Detail Work Position of Under Construction 132 D/C

PEZU -TANK-JANDOLA TRANSMISSION UNE UNDER USAID FATA INFRASTRUCTURE PROGRAM (FIP)

Package 1: Starts form Pezu Grade Station and Comprises of 45 No Location i:e 1-45
Firm Name: M/S Abid Hussain & Co

Sr# No Foundation Completed Towers Erected Stringing Status Remarks


1) Due to short distance the one number tower at
Straining work location no 39 as has been discarded.
completed at 26
1 43 nos 42 nos
no Location i:e
2) The foundation work at location no 2 completed,
18 to 33 erection of tower is remaining
33 to 45
Package 2: Package II Comprises from location no 46 -90

Firm Name: ZK Associates

Sr# No Foundation Completed Towers Erected Stringing Status Remarks


1) In Package no 2 , the Tower location no 81 (ZM-30) is
under the thread of stay, as the owner of land is not allowing
to work on the said location. Executive Engineer GC is
requested to resolve the Issue of ROW.
1 40nos 22 nos
Package 3: Package III Comprises from location no 91 -135

Firm Name: ZK Associates

Sr# No Foundation Completed Towers Erected Stringing Status Remarks

1 5nos Nil
Package 4: Package IIII Comprises from location no 136 -181

Firm Name: Shamas Ul Tamraiz & Brothers

Sr# No Foundation Completed Towers Erected Stringing Status Remarks


1) After excavation, accumulation of water observed at location no
158 & 159, status to be decided, either water logged foundation i;e RCC is
required or PCC. Executive Engineer GC Division TESCO is requested to
depute his representatives do decide the states of work to be required at
site with the coordination of R E Power CAMEOS staff at Tank.
2) XEN Gc TESCO is requested to depute his officers to decide the
1 21nos Nil status of erection of terminal tower no 180 at Tank Grid & rest of the
towers at location no 179,178 & 177 as there is severe problem of line
route in termination at tank grid , due to kiln of brick Bata, Grave yard
,private plots and Nala. According to the present demarkation the
conductor falls right on the top of the kiln and similarly grave yard & plot
owners also not allowing the towers in their premises.
3) The owner of land at location no 176 is also continuously insisting for
shifting of towers from his plot, the foundation work of said tower already
completed matter also required to be resolved by XEN GC Division TESCO.
Package 5: Package 5 starts from Tank Grid station towards Jandola & Comprises of locations no 1-49

Firm Name: Fida Muhammad & Sons

Sr# No Foundation Completed Towers Erected Stringing Status Remarks


1) The work have been started by the contractor at water logged
locations that has been identified as location no 7-27 & 33.a
2) The matter of ROW at location no 13 & 33 steel persist, XEN GC
TESCO is requested to resolve the issue of ROW, as the owners of the
land are no allowing for the work and location no 33 under stay. ed as
1 25nos 18 nos per drawings & foundation work completed at location no 14,15,16,&
17.
3) XEN Gc TESCO is requested to depute his officers i;e is SDos to
decide the erection of terminal tower at Tank Grid toward Jandola.
Package 6: Package 6 comprises of locations no 50-99

Firm Name: Shamas Ul Tamraiz & Brothers

Sr# No Foundation Completed Towers Erected Stringing Status Remarks


16 no locations handed to contractor for execution of work & digging
work not yet started by the contractor.

10nos Nill

1
Package 7: Package 7 comprises of locations no 100-149

Firm Name: Shamas Ul Tamraiz & Brothers

Sr# No Foundation Completed Towers Erected Stringing work Remarks

Nil Nil Work not yet started


7