Professional Documents
Culture Documents
Strictly Confidential 2
Strictly Confidential 3
Executive Summary
• On Friday 26 Feb 2021 at 09.22 pm, generator differential protection (87G) was activated causing Unit-1 Wayang
Windu turbine and generator were tripped by the lockout relay while it was exporting 107 MW.
• The protection relay log showed that the differential current was detected at phase T while the DCS measurement
reading showed the unbalance current measured at phase S.
• Based on the insulation resistance test result, there was no indication of the real phase fault on the stator winding.
• There was a finding on the cable of CT circuit of phase T. The cable insulation had broken and its conductor was
exposed to the wye (neutral) bus bar connection of generator stator winding.
• Corrective action was immediately done by wrapping up with the new insulation and rerouting the cable to prevent
reoccurring problem
Strictly Confidential
Background
On Friday 26 Feb 2021 at 09.22 pm, generator differential protection (87G) was activated causing Unit-1 Wayang
Windu turbine and generator were tripped by the lockout relay while it was exporting 107 MW.
Failure Description
There was an unbalance current indication at Phase S on DCS screen. There are possible causes of a trip based on
historical events:
1. Generator winding internal failure
2. Instrumentation failure (Generator Current Transformer or its sensing wiring problem)
3. Generator Protection Relay malfunction
Protection System
No Protection System Function Performed Status
1. 87G1 S/D if active Exist and active
Strictly Confidential
Investigation
Fact Finding and Observation Result
Based on DCS trending and Relay log list event, IC&E team has done several of action such as: LOTO application to
perform troubleshooting, Generator winding insulation resistance test, Generator end winding visual inspection, cable
damage replacement and re-routing the existing CT cable.
Strictly Confidential
Sequence of Event
Factual Chronological Information
Strictly Confidential
Sequence of Event
Factual Chronological Information
Date: 26 Feb 2021
21:22Call maint team and collect related documents
23:45 Discuss and visual inspection
Date: 27 Feb 2021
06:00Apply LOTO
09:00 Open generator terminal, open connection to generator terminal, check winding condition and test .
10:00 Perform generator winding internal , instrumentation (Generator Current Transformer or its sensing
wiring) , generator Protection Relay.
13:00 Generator visual inspection
14:00 Perform CT test
18:00 Generator termination
19:00 Monitoring U1 due to shut down condition
20:30Found CT cable broken.
21:00Repair CT cable completed.
22:00 Generator protection relay inspection (Log Event Relay)
23:00 Startup preparation
Strictly Confidential
Analysis of Suspected Cause
Based on the as-found finding and data trending, it was expected that the possible cause of the 87G1 failure were
1. Generator winding internal failure,
2. Instrumentation failure (Generator Current Transformer or its sensing wiring problem)
3. Generator Protection Relay malfunction.
During the event, several inspection and test was carried out in generator winding resistance test. Visual inspection then
conducted and found cable to CT was broken (burnt out) on cable section that attached to wye connection of neutral bus bar
(wye connection) of generator stator winding.
Strictly Confidential
Why Tree Analysis
3. Operation Issue : Focused on CT cable usage whether it exceed lifetime limit that
SOP Implementation during start up after plant S/D due to 87 G1 might have contributing factor to this event. Generator design
relay activated where clarified to operation team. From DCS data lifetime is ~ 25 years. Team also found that cable installation
and information given during RCA discussion it was found that nearby still have good condition.
anomalies in 87 G1 relay prior to S/D were identified by
operation team by DCS alarm. SOP for start up (PRD-3.0-GEL-
OP-203-SOP Turbine Start Up) also followed as well.
Strictly Confidential
Corrective Action, Conclusion and Recommendation
Corrective Action:
IC&E Maintenance team performed corrective action by replacing the damage cable and re-routing all the CT cable with
proper way, then proceed to start up the turbine successfully which also confirm that the problem is related to current
transformer cable that touch the generator wye connection bus bar.
Conclusion:
RCA team had come up with conclusion that the root cause of failure of Protection Relay (87G1) active was the problem on
current transformer cable that touched (closed) to the generator wye connection bus bar. This problem might be come from
improper installation and surroundings that triggered the cable touching the generator wye connection bus bar.
Recommendation:
• Perform Relay test on next SDTA (both Unit 1 and Unit 2).
• Check the CT and PT cable installation of the generator protection relay on the next SDTA, compare and update the
existing drawing if needed (both Unit 1 and Unit 2).
• Share this incident to other assets (Salak and Darajat) for lesson learned.
• Install the Digital Fault Recorder(DFR) for Unit 1 and Unit 2 for further analysis.
.
Strictly Confidential