TIGER SAFARI WORK COMPLIANCE

SR NO Points observed by inspection committee (27-7-2020 & 29-7-2020) Compliance


A Chainlink Fencing
1 At pole no. 150 to 151, soil below beam drained due to strom water flow. It is suggested to fill stones
Stones have been filled across the
confined in chainlink at both sides of beam/ wall to close opening below beam. wall
2 In bay pole no.184 to pole no. 194, lateral distance between anchor bolts is below 80mm. As per As discussed with structural
structural drawing, lateral distance between anchor bolts should be minimum 80mm. PMC should consultant & GM sir an additional
suggest solution on this defect. inclined support is provided at
pole no 191
3 The verticality of poles, which were tilted more than 100 mm (i.e. pole no. 364, pole no. 366, pole. Above given pole no have been
No.642, pole no.702) rectified.
4 At pole no. 226 and pole no.227, chainlink found rusting. PMC should suggest solution on this defect. Around 2.1km of fence only 3m
portion of chainlink is found
rusted. We have instructed the
contractor to replace it.

B Entry Gate
1 Both gates operated manually. But electrical supply connections are yet to be done. Hence electrical As power supply is pending from
operation, by switch at watch tower and by remote, cannot be performed. J V's side, hence as it gets
completed gates can be tested.
2 Electrical part like earthing, DP, feeder pillar etc. needs to be checked by electrical engineer of PMC All electrical works executed by
and issue test certificate/ completion certificate accordingly. LCES will be certified by PMC.

C Exit Gate
1 Both gates operated manually. But electrical supply connections are yet to be done. Hence electrical As power supply is pending from
operation, by switch at at watch tower and by remote, cannot be performed. J V's side, hence as it gets
completed gates can be tested.
2 Electrical part like earthing, DP, feeder pillar etc. needs to be checked by electrical engineer of PMC All electrical works executed by
and issue test certificate/ completion certificate accordingly. LCES will be certified by PMC.
3 Work of strom water cross drainage pipe front of outer gate is in progress. Work is completed.

D Emergency Gate
1 Both gates operated manually. But electrical supply connections are yet to be done. Hence electrical As power supply is pending from
operation, by switch at watch tower and by remote, cannot be performed. J V's side, hence as it gets
completed gates can be tested.
Electrical part like earthing, DP, feeder pillar etc. needs to be checked by electrical engineer of PMC All electrical works executed by
2 and issue test certificate/ completion certificate accordingly. LCES will be certified by PMC.
3 Work of strom water cross drainage pipe front of inner gate is in progress. Work is completed.

E Night Shelter
1 PVC water storage tank at ground displaced due to rain water. It is necessary to provide masonary Masonary platform has been
platform for water tank. constructed.
2 Hair cracks at joint of parapet and roof slab observed and needs to be sealed. Contractor has assured that work
will be completed by tommorow.

Points observed by inspection committee (31-7-2020)


1 The inclined chain link of entry, exit and emergency gates in Tiger safari is short. Hence an improper Whole chain link at inclined
join has been given there. But it is security hazard and aesthetically bad. Need replacement. portion has been replaced, hence
above all ponts have been
rectified.
2 U clamp on the top of inclined chain link in entry, exit and emergency gates are improperly fitted U clamps have been removed and
need rework. fixed again properly.
3 Painting of horizontal section at various places is to be done again as painting has been done without Work completed.
removing cement and welding spatter.
4 Contractor has assured that work
In Tiger night shelter, outside painting has prominnent marks of leakage of roof due to late water will be completed by tommorow.
proofing. Needs to be repainted some part.