Professional Documents
Culture Documents
Duration Manpower
Quantity Unit Productivity Unit Contract Value
(days) (No)
NA LS 1 1 RM500.00
12 nos 4 3 2 RM3,000.00
60 m 20 3 1 RM6,000.00
50 l 50 1 2 RM2,000.00
12 nos 3 4 3 RM8,000.00
6 m3 2 m3/d 3 3 RM6,000.00
3 m3 0.5 m3/d 6 4 RM12,000.00
6 m 3
3 m /d
3
2 2 RM2,000.00
NA LS 7 4 RM7,000.00
CRITICAL PATH METHOD
1 - Project Start
Legend: ES - Early Start 2 - Activity, Duration, Sequence
ES EF EF - Early Finish 3 - Activity Network Diagram
Activity Name LS - Late Start 4 - Forward Pass (ES & EF)
LS Duration LF LF - Late Finish 5 - Backward Pass (LF & LS)
TF = LF - EF TF - Total Float 6 - TF = LF - EF
= 0 = CRITICAL
10/5/2023 10/5/2023
Buy Paint
10/19/2023 1 10/19/2023
TF 14
10/5/2023 10/7/2023
Buy Timber
10/17/2023 3 10/19/2023
TF 12
Man-
Activity Duration ES EF TF 1 2
power
Determine Location 1 10/1/2023 10/1/2023 0 1 1
Sketch Design 3 10/2/2023 10/4/2023 0 2 2
Buy Timber 3 10/5/2023 10/7/2023 12 1
Buy Paint 1 10/5/2023 10/5/2023 14 2
Hire Workers 4 10/5/2023 10/8/2023 0 3
Excavate Trench 3 10/9/2023 10/11/2023 0 3
Construct Foundation 6 10/12/2023 10/17/2023 0 4
Backfill Foundation 2 10/18/2023 10/19/2023 0 2
Construct Store 7 10/20/2023 10/26/2023 0 4
Daily Manpower 1 2
Manpower Limit 4 4
7
6
No. of Manpower
5
4
3
2
1
0
1 2 3 4
OCTOBER 2023
3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
2 2
1 1 1
2
3 3 3 3
3 3 3
4 4 4 4 4 4
2 2
4 4
2 2 6 4 4 3 3 3 3 4 4 4 4 4 4 2 2 4 4
4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
RESOURCE CHART
7
6
5
4
3
2
1
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
'OCTOBER 2023
4 4 4 4 4
4 4 4 4 4 0 0 0 0 0
4 4 4 4 4 4 4 4 4 4
20 21 22 23 24 25 26 27 28 29 30 31
FINANCIAL S-CURVE
50,000
45,000
40,000
35,000
30,000
Cummulative
25,000
20,000
15,000
10,000
500
5,000
0
1
OCTOBER 20
2 3 4 5 6 7 8 9 10 11 12 13 14
1000 1000 1000 6000 4000 4000 2000 2000 2000 2000 2000 2000 2000
1500 2500 3500 9500 13500 17500 19500 21500 23500 25500 27500 29500 31500
2.15% 2.15% 2.15% 12.90% 8.60% 8.60% 4.30% 4.30% 4.30% 4.30% 4.30% 4.30% 4.30%
3.23% 5.38% 7.53% 20.43% 29.03% 37.63% 41.94% 46.24% 50.54% 54.84% 59.14% 63.44% 67.74%
45,000
40,000
35,000
4000
4000
30,000
Cummulative
25,000
20,000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
15,000
1000
1000
1000
1000
10,000
500
5,000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
'OCTOBER 2023
Daliy Cummulative
OCTOBER 2023
15 16 17 18 19 20 21 22 23 24 25 26 27
2000 2000 2000 1000 1000 1000 1000 1000 1000 1000 1000 1000 0
33500 35500 37500 38500 39500 40500 41500 42500 43500 44500 45500 46500 46500
4.30% 4.30% 4.30% 2.15% 2.15% 2.15% 2.15% 2.15% 2.15% 2.15% 2.15% 2.15% 0.00%
72.04% 76.34% 80.65% 82.80% 84.95% 87.10% 89.25% 91.40% 93.55% 95.70% 97.85% 100.00% 100.00%
6,000
5,000
4,000
Daily
3,000
2000
2000
2000
2000
2,000
1000
1000
1000
1000
1000
1000
1000
1000
1000
1,000
0
0
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
'OCTOBER 2023
Daliy Cummulative
28 29 30 31
0 0 0 0
46500 46500 46500 46500
7,000
6,000
5,000
4,000
Daily
3,000
2,000
1,000
0
0
31
DURATION S-CURVE
*Infamously known "physical" s-curve in Malaysia
** % Complete column in Microsoft Project is calculated based on Duration
*** % Complete column = Actual Duration column / Duration column
Weightage Weightage
Activity Duration ES EF
Dur. Cost
Determine Location 1 3.33% 1.08% 10/1/2023 10/1/2023
Sketch Design 3 10.00% 6.45% 10/2/2023 10/4/2023
Buy Timber 3 10.00% 12.90% 10/5/2023 10/7/2023
Buy Paint 1 3.33% 4.30% 10/5/2023 10/5/2023
Hire Workers 4 13.33% 17.20% 10/5/2023 10/8/2023
Excavate Trench 3 10.00% 12.90% 10/9/2023 10/11/2023
Construct Foundation 6 20.00% 25.81% 10/12/2023 10/17/2023
Backfill Foundation 2 6.67% 4.30% 10/18/2023 10/19/2023
Construct Store 7 23.33% 15.05% 10/20/2023 10/26/2023
TOTAL 30 100.00% 100.00%
TF Cost (RM) 1 2 3 4 5 6 7 8 9 10 11
0 500 1
0 3000 1 1 1
12 6000 1 1 1
14 2000 1
0 8000 1 1 1 1
0 6000 1 1 1
0 12000
0 2000
0 7000
TOTAL 46500
Daily Value (Days) 1 1 1 1 3 2 2 1 1 1 1
Cummulative (Days) 1 2 3 4 7 9 11 12 13 14 15
Daily Value (%) 3.33% 3.33% 3.33% 3.33% 10.00% 6.67% 6.67% 3.33% 3.33% 3.33% 3.33%
Cummulative (%) 3.33% 6.67% 10.00% 13.33% 23.33% 30.00% 36.67% 40.00% 43.33% 46.67% 50.00%
120%
10.00%
100%
6.67%
6.67%
80%
Cummulative
60%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
40%
20%
0%
1 2 3 4 5 6 7 8 9 10 11
OCTOBER 2023
12 13 14 15 16 17 18 19 20 21 22 23 24
1 1 1 1 1 1
1 1
1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1
16 17 18 19 20 21 22 23 24 25 26 27 28
3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33% 3.33%
53.33% 56.67% 60.00% 63.33% 66.67% 70.00% 73.33% 76.67% 80.00% 83.33% 86.67% 90.00% 93.33%
DURATION S-CURVE
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
3.33%
0.00%
0.00%
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
'OCTOBER 2023
1 1
1 1 0 0 0 0 0
29 30 30 30 30 30 30
12%
10%
8%
6%
Daily
3.33%
3.33%
4%
2%
0.00%
0.00%
0.00%
0.00%
0.00%
0%
4 25 26 27 28 29 30 31
TRACKING/UPDATING WORK PROGRAMME (DET
*Tracking/updating work programme is part of monitoring process. Monitoring is a process of identifying var
**Tracking requirement/steps: Set baseline > Cut-off/reporting/Data/Status Date > Planned % > Actual % > A
PERCENTAGE DURATION
TOTAL 30 3 2
Sketch Design 4 12
RAMME (DETAILED - DELAY BASED ON CPM)
s a process of identifying variance/changes or comparing between baseline/planned/scheduled against actual/as-built
e > Planned % > Actual % > Actual Start & Actual Finish
* Finish Variance column = Fin
ATION DATES
Actual Ahead/
Duration BL Start BL Finish Actual Start ES EF
Finish Delay
Progress Actual
% Start Actual Finish
33.33% 10/3/2023
tual/as-built
= User Input
* Finish Variance column = Finish column - Baseline Finish column (+ delay, - ahead)
COST Cut off date: 10/3/2023
Total Actual
Slack Cost Text3 Cost
Planned Actual
TF Cost (RM) 1 2 3 4 5 6 7 8 9 10 11 12
Cost (RM) Cost (RM)
12 6000 0 0
14 2000 0 0
0 8000 0 0
0 6000 0 0
0 12000 0 0
0 2000 0 0
0 7000 0 0
5.38%
3.23%
-2.15%
30
-0.65
OCTOBER 2023
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
TRACKING/UPDATING WORK PROGRAMME (SIM
*Tracking/updating work programme is part of monitoring process. Monitoring is a process of identifying var
**Tracking requirement/steps: Set baseline > Cut-off/reporting/Data/Status Date > Planned % > Actual %
PERCENTAGE DURATION DATES
TOTAL 2 30
Actual
Finish Cost Cost OCTO
Actual
EF Cost (RM) 1 2 3 4 5 6 7 8 9 10 11 12 13
Cost (RM)
10/7/2023 6000 0
10/5/2023 2000 0
10/8/2023 8000 0
10/11/2023 6000 0
10/17/2023 12000 0
10/19/2023 2000 0
10/26/2023 7000 0
46500 1500
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31