Professional Documents
Culture Documents
Total #REF!
#REF!
Wiring of Two way, stair case light point, with 3/0.029 PVC
3 insulated wires in PVC pipe recessed, including Two way 15-52 4 Each
switch
Supply and Erection PVC pipe for wiring purpose complete
4 15-02-b-03 160.02 m
Recessed in walls including chase etc : 1" i/d
Supply and Erection 1" dia & 0.6 m long lightening conductor
12 15-44 5 Each
(Air Terminal) copper rod with base etc.
3 of 7
Supply and Installation of Stabilizer 8000 Watts 230 V, 1-Ph
19 with Change over switch 100 A, 400 V complete according to NSI 1 Each
Design Drawing.
4 of 7
ABSTRACT OF COST
Head: Internal Electrification
M3 (P) Module
Rate Amount
(Rs) (Rs)
1,005.07 98,496.86
530.02 8,480.32
1762.19 7,048.76
275.83 44,138.32
339.78 17,088.22
69.5 33,364.17
159.94 16,087.40
3845.53 138,439.08
15650.82 15,650.82
38157.65 21,277.50
89.3 893.00
4315.63 21,578.15
1144.23 85,817.25
15650.82 31,301.64
1136.41 39,774.35
970.00 33,950.00
950.00 11,400.00
350.00 12,600.00
5 of 7
50000.00 50,000.00
40000.00 40,000.00
TOTAL 727,386
6 of 7
Steps - 1
S.No. Description Quantity Unit Rate (Rs)
Total
TOTAL
NET TOTAL
Steps - 2
S.No. Description Quantity Unit Rate (Rs)
1 #REF! M3 #REF!
RCC 1:2:4 in roof beam, column, slab
2 #REF! T #REF!
Mild Steel
3 #REF! M3 #REF!
Brick work in Foundation
4 #REF! M3 #REF!
Sand Filling
5 #REF! M2 #REF!
PCC 1:3:6
6
Electrical Conduits 20 %
Total
TOTAL
7 of 7
Add 0.5% Contigency
NET TOTAL
In Million
8 of 7
Steps - 3
S.No. Description Quantity Unit Rate (Rs)
1 #REF! M3 #REF!
RCC 1:2:4
2 #REF! T #REF!
Mild steel
3
Electrical Conduits 20 %
Total
TOTAL
NET TOTAL
In Million
Steps - 4
S.No. Description Quantity Unit Rate (Rs)
2 #REF! M3 #REF!
Brick work in G/F
3 #REF! M2 #REF!
Steel Chokat
4 #REF! M2 #REF!
Steel Window
5 #REF! M2 #REF!
Wooden Joinery
6 #REF! M #REF!
Marble Strips
7 #REF! M2 #REF!
PCC 1:2:4 under floor
8 #REF! M2 #REF!
grey cement skirting 3/8" thick
9 #REF! M2 #REF!
Plaster 3/4"
10 #REF! M2 #REF!
Plaster 3/8"
11
Electrical Conduits 20 %
Total
9 of 7
TOTAL
NET TOTAL
In Million
10 of 7
Steps - 5
S.No. Description Quantity Unit Rate (Rs)
2 #REF! M3 #REF!
Brick work in F/F
3 #REF! M 3000.00
Steel Chokat F/F
4 #REF! M2 #REF!
Steel Window
5 #REF! M2 #REF!
Wooden Joinery
6 #REF! M #REF!
Marble Strips
7 #REF! M2 #REF!
PCC 1:2:4 under floor
8 #REF! M2 #REF!
grey cement skirting 3/8" thick
9 #REF! M2 #REF!
Plaster 3/4"
10 #REF! M2 #REF!
Plaster 3/8"
11
Electrical Conduits 20 %
Total
TOTAL
NET TOTAL
In Million
Steps - 6
S.No. Description Quantity Unit Rate (Rs)
1
Finishing
2
Electrical Conduits 20 %
Total
TOTAL
11 of 7
Add 0.5% Contigency
NET TOTAL
In Million
12 of 7
Steps - 1
Amount (Rs)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0
#REF!
Steps - 2
Amount (Rs)
#REF!
#REF!
#REF!
#REF!
#REF!
145477.17
#REF!
#REF!
#REF!
13 of 7
#REF!
#REF!
#REF!
14 of 7
Steps - 3
Amount (Rs)
#REF!
#REF!
145477.17
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Steps - 4
Amount (Rs)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
145477.17
#REF!
#REF!
15 of 7
#REF!
#REF!
#REF!
#REF!
16 of 7
Steps - 5
Amount (Rs)
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
145477.17
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
Steps - 6
Amount (Rs)
1858777.42
145477.17
2004254.59
160340
2164595
17 of 7
10823
2175418
2.18
18 of 7
Milestones, Module (M3) High
S.No Milestone Cost (Rs Millions) Percentage of total Cost
Step - A
Mobilization Advance #REF! #REF!
GROUND FLOOR
1 Dismantling
2 Excavation,
4 PCC 1:4:8
#REF! #REF!
5 RCC 1:2:4 in Footing
7 Mild Steel
8 Back Filling
GROUND FLOOR
2 Mild Steel
7 Electrical Conduits 20 %
FIRST FLOOR
GROUND FLOOR
1 Wire Mesh
3 Steel Chokat
4 Steel Window
5 Wooden Joinery
Step 4
8 Marble Skirting
9 Plaster 3/4"
10 Plaster 3/8"
11 Electrical Conduits 20 %
FIRST FLOOR
1 Wire Mesh
4 Steel Window
Step 5
5 Wooden Joinery
#REF! #REF!
6 Marble Flooring
7 Marble Skirting
8 Plaster 3/4"
9 Plaster 3/8"
10 Electrical Conduits 20 %
COMPLETE
Step 6
1 Finishing
1.74033 #REF!
2 Electrical Conduits 20 %
Total #REF! #REF!
Milestones, Module (M-3 High) for GHS Swegalai, District Swat
FOUNDATION
i Dismantling
ii Excavation, Termite Proofing & PCC 1:4:8
iii RCC 1:2:4 in Footing, Neck Columns & Plinth Beam
1 #REF! #REF!
iv Brick work in foundation
v Steel Reinforcement (Foundation up to Plinth Beam)
GROUND FLOOR
i Back Filling (complete)
ii Sand Filling under floor & PCC 1:3:6 in flooring
iii RCC 1:2:4 in Columns, Stairs, Beams & Slab
2 #REF! #REF!
Steel Reinforcement (Columns, Stairs, Beams &
iv
Slab)
v Electrical Conduits
FIRST FLOOR
RCC 1:2:4 in Columns, Stairs, Beams, Slab & Mumty
i
complete
3 Steel Reinforcement (Columns, Stairs, Beams, Slab #REF! #REF!
ii
& Mumty complete)
iii Electrical Conduits
GROUND FLOOR
i Brick work in G/F complete
ii Steel Chowkat for Doors & Windows
iii Plastering complete (including wire mesh)
4 #REF! #REF!
iv Fixing of Doors & Windows (without glass)
v Marble Flooring & Skirting complete (except grinding)
FIRST FLOOR
i Brick work in F/F complete
ii Steel Chowkat for Doors & Windows
iii Plastering complete (including wire mesh)
iv Fixing of Doors & Windows (without glass)
5 #REF! #REF!
v Marble Flooring & Skirting complete (except grinding)
21 of 7
Supervisory Consultant Charges (50 %)
7b i (This milestone will be paid upon completion of #REF! #REF!
Milestone No. 1,2,3)
Supervisory Consultant Charges (25 %)
7c i (This milestone will be paid upon completion of #REF! #REF!
Milestone No. 4,5,6)
Total : #REF! #REF!
22 of 7
-3 High) for GHS Swegalai, District Swat
Percentage of
Total Cost
FOUNDATION
#REF!
GROUND FLOOR
#REF!
FIRST FLOOR
#REF!
GROUND FLOOR
#REF!
FIRST FLOOR
#REF!
NG WORKS COMPLETE
#REF!
#REF!
23 of 7
#REF!
#REF!
#REF!
24 of 7