You are on page 1of 5

LLNL-CONF-497353

Case Study of the Failure of two 13.8kV


Control & Metering Transformers that
caused significant Equipment Damage

G. R. Dreifuerst, D. B. Chew, H. L. Mangonon, P.


W. Swyers

September 1, 2011

IEEE Electrical Safety Workshop


Daytona Beach, FL, United States
January 30, 2012 through February 3, 2012
Disclaimer

This document was prepared as an account of work sponsored by an agency of the United States
government. Neither the United States government nor Lawrence Livermore National Security, LLC,
nor any of their employees makes any warranty, expressed or implied, or assumes any legal liability or
responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or
process disclosed, or represents that its use would not infringe privately owned rights. Reference herein
to any specific commercial product, process, or service by trade name, trademark, manufacturer, or
otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the
United States government or Lawrence Livermore National Security, LLC. The views and opinions of
authors expressed herein do not necessarily state or reflect those of the United States government or
Lawrence Livermore National Security, LLC, and shall not be used for advertising or product
endorsement purposes.
CASE STUDY OF THE FAILURE OF TWO 13.8KV CONTROL & METERING
TRANSFORMERS THAT CAUSED SIGNIFICANT EQUIPMENT DAMAGE
Copyright Material IEEE
Paper No. ESW-12 (do not insert number)

Gary Dreifuerst PhDEE Dennis Chew, P.E. Harry Mangonon, P.E. Paul Swyers, P.E.
Member, IEEE Member, IEEE LLNL M/S L-604 Member, IEEE
LLNL M/S L-449 LLNL M/S L-601 Livermore, CA 94550 LLNL M/S L-604
Livermore, CA 94550 Livermore, CA 94550 USA Livermore, CA 94550
USA USA mangonon2@llnl.gov USA
dreifuerst1@llnl.gov chew7@llnl.gov swyers1@llnl.gov

Abstract - The degradation and failure of cast-coil epoxy little mechanical damage to the surrounding structure. A risk
windings within 13.8kV control power transformers and would have existed for any worker present during this incident.
metering potential transformers has been shown to be The CPT, which feeds one side of the line-up, failed its primary
dangerous to both equipment and personnel, even though best (13.8kV winding) side insulation. It experienced turn-turn and
industrial design practices were followed. Accident scenes will layer-layer shorting (i.e., the transformer shorted-out and failed)
be examined for two events at a U.S. Department of Energy during the failure event. The failure was not sufficient to cause
laboratory. Failure modes will be explained and current design the “E” type primary fuse (7E) to clear the fault. This device is
practices discussed with changes suggested to prevent a constructed using a cast-epoxy, copper primary winding. The
recurrence and to minimize future risk. New maintenance failure of this transformer caused the loss of AC power to
philosophies utilizing partial discharge testing of the various transducers. This event was logged by the SCADA
transformers as a prediction of end-of-life will be examined. system. Protective actions resulted in shutting down power to
107 buildings.
Index Terms — 13.8kV, arc flash, arc blast, CPT, MPT,
designing for safety B. Technical Review

Auspices — This work performed under the auspices of the The metal-clad switchgear line-up was manufactured in the
U.S. Department of Energy by Lawrence Livermore National 1990s. There are six line-ups on the lab’s 13.8kV system. Four
Laboratory under Contract DE-AC52-07NA27344. of the line-ups have identical layouts and CPTs. The rest of the
line-ups have slightly different CPTs. This was the first failure of
I. INTRODUCTION a CPT. It is not possible to perform an accident reconstruction
because of the magnitude of the damage to the CPT.
This Department of Energy lab was founded in 1952 with the The specific initiator is not known. It is known that no power
mission to ensure the safety and security of the nation through system disturbances were observed by the SCADA system until
applied science and technology. This lab houses world-class the CPT started to fail at 07:14:40. The 13.8kV primary power
high performance computing facilities, the world’s most was still applied until 07:25:21 when the bus differential relays
powerful laser and numerous other high technology facilities on tripped. Over that time, the CPT failure progressed until the
its one square mile location. The electric utility supply for these epoxy cast primary was sufficiently overheated, which boiled off
requires high availability and quality of service. The base line resin creating substantial smoke which prompted the call to the
power supply is about 180MVA. This is distributed on-site Fire Department.
through double-ended 15kV-class metal-clad switchgear line- The CPT failure may have started with a simple shorted-turn
ups. The line-up circuit breakers are switchable through a in the winding due to interwinding (turn-turn or layer-layer)
Supervisory Control And Data Acquisition (SCADA) system. insulation failure. That would have increased the primary
Each line-up has two sets of Control Power Transformers current, in order to apply more power to the failed winding area.
(CPT) and four sets of Metering Potential Transformers (MPT) As the temperature increases, the remaining insulation starts to
to drive local relaying protection networks and automatic fail, causing additional damage sites to develop and to deposit
transfer schemes. These are all 15kV-class transformers using even more heat. This dynamic would not require a substantial
cast-epoxy solid dielectrics. amount of current to destroy the transformer.
Figure 1 shows the result that the extreme heat caused by
II. CPT FAILURE AUGUST 29, 2007 [1] the arcing, progressively destroying the insulation and welding
the wire fragments together. The arc debris damaged the two
A. Background vertical compartments which were exposed to the CPT. Just
above the CPT is the compartment for the Main Breaker for the
The first failure of a cast-epoxy 15kVA 13.8kV primary main bus. After disassembly for cleaning and rewiring, arc
transformer in our recent history was destructive to the spots to the frame were observed in the rear of the CPT
transformer and to the 13.8kV line-up. Substantial debris was compartment. The presence of these arcs is the likely reason
circulated through the medium-voltage switchgear with very that the bus differential relay opened the bus breakers at

[Type text]
07:25:21. The action of the differential relay properly opened 124 buildings for at least 2 seconds and 173 buildings for
the main, tie and all feeder breakers, but could not open the approximately 4 hours.
source side breaker (remote from this line-up) which powers the An internal failure in one of the two single-phase MPTs—
main breaker. The extent of the debris from the CPT failure located in the lower compartment of the vertical section
bridged the bus insulators to ground. The source feeder containing the tie breaker—caused a short-circuit and ground
breaker tripped on overcurrent. fault at the MPT’s input contacts, melting and vaporizing the
contacts. The resulting damage is shown in Figure 2. This
created an arc across the 13.8kV input contacts of the MPT,
resulting in an arc flash and an arc blast (an arc flash of
significant power and energy sufficient to create a pressure
wave able to mechanically destroy facility equipment) that blew
the lower compartment front door off the enclosure and
damaged the rear panels in that compartment.

Figure 2: MPT failure in bottom drawer of feeder breaker


cabinet.
Figure 1: Damaged 15kVA CPT protected by 7E fuses
The tie breaker, located in the upper compartment above the
C. Manufacturer’s Installation Instructions for Replacement MPTs, began to open in order to clear the fault condition.
CPTs reveals likely fault scenario However, the tie breaker experienced a failure at its input
connections due to the arc blast originating in the lower
“If a transformer develops a winding fault, in many instances compartment, which created a second arc flash and resulting
the primary fuses do not clear the fault until the transformer has arc blast. The section’s front panel and the upper compartment
split open from internal pressure and vented ionized gases. door were blown off. See Figure 3.
These gases can travel to the top of the vertical section and can
cause a phase-to-phase or phase-to-ground fault on an The building showed minor evidence of overpressurization,
uninsulated bus, which can then travel to adjacent sections in a with some sheet metal screws popped out of the metal siding
line-up. Good practice would indicate that the sections with a and a double-hung window tipped outward after shearing off
transformer should be designed to prevent ionized gas traveling two of the four framing screws.
into adjacent sections.” The extent of damage resulted in the Incident Analysis
Report [2] concluding that death may have resulted for
III. MPT Failure December 17, 2010 [2] someone in front of the line-up’s faulted vertical section, and
organ or hearing damage for anyone in the room.
A. Background

The s e c o n d f a i l u r e o f a c a s t-epoxy 13.8kV primary


transformer was destructive to the transformer and to the
13.8kV switchgear line-up. A major risk of harm would have
existed for any worker present during this incident. The failure
was not sufficient to cause the “E” type primary fuse (0.5E) to
clear the fault. Substantial debris was circulated through the
medium-voltage switchgear with significant mechanical damage
to the surrounding structure and observable over-pressurization
effects for the building.

B. Technical Review

At approximately 11:37, an electrical outage occurred due to Figure 3: Line-up with damaged feeder breaker cabinet.
the unintentional opening of a tie breaker. This outage affected

Revision 2, 2008 2
IV. CONCLUSIONS VI. REFERENCES
A. Transformer Issues
[1] Lawrence Livermore National Laboratory, Investigation of
The first failure led us to believe that the temperature rise in the LLNL Power Outage due to a Transformer Failure in
the epoxy core and resulting insulation degradation was the LGS-15 on August 29, 2007, Incident Analysis Report
likely initiator, so we implemented a pro-active replacement of 200740, March 3, 2008.
all CPTs, regardless of their age, in our metal-clad switchgear [2] Lawrence Livermore National Laboratory, Building U424
line-ups. The second failure changed our thinking about Electrical Utility Incident, December 17, 2010, Incident
temperature rise, because the MPTs are not a power-handling Analysis Report 201064, March 7, 2011, LLNL-AR-
transformer. MPTs have no appreciable temperature rise in 471633.
service. In reviewing the switchgear design, we confirmed that [3] Electrical Installations in Petroleum Processing Plants,
locating MPTs in switchgear is not a disallowed practice by API API Recommended Practice 540, Fourth Edition, April
[3] and by IEEE [4]. Overcurrent HV-side fusing is set up to 1999.
protect the buses and not the PTs. The insulation failure in both [4] IEEE Std C37.20.2-1999 Standard for Metal-Clad
manufactured transformer types is now believed to be due to Switchgear.
partial discharge (PD) activity. A regular measurement and [5] Hank Lee, LLNL-Bldg 424, T200 15kV Switchgear West
trending of PD levels for the 13.8kV transformers is being Bus Fault Investigation and Analysis, Electrolink
planned to look for degradation tendencies, with replacement Engineering Services, Inc., report, January 25, 2011.
as part of the Preventative Maintenance (PM) program. This
PM effort is being used to decrease not just the equipment
failure rate, but also to reduce the risk exposure to the VII. VITA
engineers and electricians that work on and around the line-
ups. Gary R. Dreifuerst (M’1970) is an electronics engineer at
The second incident had the good fortune to be monitored by Lawrence Livermore National Laboratory (LLNL) since June
a computer-based relay. The waveform data gathered by this 1981 working in the Inertial Confinement Fusion Laser
relay provided a clear picture of exactly how fast the failure programs after receiving his electrical engineering PhD degree
mechanism occurred. What showed up as an intermittent from the University of Wisconsin-Madison.
SCADA undervoltage relay error message overnight, became a
fully involved 30kA three phase fault in less than 7 cycles (0.12 Gary is the Electrical Safety Officer for the National Ignition
seconds) Facility and the chair of the LLNL Electrical Safety Committee.

B. Safe Work Practices Dennis B. Chew (M’2001) received his BSEE degree in 2002
from California Polytechnic State University, San Luis Obispo
The standard work practices for the High Voltage Electricians and is a registered Professional Electrical Engineer in
included reviewing the status of panel mounted instruments and California. Dennis has worked at Lawrence Livermore National
verifying connections or settings of components that are Laboratory (LLNL) since 2002 as an Electrical Engineer. In
housed in the control compartments of the energized metal clad 2008, Dennis began working for the LLNL Electric Utility Group
switchgear line-ups are operating correctly. Following the first and is currently the Electric Utilities Services Supervisor as well
incident detailed in section II above, there was no modification as a member of the LLNL Electrical Safety Committee.
to that work practice. The engineering action of replacing all the
CPTs was thought to have significantly decreased the Harry L. Mangonon received his BSEE degree in 1971 from the
probability of exposure to a repeat of that failure and therefore University of the Philippines. He has been a Utility Engineer at
was viewed as an appropriate action that mitigated the risk. Lawrence Livermore National Laboratory since 2004. He is a
registered Professional Electrical Engineer in California and
Both engineering and electrician personnel recognized that a Wyoming. Harry has over 40 years experience as an engineer
risk still exists due to the destruction brought about from the that included stints at Bechtel and Aker Kvaerner in the
second incident detailed in section III. Any work where a petrochemical, non-ferrous metals and power industries; and as
compartment must be opened while the line-up is energized is a Field Service Engineer for Westinghouse Electric
no longer allowed. The time that a worker must be in the vicinity Corporation.
of an energized line-up is also minimized. As PM data is
gathered, further work modifications may be incorporated. Paul W. Swyers (M’1983) received his BSEE degree in 1984
from California Polytechnic State University, San Luis Obispo
and his MSEE degree in 1994 from Santa Clara University.
V. ACKNOWLEDGEMENTS Paul worked at Pacific Gas & Electric Company from 1984 to
1989 as an electric utility distribution engineer. Since 1989,
An outside consultant was hired to help analyze the second Paul has worked at Lawrence Livermore National Laboratory
fault [5]. He agreed that the transformer location complied with (LLNL) in the Electric Utility Group. Paul is currently the LLNL
industry practice and that the primary fusing for the transformer Electric Utility Group Leader and a member of the LLNL
would not protect against the destruction of the transformer. Electrical Safety Committee. Paul is a registered Professional
Electrical Engineer in California.

Revision 2, 2008 3

You might also like