Desilting the exsting well free of silt and organic matter and then fill the wells with
5.00 alternate layer of filter media and well graded M sand and aggregates by the direction
of engineer incharge.
6.00 Hume Pipe

Providing and laying reinforced cement concrete heavy duty NP3 type pipe of the
following diameter with necessary collars conforming to IS 458, embedded in C.C.1:2:4
including cost and conveyance to site, laying to proper grade and alignment, jointing
etc. complete as per direction of the Engineer including cost and conveyance of all
materials to site, all labour, hire and fuel charges for all tools and plants employed and
all other incidental charges etc. complete as per specifications.

Supplying and fixing of 450mm dia NP3 class Hume pipe


S&F chain link fencing including the cost of MS angles, MS flats and necessary bolts
7.00 fixing the vertical post (spacing 3m) below the ground level with excavation and
concrete foundation.
S&F chain link fence MS gate including the cost of MS angles, MS flats and
8.00 necessary bolts fixing the vertical post below the ground level with excavation and
concrete foundation. Size double shutter 3m Gate
BUILDINGS, ROAD & DRAINS @ PLOT # C 10 & C 11, SIPCOT INDUSTRIAL
TRICT, NEAR CHENNAI (PHASE – 1 WORKS)

CT ESTIMATE FOR CIVIL WORKS

Unit Qty Rate Amount

Cum 1250 0

Sqm 380 0

Cum 45 0

Rmt 25 0

Cum 60 0

Rmt 40 0

Rmt 112 0

No 1 0

TOTAL 0
Si.no Description Unit Nos L B D Qty Remarks

1 Excavation Cum 1 18.75 18.75 3.5 1230.469 1300

2 Stone Pitching
Cum 2 20 3.5 140 4.9
Cum 2 20 3.5 140
280

3 HDPE Sheet Sqm 4 20 3.5 - 280


1 15 15 - 225
505

4 Cuddapha Stone 600x600mm


(in step) Cum 20 0.3 2 12
20 0.2 2 8
20

Filter media with granular


materials/stone crushed
5 aggregates in bed Cum 1 15 15 0.2 45

empty boring for 600mm dia


6 perforated PVC pipe Rmt 5 7 35

7 granular Material filling in well Cum 5 13.188 65.94


Cum 5 2 2 0.6 12
77.94

8 Hume Pipe 450mm dia NP3 Rmt 40

9 PCC Cum 1 15 15 0.1 22.5


367.5
37.5
18.75

90
28 112