Compliance of Tiger
Compliance of Tiger
B Entry Gate
1 Both gates operated manually. But electrical supply connections are yet to be done. Hence electrical As power supply is pending from
operation, by switch at watch tower and by remote, cannot be performed. J V's side, hence as it gets
completed gates can be tested.
2 Electrical part like earthing, DP, feeder pillar etc. needs to be checked by electrical engineer of PMC All electrical works executed by
and issue test certificate/ completion certificate accordingly. LCES will be certified by PMC.
C Exit Gate
1 Both gates operated manually. But electrical supply connections are yet to be done. Hence electrical As power supply is pending from
operation, by switch at at watch tower and by remote, cannot be performed. J V's side, hence as it gets
completed gates can be tested.
2 Electrical part like earthing, DP, feeder pillar etc. needs to be checked by electrical engineer of PMC All electrical works executed by
and issue test certificate/ completion certificate accordingly. LCES will be certified by PMC.
3 Work of strom water cross drainage pipe front of outer gate is in progress. Work is completed.
D Emergency Gate
1 Both gates operated manually. But electrical supply connections are yet to be done. Hence electrical As power supply is pending from
operation, by switch at watch tower and by remote, cannot be performed. J V's side, hence as it gets
completed gates can be tested.
Electrical part like earthing, DP, feeder pillar etc. needs to be checked by electrical engineer of PMC All electrical works executed by
2 and issue test certificate/ completion certificate accordingly. LCES will be certified by PMC.
3 Work of strom water cross drainage pipe front of inner gate is in progress. Work is completed.
E Night Shelter
1 PVC water storage tank at ground displaced due to rain water. It is necessary to provide masonary Masonary platform has been
platform for water tank. constructed.
2 Hair cracks at joint of parapet and roof slab observed and needs to be sealed. Contractor has assured that work
will be completed by tommorow.