You are on page 1of 2

Ref: BICPL/MUM/MOPA/23-24/004

Date: 07/09/2023
To,
M/s. GMR Goa International Airport Limited
Dadachiwadi Road, Nagzar, Taluka Pernem,
District: North Goa, Goa 403512

Kind Attn: Mr. VK Prasad

Dear Sir,

LOA No.: GMR/CGIAL/2023-24/LOA/024, dt. 29.05.2023


Work: Development of Green field International Airport at Mopa, Goa- Reply of delay in Execution-
Construction of Main Spine Road- Reg.

Ref.: GGIAL/BICPL/MSR/2023-24/1269, Dated 05.09.2023

We are in receipt of the letter referred above & would like to invite your kind attention to the
following:

1. Based on submitted plan, we have mobilized the equipments but due to continuous Rainfall at
site our targeted plans was hampering & our equipment was idle.

2. We are aware that, due to non- availability of Approach Road, excavated soil was kept aside of
road around 3months, now we are dumping the same, accordingly.

3. To recover the shortfall works, we are increasing the equipments simultaneously, details of same
are as under:

Equipments
4. Planned for deploy
Sl. No. Machinery Deployment available at site
(Nos) Qty. Date
1 Dozer with Ripper 3 2 07/09/2023
2 Dozer 1 1 10/09/2023
3 Excavator 4 2 15/09/2023
4 Surface Minor 0 1 07/09/2023
5 Motor Grader 1  - -
6 Compactor 1 -  -
7 JCB 0 1 05/09/2023
8 Water Tanker 1 1 08/09/2023
9 Dumper 10 32 09/09/2023
10 Bobcat Broomer 1  - -
Details of Recovery plan, Engineering and Procurement are enclosed as a Annexure-I and Annexure-
II.

Cont….2

Balajee Infratech and Constructions Pvt. Ltd.


{2}

We have also deployed the team for night shift work since 05/09/2023 i.e. Tuesday and giving
assurance will cover the all shortfalls due to several issues.

Thanking and assuring you of our best services at all times.

Yours faithfully,
For Balajee Infratech & Constructions Pvt. Ltd.,

Authorized Signatory

Enclosed: Original Copy of ABG


Cc.: The PM/GMR GIAL/Pernem, Goa

You might also like