ACTIONS TO ACTUAL
SL. SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN BY (R1) (R2) (R3) (R4) COMPLITION
NO. Schedule Date (R0): IN DAYS (Status Date:-09-10-2023)
: DATE
A Safety
If they fail to provide manpower for dengue
SMN/
A.0 Dengue Care precaution then Ambuja will engage manpower
Ambuja
and the cost will be deducted from their bill
Only 1 no aluminium ladder is available at Block-E.
MS/Aluminium Block-D &
4 nos aluminium ladder required for each block SMN 07-10-2023 Only 2 Nos aluminium ladder is available at Block-D.
Ladder Block-E
Block-C (No Aluminum Ladder)
SMN said basement housekeeping work will be Basement House kipping work not completed. House
completed on 04-08-2023. kipping work is in progress.
Block-D Ambuja said if SMN unable to achieved this SMN 04-08-2023 11-08-2023 24-08-2023 SMN engaged manpower from 20-08-2022.
target date, Ambuja will be depute manpower of 90 % Completed.
house kipping work on the head of SMN. Required revised date.
A.1 House keeping Basement Housekeeping work will be completed Basement House kipping work not completed. House
on 04-08-2023 kipping work is in progress.
Ambuja said if SMN unable to achieved this SMN engaged manpower from 20-08-2022.
Block-E SMN 04-08-2023 11-08-2023 24-08-2023
target date, Ambuja will be depute manpower of 90 % Completed.
house kipping work on the head of SMN. Required revised date.
PART-02 Civil Activity 24-09-2023 29-09-2023 Reinforcement and shuttering work is in progress.
Page 1 of 2
ACTIONS TO ACTUAL
SL. SMN Submitted DUE DATE DELAY/ADVANCE Remarks
AGENDA : Block Part DISCUSSION POINT : BE TAKEN BY (R1) (R2) (R3) (R4) COMPLITION
NO. Schedule Date (R0): IN DAYS (Status Date:-09-10-2023)
: DATE
Club
If they fails to achieve to complete the Raft and
Sankha Sir's
SMN R/Wall of club before puja then SM Nirman will SMN
Instruction
be descoped from Club
Ambuja requested to complete deck slab before PCC should be Pile Cap Scope: 25 Nos Excavation
Puja and requested to submitted catch up plan. completed on 28-06- done: 25 Nos
SMN shall given engineer on or before 28-08-2023. 23 PCC:- 24 Nos Pile Cap/ Sump area
C.8 Pile Cap and Raft SMN SMN 03-04-2023 02.05.2023 31.05.2023 30-06.2023 10-09-2023 14-10-2023 -190
Raft should be RCC : 23nos cap casting done. 2 Nos Pending.
completed on 02-07-
2023
D Other Issues :
D.5 Concrete Pipe Shortage of concrete pipe line. SMN 09-08-2023 Sufficient conncrete pipe not available at site.
Page 2 of 2