MINUTES OF MEETING

Meeting: Project Review Meeting with Simplex Infrastructure Meeting Date: 03-Oct-23
Meeting Number: (PM 085 PRM 063) Meeting Time: 4:00 PM

Date of Issue: 04-Oct-23


Agenda: Time of Issue: 7:00 PM
List of Participants :
SL Name Agency Code Party
No.
01 Mr. Madan Bhar SPL Estates Private Limited (SPLEPL) MB Developer

02 Mr. Abir Sengupta SPL Estates Private Limited (SPLEPL) AS Developer

03 Mr. Subramanyam Gujari SPL Estates Private Limited (SPLEPL) SG Developer

04 Mr. Goutam Bhattacharjee Shapoorji Pallonji & Company Pvt Ltd GB Contractor

05 Mr. Amit Bhowmik Shapoorji Pallonji & Company Pvt Ltd AB Contractor

06 Mr. Jayprakash Pradhan Shapoorji Pallonji & Company Pvt Ltd JP Contractor

07 Mr. Sudip Kar Masters Developement Management(India) Pvt. Ltd. (MDM) SK Project Management Consultant

** Personnels could not attend.

Details of Minutes described in the next sheet(s).

Page 1 of 3
MASTERS

MINUTES OF MEETING
Sr. Raised Action
Subject Points/Issues Raised Comments and Decisions Date
No. by by
01 Work Progress and Other pertinent issues

a Site Establishment The schedule of commencement of Site Infrastructure has been enquired. SPLEPL SPCPL has provided the following updates. SPCPL As mentioned
MDM 1. DG- 40 KVA DG has already been delivered at site on 3 Oct 2023.
2. Porta Cabin - 2 nos. Porta Cabin (Site Office & Store) from Rajarhat Yard shall be delivered by 5
Oct 2023.
3. Batching Plant - The dismantling of CP-30 Plant is already in process at ongoing Guwahati
Project & is expected to be delivered by this month end OR early next month. However, the Plant
shall be commissioned by 15 Nov 2023.
4. Labour Camp - The dismantling of Labour Camp is already in process at ongoing Delhi Project &
is expected to be delivered by this month end OR early next month. However, the Camp shall be
operational by 15 Nov 2023.
5. Quality Laboratory - This shall be operational by 15 Nov 2023.
6. Construction Power - Follow up with the concerned Authority is already in progress.
7. Others - 125 KVA DG for Plant , Transit Mixers etc. shall be delivered at site by 15 Nov 2023.
However, SPCPL has assured to commence the foundation work of Plant & Camp by 10 Oct 2023.

b Project Schedule SPCPL has been requested to submit the Project Schedule in line with LOI. SPLEPL The Project Schedule shall be submitted by 12 Oct 2023 for review & approval. SPCPL 12 October 2023
MDM

c Project Quality Manual. SPCPL has been requested to expedite the submission of Quality Manual. SPLEPL The Quality Manual shall be submitted by 16 Oct 2023. SPCPL 16 October 2023
MDM The submitted Documents shall be vetted by all concerned for approval.

d Plant and Machinery deployment SPCPL has been requested to submit the Plant and Machinery deployment SPLEPL The Plant and Machinery deployment schedule shall be submitted by 12 Oct 2023. SPCPL 12 October 2023
schedule schedule MDM

e Work Methodology SPCPL has been requested to submit the Work Methodology of all the activities SPLEPL The submission of Work Methodology of certain activities will be commenced from 16 Oct 2023 & the SPCPL 16 October 2023
Inspection Test Plan (ITP) which are pertinent to the Scope of Work as per LOI. MDM Work Methodology of all the activities shall be submitted by the end of October 2023. 31 October 2023
Activity-wise checklist. The submitted Documents shall be vetted by all concerned for approval.

f Safety Manual SPCPL has been requested to expedite the submission of Safety Manual. SPLEPL The Safety Manual shall be submitted by 16 Oct 2023. SPCPL 16 October 2023
MDM The submitted Documents shall be vetted by all concerned for approval.

g Contract Agreement It has been Clearly conveyed that all the above documents will be part of SPLEPL SPLEPL accepted & agreed upon to the same. SPCPL For necessary action.
Contract Agreement and therefore these documents must be submitted on MDM
priority.
h Project Cash Flow SPCPL has been requested to submit the Cash Flow in line with the Project SPLEPL SPCPL has assured the same by 12 Oct 2023 SPCPL 12 October 2023
Schedule MDM

i Manpower Deployment Schedule. SPCPL has been requested to submit the Manpower Deployment Schedule. SPLEPL SPCPL has assured the same by 15 Oct 2023 SPCPL 15 October 2023
MDM

j Detailed Organization Chart The Organization Chart to be resubmitted mentioning name and designation SPLEPL SPCPL has assured the same by 6 Oct 2023 SPCPL 06 October 2023
of the concerned person along with the date of deployment (Initial Submission MDM
21 Sep 2023)

04 Logistics Plan SPCPL has been requested to submit the Site Logistic Plan at the earliest where SPLEPL The Logistics Plan shall be submitted by 6 Oct 2023. SPCPL 06 October 2023
the location various site Establishment , Plant / machineries & approach Road MDM
shall be indicated clearly. SPLEPL shall accord their consent after due verification from their end.

1 All participants
Page 2 of 3
MASTERS

Sr. Raised Action


Subject Points/Issues Raised Comments and Decisions Date
No. by by

Notes To Recipients:
7 Departments & individuals are expected to implement any action as noted.

2 This minutes record the true understanding of the concern and intended action rising there from. Your agreement that the minutes form a true record of the discussion will be assumed unless adverse comments are received in writing
within two days of receipt of this MOM.

Page 3 of 3