PROJECT = 132 KV TRANSMISSION LINE PEZU TANK JANDOLA

PACKAGE # 01
Tower Tower Distence Angles Coordinates Foundation Erection STRINING WORK
No- Type (M) Degree Easting Northing Complete Complete
T-1 EG+0+4 50 661173.720 3574901.800 Remaining Remaining
Road Crossing Pezu To Tank
T-2 ZM 1+6 M 170 661011.630 3574953.030 4/5/2020 Remaining
T-3 ZM 1 150 660868.600 3574998.230 6/5/2020 Erected
T-4 ZM 60 140 45-00-00 LT 660735.11 3575040.42 15/6/2020 Erected
T-5 ZM 1 220 6/5/2020 Erected
T-6 ZM 1 220 8/5/2020 Erected
T-7 ZM 1 230 10/5/2020 Erected
T-8 ZM 1 220 11/5/2020 Erected
T-9 ZM 1 200 13/5/2020 Erected
T-10 ZM 1 220 14/5/2020 Erected
T-11 ZM 1 220 4/6/2020 Erected
T-12 ZM 1 220 6/6/2020 Erected
T-13 ZM 1 220 8/6/2020 Erected
T-14 ZM 1 220 11/6/2020 Erected
T-15 ZM 1 230 10/6/2020 Erected
T-16 ZM 1 230 13/6/2020 Erected
T-17 ZM 1 220 14/6/2020 Erected
T-18 ZM 30 218 15-00-00 RT 657986.229 3573611.850 10/6/2020 Erected

Started
T-19 ZM 1 232 17/6/2020 Erected
T-20 ZM 1 230 18/6/2020 Erected
T-21 ZM 1 230 22/6/2020 Erected
T-22 ZM 1 230 21/6/2020 Erected
T-23 ZM 1 220 23/6/2020 Erected
T-24 ZM 1 220 24/6/2020 Erected
T-25 ZM 1 220 28/6/2020 Erected
T-26 ZM 1 220 25/6/2020 Erected
T-27 ZM 1 230 24/6/2020 Erected
T-28 ZM 1 230 29/6/2020 Erected
T-29 ZM 1 230 27/6/2020 Erected
T-30 ZM 1 230 1/7/2020 Erected
T-31 ZM 1 220 2/7/2020 Erected
T-32 ZM 1 220 5/7/2020 Erected
T-33 ZM 30 223.5 3-19-10 RT 654680.468 3572881.401 14/7/2020 Erected
T-34 ZM 1 180 4/7/2020 Erected
T-35 ZM 1 180 8/7/2020 Erected
T-36 ZM 1 180 7/7/2020 Erected
T-37 ZM 1 180 11/7/2020 Erected
T-38 ZM 1 180 12/7/2020 Erected
T-39 This tower terminated due to short distance
T-40 ZM 1 198.789 23/4/2020 Erected
T-41 ZM 1 283.561 25/4/2020 Erected
T-42 ZM 1 226.35 27/4/2020 Erected
T-43 ZM 1 263.3 29/4/2020 Erected
T-44 ZM 1 230.72 2/5/2020 Erected
T-45 ZM1+3 M 261.25 17/6/2020 Erected

Total 43 42

PACKAGE # 02
Tower Tower Distence Angles Coordinates Foundation Erection STRINING WORK
Complet
No- Type (M) Degree Easting Northing Completed
ed
Road Crossing Village Sher Ali
T-46 ZM 1 231.62 13/6/2020 Erected
T-47 ZM 1 231.65 15/6/2020 Erected
T-48 ZM 1 222.11 17/6/2020 Erected
T-49 ZM 1 220 20/6/2020 Erected
T-50 ZM 1 220 22/6/2020 Erected
T-51 ZM 1 210 24/6/2020 Erected
T-52 ZM 30 210 10-00-00 RT 650819.728 3572267.422 Remaining
T-53 ZM 1 220 27/6/2020 Erected
T-54 ZM 1 210 28/6/2020 Erected
T-55 ZM 1 195 1/7/2020
Road Crossing Village Mekhani
T-56 ZM 30 211 20-00-00 LT 649983.863 3572282.442 Remaining
T-57 ZM1+3 224 2/7/2020 Erected
T-58 ZM1+3 220 11/7/2020
T-59 ZM 1 230 12/7/2020 Erected
T-60 ZM 1 230 8/7/2020 Erected
T-61 ZM 1 230 27/7/2020 Erected
T-62 ZM 1 230 26/7/2020 Erected
T-63 ZM 1 230 25/7/2020 Erected
T-64 ZM 1 230 24/7/2020 Erected
T-65 ZM 1 230 22/7/2020 Erected
T-66 ZM 1 230 19/7/2020 Erected
T-67 ZM 1 230 18/7/2020 Erected
T-68 ZM 1 230 21/7/2020 Erected
T-69 ZM 1 230 15/7/2020 Erected
T-70 ZM 1 230 14/7/2020 Erected
T-71 ZM 1 230 18/8/2020 Erected
T-72 ZM 1 230 19/8/2020
T-73 ZM 1 230 22/8/2020
T-74 ZM 30 230 5-53-06 RT 646082.855 3570941.803 =
T-75 ZM 1 230 23/8/2020
T-76 ZM 1 230 25/8/2020
T-77 ZM 1 230 2/9/2020
5/9/2020
T-78 ZM 1 230
6/9/2020
T-79 ZM 1 230
8/9/2020
T-80 ZM 1 230
T-81 ZM 30 230 18-34-07 LT 644515.662 3570577.290 =
9/9/2020
T-82 ZM 1 230
12/9/2020
T-83 ZM 1 230
14/9/2020
T-84 ZM 1 230
15/9/2020
T-85 ZM 1 230
16/9/2020
T-86 ZM 1 230
T-87 ZM 1 230 =
19/9/2020
T-88 ZM 1 230
20/9/2020
T-89 ZM1+3 M 230
Road Crossing Village Abizer
T-90 ZM1+3 M 188
22/9/2020

Total 40 22

PACKAGE # 03

Tower Tower Distence Angles Coordinates Foundation Erection STRINING WORK


Complet
No- Type (M) Degree Easting Northing Completed
ed
T-91 ZM30 230 6 - 03 - 32 LT 642593.580 3569392.311 23/9/2020 Nill
NALLA
T-92 ZM 1 240 26/9/2020 Nill
T-93 ZM 1 240 27/9/2020 Nill
T-94 ZM 1 240 29/9/2020 Nill
T-95 ZM 1 240 30/9/2020 Nill
T-96 ZM 1 240 Nill Nill
T-97 ZM 1 240 Nill Nill
T-98 ZM30 240 25 - 34 - 58 RT 641264.553 3568364.641 Nill Nill
T-99 ZM 1 240 Nill Nill
T-100 ZM 1 240 Nill Nill
T-101 ZM 1 240 Nill Nill
T-102 ZM 1 240 Nill Nill
T-103 ZM 1 240 Nill Nill
T-104 ZM 1 240 Nill Nill
T-105 ZM 1 240 Nill Nill
T-106 ZM 1 240 Nill Nill
T-107 ZM 1 240 Nill Nill
T-108 ZM 1 240 Nill Nill
T-109 ZM1+3 M 240 Nill Nill
NALLA
T-110 ZM 1 240 Nill Nill
T-111 ZM 1 240 Nill Nill
T-112 ZM1 240 Nill Nill
T-113 ZM30 208.354 7 - 22 - 24 RT 637775.864 3567614.810 Nill Nill
T-114 ZM 1 240 Nill Nill
T-115 ZM 1 240 Nill Nill
T-116 ZM 1 240 Nill Nill
T-117 ZM 1 240 Nill Nill
T-118 ZM 1 240 Nill Nill
T-119 ZM 1 240 Nill Nill
T-120 ZM 1 240 Nill Nill
T-121 ZM 1 240 Nill Nill
T-122 ZM 1 240 Nill Nill
T-123 ZM 1 240 Nill Nill
T-124 ZM 1 240 Nill Nill
T-125 ZM 1 240 Nill Nill
T-126 ZM30 222.34 18 - 44 - 04 LT 634684.201 3567357.536 Nill Nill
T-127 ZM 1 230 Nill Nill
T-128 ZM 1 230 Nill Nill
T-129 ZM 1 230 Nill Nill
T-130 ZM 60 213 58 - 00 - 00 LT 633856.040 3566997.589 Nill Nill
NALLA
T-131 ZM1+3 M 220 Nill Nill
Road Crossing Pezu To Tank
T-132 ZM1+3 M 220 Nill Nill
T-133 EA+0+6 220 Nill Nill
T-134 ZM 1 220 Nill Nill
T-135 ZM 1 220 Nill Nill

Total 5 0
PACKAGE # 04
Tower Tower Distence Angles Coordinates Foundation Erection STRINING WORK
Complet
No- Type (M) Degree Easting Northing Completed
ed
T-136 ZM 1 220 15/9/2020 Nill
T-137 ZM 1 210 16/9/2020 Nill
T-138 ZM 1 210 19/9/2020 Nill
T-139 ZM 1 210 17/9/2020 Nill
T-140 ZM 1 210 17/9/2020 Nill
T-141 ZM 1 210 14/9/2020 Nill
T-142 ZM 1 210 15/9/2020 Nill
T-143 ZM 1 210 Nill Nill
T-144 ZM30 200 11 - 31 - 37 LT 633413.638 3564040.493 Nill Nill
T-145 ZM 1 228 Nill Nill
T-146 ZM 1 220 Nill Nill
T-147 ZM 1 220 Nill Nill
T-148 ZM 1 220 Nill Nill
T-149 ZM 1 220 Nill Nill
T-150 ZM 1 220 Nill Nill
T-151 ZM 60 220 54 - 03 - 23 RT 633495.147 3562494.639 22-9-2020 Nill
T-152 ZM 1 230 Nill Nill
T-153 ZM 1 230 Nill Nill
T-154 ZM1+3 M 200 20-9-2020 Nill
NALLA
T-155 ZM 1 230 13/9/2020 Nill
T-156 ZM1+3 M 220 12/9/2020 Nill
T-157 EA+0+6 180 Nill Nill
Road Crossing Tank To D . I Khan
T-158 ZM1+3 M 200 Nill Nill
T-159 ZM1+3 M 220 Nill Nill
NALLA
T-160 ZM1+3 M 230 9/9/2020 Nill
T-161 ZM 1 210 Nill Nill
T-162 ZM 1 210 10/9/2020 Nill
T-163 ZM 1 210 29/9/2020 Nill
T-164 ZM 60 205 42 -33 -28 RT 631337.403 3560749.706 27/9/2020 Nill
NALLA
T-165 ZM 1 230 22-9-2020 Nill
T-166 ZM 1 200 20-9-2020 Nill
T-167 ZM 1 200 Nill Nill
T-168 ZM30 159.52 12 -25 - 11 RT 630549.435 3560799.224 Nill Nill
NALLA
T-169 ZM 1 230 23-9-2020 Nill
T-170 ZM 1 230 27-9-2020 Nill
T-171 ZM 1 230 26-9-2020 Nill
T-172 ZM 1 230 30-9-2020 Nill
T-173 ZM 1 230 Nill Nill
NALLA
T-174 ZM60 228 43 - 59 - 40 RT 629224.919 3561179.414 Nill Nill
T-175 ZM 1 205 Nill Nill
T-176 ZM30 200 12 - 00 - 00 LT 629022.480 3561530.190 Nill Nill
T-177 ZM60+3 220 59 - 13 - 25 RT 628875.299 3561693.708 Nill Nill
Road Crossing Tank To Jandola
T-178 EA+0+8 210 Nill Nill
T-179 ZM1+3 M 200 Nill Nill
T-180 ZM 60 160 629044.170 3562238.118 Nill Nill

Total 21 0
PACKAGE # 05
Tower Tower Distence Angles Coordinates Foundation Erection STRINING WORK
Complet
No- Type (M) Degree Easting Northing Completed
e
T-1 EG+0+2 - 629024.840 3561790.290 Remaining Nill
T-2 EA+6+8 170.88 628942.392 3561939.960 = =
T-3 ZM1+3 M 328.35 628783.917 3562227.540 = =
T-4 ZM 30+3M 239.92 16-12- 34 LT 628668.200 3562437.710 = =
T-5 ZM1+3 M 270 10/6/2020 Erected
T-6 ZM 30 250 5-26-57 RT 628300.228 3562805.120 14/9/2020 =
T-7 ZM 1 242 = =
T-8 ZM 1 240 = =
T-9 ZM 1 240 = =
T-10 ZM 1 224 = =
T-11 ZM 1 246 = =
T-12 ZM 1 230 = =
NALLA
T-13 ZM 1 260 Remaining =
T-14 ZM1+3 M 250 Water logged area 20-9-2020 =
T-15 ZM 30.(WLA) 248 24-40-14 RT 626910.793 3564484.970 23-9-2020 =
Road Crossing Village Budai
T-16 ZM1+3 M 262 Water logged area 26-9-2020 =
T-17 ZM 1 250 Water logged area 27-9-2020 =
T-18 ZM 1 240 = =
T-19 ZM1+3 M 250 = =
T-20 ZM 30 256 27-17-40 LT 626586.8 3565700.530 = =
T-21 ZM 1 224 = =
T-22 ZM 60 103 48-41-50 LT 626367.070 3565942.700 = =
T-23 ZM 1 257 = =
T-24 ZM 1 230 = =
T-25 ZM 1 230 = =
T-26 ZM 1 240 = =
T-27 ZM 1 230 = =
T-28 ZM 1 230 23/6/2020 Erected
T-29 ZM 1 230 21/6/2020 Erected
T-30 ZM 1 230 21/7/2020 Erected
T-31 ZM 1 220 20/6/2020 Erected
T-32 ZM 1 228 Remaining =
T-33 ZM 60 202 53-13-20 RT 623840.400 3565902.318 = =
T-34 ZM 1 230 19/7/2020 Erected
T-35 ZM 1 230 25/6/2020 Erected
T-36 ZM 1 220 28/6/2020 Erected
T-37 ZM 1 218 22/7/2020 Erected
T-38 ZM 1 220 29/6/2020 Erected
T-39 ZM 60 182 44-34-41 LT 623045.540 3566931.017 2/7/2020 Erected
T-40 ZM1+6 M 258 15/7/2020 Erected
T-41 ZM1 250 4/7/2020 Erected
NALLA
T-42 ZM 30 234 15-21-23 RT 622310.280 3567030.810 6/7/2020 =
Road Crossing Village Baba Khel
T-43 ZM1+3 M 266 7/7/2020 Erected
T-44 ZM1+3 M 250 8/7/2020 Erected
T-45 ZM1 240 11/7/2020 Erected
NALLA
T-46 ZM1 250 12/7/2020 Erected
T-47 ZM1 240 13/7/2020 Erected
T-48 ZM1 230 14/7/2020 Erected
T-49 EA+0+4 280 Remaining =

Total 25 18
PACKAGE # 06
Tower Tower Distence Angles Coordinates Foundation Erection STRINING WORK
Complet
No- Type (M) Degree Easting Northing Completed e
NALLA
T-50 ZM 30 286 24 - 20 - 51 LT 620431.834 3567831.567
T-51 ZM 1 324
T-52 This tower shifted to 56A
T-53 ZM 30 220 16 - 41 - 04 LT 619887.965 3567819.609
NALLA
T-54 ZM 30 400 17 - 20 - 48 RT 619507.422 3567696.373
T-55 ZM 1 200 8/9/2020 
T-56 ZM 1 160 3/9/2020 
NALLA
5/9/2020 
T-56A ZM 1 135
NALLA
T-57 ZM 1 325 25-8-2020
T-58 ZM1 130 27-8-2020
NALLA
T-59 ZM 30 200 5 - 38 - 13 RT 618357.485 3567684.381
T-60 ZM 1 242 23/8/2020
NALLA
T-61 ZM 30 240 3 - 19 - 10 RT 617877.383 3567726.717
T-62 ZM 1 260 18/8/2020
T-63 ZM 1 260 16/8/2020
T-64 ZM 1 260 20/8/2020
Road Crossing Tank To Jandola
T-65 ZM 1 260 9/9/2020
T-66 ZM 60 262.459 616588.760 3567916.060

Total 10 0

PACKAGE NAME Foundation Date Foundation Complated Nos Erected Date Erection
PACKAGE #01 14-7-2020 43 19-8-2020 42
14-9-2020
PACKAGE #02 40 14/9/2020 22
PACKAGE #03 ….. 5 ….. 0
PACKAGE #04 ….. 21 ….. 0
PACKAGE #05 14-7-2020 25 ….. 18
PACKAGE #06 14/9/2020 6 ….. 0
PACKAGE #07 ….. 0 ….. 0
Total 140 82