21.02.

2023
Compliance - SOR dated
Observation
Nagawara Station Cut & Cover-02

RC wall (East and WestSide)


Ch - 21220 to 21250
11.01.2023, however backfilling
of cut &cover-2 on
PUSpray applied on the walls
has been not carried as on date.

Compliance
after completion of PU
work has not been carried out
It was observed backfilling work
Zone-03 Ch 21220-21250. Backfilling
Waterproofing on RC Wall(East &West side) of
blind strut.
has been delayed due to removal of temporary
dismantle main struts
blind struts were erected in order to
Tocast main wall2nd lift, temporary
was
space. Due to this reason, soil compaction
in particular location which created confined
delayed.
blind struts were removed immediately &
After casting 2nd lift of main wall with roof slab,
started backfilling work.

carried out after completion of self


ITD Cem will be ensuring that in future, backfilling willbe
curing period of PU spray membrane with proper suppoting system.

Attachments:

1. Compliance photos

En(gegr) ec P b H I
B R o s e

D r d e a
Confined area backfilled with crushed stone sand in between
Walls and soldier pile.

A B H
bRo s E )

Sibanaran
BMRCL

Soil backfilling at unconfined portion


Sibanaryn

teef
Compaction done for each layer by means of Baby Roller.
Sibanarayan
Backfilling done.
ibanarayan
SA|pre
TAlem: