ASSEMBLY & FIT-UP WELDING PAINTING Fit-up Date Duration Fit-up Inspection Welding Date Duration Total Welder Vis. Welding No Item Description Touch-up Paint Remarks Start Finish (Days) Date Start Finish (Days) (person) Inspection Date 1 Air Secondary 08L 08/02/2023 Not yet welder 2 Air Secondary 08R 08/02/2023 Not yet welder 3 Air Secondary D12R, D13R 12/01/2023 On going repair Visual 2 Welder 4 Air Secondary D12L, D13L 30/01/2023 Not yet welder for Visual Comment 5 Air Secondary D15L,D14L 12/02/2023 14/02/2023 1 Welding on going 6 Air Secondary D15R,D14R 08/02/2023 10/02/2023 1 Welding on going 7 Air Secondary D17R,D18R,D19R,D20R,D21R 22/02/2023 27/02/2023 1 Welding on going 8 Air Secondary D17L,D18L,D19L,D20L,D21L 14/02/2023 15/02/2023 1 Welding on going 9 Air Secondary D22L 22/02/2023 16/02/2023 1 Welding on going 10 Air Secondary D22R 23/02/2023 Not yet welder 11 Air Secondary M04L 21/02/2023 Not yet welder 12 Air Secondary M04R 21/02/2023 Not yet welder 13 Air Secondary J01R, J02R 14/02/2023 18/02/2023 2 Welding on going 14 Air Secondary J01L, J02L 07/02/2023 Done On going Visual Inspection 15 Air Windbox F11 23/01/2023 23/02/2023 Not yet welder for Visual Comment 16 Air Windbox G11 19/01/2023 23/02/2023 Not yet welder for Visual Comment 17 Air Windbox H11 20/01/2023 23/02/2023 Not yet welder for Visual Comment 18 Air Secondary K01R, K02R 20/01/2023 Done On going Visual Inspection 19 Air Secondary K01L, K02L 07/01/2023 Done Not yet welder for Visual Comment 20 Air Secondary L01L, L02L 09/02/2023 17/02/2023 25/02/2023 8 On going Visual Inspection 21 Air Secondary L01R, L02R 30/01/2023 Done On going Visual Inspection 22 Air Secondary K04L 04/02/2023 26/02/2023 1 Welding on going 23 Air Secondary K04R 04/02/2023 26/02/2023 1 Welding on going 24 Air Secondary L04L 04/02/2023 Not yet welder 25 Air Secondary H01L, H02L 06/01/2023 Done Finish touch up paint 26 Air Secondary H01R, H02R 11/01/2023 Done On going Visual Inspection 27 Air Secondary G01L, G02L 18/01/2023 18/02/2023 25/02/2023 7 On going Visual Inspection 28 Air Secondary G01R, G02R 25/01/2023 26/02/2023 1 Welding on going 29 Gas CID Fan Outlet CID-01R 24/02/2023 Fit-up on going 30 Gas CID Fan Outlet CID-01L 25/02/2023 Fit-up on going 31 Air Secondary J03L 21/02/2023 Not yet welder 32 Air Secondary J03R 21/02/2023 Not yet welder 33 Air Secondary L04R 21/02/2023 Not yet welder 34 Air Secondary D05R,06R,07R,09R,10R 14/01/2023 On going touch up paint 35 Air Secondary D05L,06L,07L,09L,10L Fit-up on going 36 Air Secondary F01L, F02L 06/01/2023 Done Finish touch up paint 37 Air Secondary F01R, F02R 11/01/2023 On going touch up paint 38 Air Secondary E01L, E02L 21/01/2023 15/02/2023 1 Welding on going (Remain Bottom Side) 39 Air Secondary E01R, E02R 25/01/2023 17/02/2023 25/02/2023 8 On going Visual Inspection 40 Air Secondary M01L, M02L 10/02/2023 16/02/2023 6 Fit-up on going 41 Air Secondary M01R, M02R 22/02/2023 Fit-up on going 42 Air Primary G11R 13/02/2023 Not yet welder 43 Air Primary F09R 13/02/2023 Not yet welder 44 Air Primary E10R 13/02/2023 Not yet welder 45 Air Primary G11L 13/02/2023 Not yet welder 46 Air Primary F09L 13/02/2023 Not yet welder 47 Air Primary E10L 13/02/2023 Not yet welder 48 49 50 Total 42 Total 11