Project: Hotel Sogo Davao

Location: Bajada Davao City


Subject: Concrete Pouring Monitoring

Volume as per
item Description Date of Pouring Design PSI
plan etimate

1 Footing 12/6/2019 5000.00

2 Footing 12/10/2019 5000.00

3 Footing 12/19/2019 5000.00

4 Footing and FTB 1/18/2020 5000.00

5 Footing and FTB 1/25/2020 5000.00

6 RW Cistern and Elevator Footing 1/29/2020 5000.00

7 Footing and I-3 and Column Gr-3 2/1/2020 5000.00

8 Shearwall and FTB 2/6/2020 5000.00

9 FOOTING , FTB & Elevator Shear 2/12/2020 5000.00

10 Column , FTB, Shear wall 2/14/2020 5000.00

11 ,sumpit slab, FTB Drive-in, column 2/19/2020 5000.00

cister slab,sumpit slab, FTB Drive-


12 2/25/2020 5000.00
in, column
13 Footing and column 3/3/2020 5000.00

14 Footing and column 3/10/2020 5000.00

14 Footing and column 3/13/2020 5000.00

15 STP FOOTING and column 3/17/2020 5000.00

16 FOOTING AND Lobby SLAB 3/22/2020 5000.00

17 Column ,FTB and Loobhy slab 9/8/2020 5000.00

18 DRIVE IN FTB, DRIVE IN FOOTING, 9/14/2020 5000.00


WALK IN RETAINING WALL

2nd floor slab D-E/4-6, FOOTING


19 9/26/2020 5000.00
I/9-10

STP WALL, Slab Ground floor,


20 column 9/29/2020 5000.00

21 Footing 10/9/2020 5000.00


21 Footing 10/9/2020 5000.00

22 Slab 2nd floor drive in 10/13/2020 5000.00

2nd floor slab walk in Gride line (A-


23 C)/7-10, Retaining wall(B-C/2), C- 10/21/2020 5000.00
3/4 and footing

2nd floor slabdrive in Gride line (F-


24 10/26/2020 5000.00
G)/4-9, C-G/3 and footing

25 STP AND Retaining Wall 10/30/2020 5000.00

1st floor slab walk in Gride line (A-


C)/4-5, Retaining wall(A/1-4,1/A-
26 B'), 2nd level column (C2&C3 10/A- 11/14/2020 5000.00
C), (C3 9/B), (C3 8'-C), (C3 8/B), FTB
5-7'/E'-G

2nd floor slab, beams and C3(11)


27 walk-in GL: A-C/4-7 and FTB GL: G- 11/26/2020 5000.00
H/4,5,8&9 E-F/8-9
2nd Floor level GL: G-H/4'-10 2nd
28 Floor level GL: C-D/2-4 1/12/2020 5000.00

Total Volume
Total paid
Volume as per Testing(days)
Location Gridline Payment
actual 7 14 28
13-Dec-19 20-Dec-19 3-Jan-20

72 4344 4719 5227 E-10 TO E-5 / D-7 352,800.00


To D5
17-Dec-19 24-Dec-19 7-Jan-20

35 4431.5 4929.5 F-9 TO F-5 171,500.00


5327
26-Dec-19 2-Jan-20 16-Jan-20
Cistern and Footing A-
120 4419.3 4485 5327 7to 8 and Footing D 588,000.00
8to10
25-Jan-20 1-Feb-20 15-Feb-20
C5-10 / SUMPIT F / AB-5
164 4300.0 4400 4770 to 7 Footing column D5 803,600.00
to 7 EtoG 5 to 10
1-Feb-20 8-Feb-20 22-Feb-20
SUMPIT WALL and FTB
47 3120.0 5102 Walkin And Footing D to 230,300.00
5600 G -3
5-Feb-20 12-Feb-20 26-Feb-20
RW Cistern and Elevator
55 4850.0 5820 4889 Footing 269,500.00

8-Feb-20 15-Feb-20 29-Feb-20


Footing and I-3 and
62 4260.0 4579 Column Gr-3 303,800.00
5008
13-Feb-20 20-Feb-20 5-Mar-20
Footing and I-3 and
37 5153.0 6000 Column Gr-3 181,300.00
19-Feb-20 26-Feb-20 11-Mar-20

Footing Grd- G, FTB GRD


72 4704 5900 I-3, Elevator Shear Wall 352,800.00

21-Feb-20 28-Feb-20 13-Mar-20

38 4887.0 5239 5900 Shear wall Grd - C, 186,200.00


Column Grd -H
26-Feb-20 4-Mar-20 18-Mar-20

24 5073.0 5086 6599 FTBGrid line E to G /5 119,400.00


to 10,Cistern,sumpit
3-Mar-20 10-Mar-20 24-Mar-20

46 5005.0 6599 FTBGrid line E to G /5 225,400.00


to 10,Cistern,sumpit
10-Mar-20 17-Mar-20 31-Mar-20
Footing Grd line b' to
C/ 1-2, Column Grd
38 5383.0 6837 line H and E, F /5 to 186,200.00
10
17-Mar-20 24-Mar-20 7-Apr-20

54 6599 Grd line footing 4 Drive 264,600.00


in , elevator column,
gridlin I3 , H3/H4
20-Mar-20 27-Mar-20 10-Apr-20

40 6440 Grd line footing 4 Drive 205,200.00


in , elevator column,
gridlin I3 , H3/H4
24-Mar-20 31-Mar-20 14-Apr-20

43 6599 Grd line footing 4 Drive 210,700.00


in , elevator column,
gridlin I3 , H3/H4
29-Mar-20 5-Apr-20 19-Apr-20

105 6678 514,500.00


Footing and GF Slab A-D/

15-Sep-20 22-Sep-20 6-Oct-20

80 4270.0 4599.0 4540.0@ 29 day, column


6699.50and FTB @ and
GF Slab@43
A-D/ days 392,000.00

21-Sep-20 28-Sep-20 12-Oct-20

C-E/2-4 , G/6-8 , B-C/1-


76 4700.0 4800.0 5572.8 2,C/2-4 372,400.00

3-Oct-20 10-Oct-20 24-Oct-20

C-E/2-4 , G/6-8 , B-C/1-


88 4200.0 4551.0 5755.7 2,C/2-4 440,200.00

6-Oct-20 13-Oct-20 27-Oct-20

C-E/2-4 , G/6-8 , B-C/1-


40 4500.0 4763.0 5,669.90 2,C/2-4 196,000.00

16-Oct-20 23-Oct-20 6-Nov-20

21 4742.0 5961.7 Grid line H /8-10 96,600.00


21 4742.0 5961.7 Grid line H /8-10 96,600.00

20-Oct-20 27-Oct-20 10-Nov-20

4887.5,
36 4346.0 4951.0 Gridline E"-F /4-8 176,400.00
6034.80

28-Oct-20 4-Nov-20 18-Nov-20

100 3974.0 4986.0 5883.7/5824.9 A-C/7-10 , B-C/2 , C-3/4 490,000.00

2-Nov-20 9-Nov-20 23-Nov-20

55 5064.0 5064 6627.2/6563.5 F-G/4-9,C-G/3 269,500.00

6-Nov-20 13-Nov-20 27-Nov-20

14 4440.0 F-G/4-9,C-G/3 68,600.00

5109
21-Nov-20 28-Nov-20 12-Dec-20

100 3691.0 F-G/4-9,C-G/3 490,000.00

GL: A-C/4-7 / FTB GL: G-


82 H/4,5,8&9 E-F/8-9
2nd Floor level
GL: G-H/4'-10
75 2nd Floor level
GL: C-D/2-4

1662 5000 psi 8,157,500.00


980 cum meter 4,548,400.00

3,609,100.00
REMARKS

Paid

Paid

paid

Paid

paid

paid

paid

paid

cheque Reject Cheque/


return to
manila office

paid

paid

paid
paid 1 926
2 567

paid

paid

paid

paid

on process
transfer to
manila

for transfer
10/12/20

for transfer
10/12/20

for transfer
10/12/20
Payment Made