Name of Work:- REVISED ROUGH COST ESTIMATE FOR THE WORK PROGRAME FOR PROVISION OF MISSING FACILITIES IN NEWLY UPGRADED COLLEGES OF NURSING IN PUNJAB ONE AT NURSING COLLEGE SARGODHA.
(ADP NO 420 FOR THE YEAR 2023-24)
1 Provision of Missing Facilities in existing building (Building Portion) 15029436 15029436 11337564 26367000 11337564
E.I portion
Old block = 4000 Sft
Block 1 GF = 3300 Sft
Block 1 FF = 3300 Sft
i) Total = 10600 Sft 10600 P sft 295 3127000 3127000 3127000 0
S.I Portion
Old block = 4000 Sft
Block 1 GF = 3300 Sft
Block 1 FF = 3300 Sft
New Block GF = 3334 Sft
New Block FF = 3334 Sft
ii) Total = 17268 Sfrt 17268 P sft 162 2797416 2797416 2797416 0
Providing and fixing anti climb high security galvanized razor cut wire having
double sharp four U-shaped pointed 0.5 mm thick ( 22mmx15 mm barbs)
spaced @ 33 mm c/c cladded over 2.5 mm dia
high tensile Core wire making coil fencing of specified diameter @ 4"
c/c fixed on 2'-3" high M/S angle iron post 1½"x1½"x3/16"embeded
in base of PCC (1:2:4) (4"x4"x9") @ 4' apart i/c the cost of 2 No.
bars 3/8" dia welded horizantally with angle iron posts , binding wire,
painting of posts, etc. complete in all respects as pproved and directed
by the Engineer incharge.
5 18" dia 941 P rft 594.7 559613 559613 559613
9 Construction of OHR 10000 Gal capacity. 10000 P gal 450 4500000 4500000
1 x2 x5 x 3/8 x7 = 26 Cft
dismantling
floor Lav
1 x1 x15-1/4 x21-1/2 x 1/4 = 82 Cft
Total. = 82 Cft @Rs.2661.10%Cft Rs. 2182/-
3 Dismantling c conc reinforced, separating reinforcement from conc,
cleaning and straightening the same.
Take Quantity
item No 5 164 x6-3/4 x 4/9 = 503 Kg
Total = 503 Kg @Rs.34739.85/%Kg Rs. 174741/-
7 Mosaic dado or skirting with one part of cement
and marble powder in the ratio of 3:1 and two
parts of marble
chips, laid over ½"(13 mm) thick cement plaster
1:3, w/o rubbing and polishing
using grey cement 1/2" thick.
1 x2 x5 x 3/8 x7 = 26 Cft
1 x2 x10 x 3/8 x7 = 53 Cft
old block
comp lab 1 x1 x19 x18-3/4 x 1/8 = 45 Cft
old block
= 15 Nos
= 3 Nos
= 10 Nos
block 1 GF = 7 Nos
block 1 FF = 7 Nos
Total. = 42 No @Rs.576.20/E Rs. 24200/-
13 Removing windows with chowkat.
old block
= 19 Nos
block 1 GF = 16 Nos
block 1 FF = 16 Nos
Total. = 51 No @Rs.449.45/E Rs. 22922/-
14 P/F 1-1/2" thick solid flush door comprising of 2.5 mm thick Commercial
ply compressed over 2.5 mm thick commercial ply over 1" thick packing
wood in style and rails under proper pressure i/c the cost of nails, tower
bolt , handles, glue, sawing charges, Painting charges, sand papering and
3/8" thick matching wooden lipping as approved and directed by the
Engineer Incharge.
P/F M.S. angle iron 1½"x 1½"x ¼" (40x40x6 mm) welded
with M.S. flat 2"x ¼" (50 mm x 6 mm)
old block
10 x1 x4 x8-1/2 = 340 Sft
block 1 GF 7 x1 x4 x8-1/2 = 238 Sft
block 1 FF 7 x1 x4 x8-1/2 = 238 Sft
Total. = 816 Sft @Rs.1324.80/Sft Rs. 1081037/-
15 Providing and fixing 1st class solid wood wrought joinery in panelled or
panelled and glazed doors and windows of specified thickness with 1"
thick solid wood panels with step and 1-1/2"x2-1/2" beadings all around
the panels i/c the cost of Tower bolt and handles complete in all respect
(Excluding the cost of sliding bolt,lock and chowkats (frame), etc.) as
approved and directed by the Engineer Incharge.
Ash/oak wood door 2" thick
old block
1 x1 x12 x8-1/2 = 102 Sft
block 1 GF 1 x1 x12 x9-1/2 = 114 Sft
block 1 FF 1 x1 x12 x9-1/2 = 114 Sft
Total. = 330 Sft @Rs.3410.10/Sft Rs. 1125333/-
16 Providing and fixing 2" wide MS/ GI Chowkat singel/double rebate made
of 16 SWG MS sheet pressed/welded / supported with M.S. flat 1-
1/4"x1/8" i/c 6" long M.S. Flat 1"x1/8"hold fasts (6-Nos) welded/
screwed, punching of lock hole covered with MS Box,coating with
antirust paint including filling with cement sand mortar (1:8) and
embedding hold fast in cement concrete (1:2:4) ,complete in all respect as
approved and directed by Engineer Incharge.
15" wide.
old block
1 x1 x12 x8-1/2 = 102 Sft
block 1 GF 1 x1 x12 x9-1/2 = 114 Sft
block 1 FF 1 x1 x12 x9-1/2 = 114 Sft
Total. = 330 Sft @Rs.857.55/Sft Rs. 282992/-
17 Preparing surface and
Lacquar polish to reveal wooden grains by
application of multiple coats of wood sealer , sand papering with different
no of sandpapers and Lacquar to make glossy surface finish i/c the cost of
cotton, thinner, wood sealer complete in all respects as approved and
directed by the Engineer Incharge.
Glossy finish
old block
1 x1 x12 x8-1/2 = 102 Sft
block 1 GF 1 x1 x12 x9-1/2 = 114 Sft
block 1 FF 1 x1 x12 x9-1/2 = 114 Sft
Total. = 330 Sft @Rs.258.05/Sft Rs. 85157/-
17 i P/F fiber glass door of approved quality and design i/c chowkat complete in all respects as
approved and directed by the Engineer Incharge.
old block
comp lab 1 x1 x19 x18-3/4 = 356 Sft.
1 x1 x18-3/4 x19 = 356 Sft.
anatomy lab 2 x1 x19-1/4 x18-3/4 = 722 Sft.
sci lab
3 x1 x12 x16 = 576 Sft.
conf room 1 x1 x23-1/4 x12 = 279 Sft.
cills 20 x1 x4 x 3/4 = 60 Sft.
Block 1 GF
room 1 x1 x12-3/4 x21-3/4 = 277 Sft.
room 1 x1 x22 x13 = 286 Sft.
room 1 x1 x22 x13 = 286 Sft.
room 1 x1 x22 x13 = 286 Sft.
kit 1 x1 x22 x13 = 286 Sft.
cills 8 x1 x4 x 3/4 = 24 Sft.
Block 1 FF
hall 1 x1 x23 x28 = 644 Sft.
room 1 x1 x12-3/4 x21-3/4 = 277 Sft.
room 1 x1 x22 x13 = 286 Sft.
room 1 x1 x22 x13 = 286 Sft.
kit 1 x1 x22 x13 = 286 Sft.
cills 8 x1 x4 x 3/4 = 24 Sft.
old block
comp lab 1 x1 x2 x(18-3/4 +19-1/6) x3 = 228 Sft.
anatomy lab 2 x1 x2 x(19-1/4 +18-3/4) x3 = 456 Sft.
1 x1 x2 x(19 +18-3/4) x3 = 227 Sft.
corr 1 x1 x2 x(19-4/7 +7 ) x3 = 160 Sft.
corr 1 x1 x2 x(51-3/4 +6-1/2) x3 = 350 Sft.
1 x1 x2 x(15-3/4 +23-5/8) x3 = 236 Sft.
sci lab
3 x1 x2 x(12 +16 ) x3 = 504 Sft.
toilet block 1 x1 x2 x(9-3/4 +16 ) x10 = 515 Sft.
3 x1 x2 x(3 +3-3/4) x10 = 405 Sft.
2 x1 x2 x(4 +6 ) x7 = 280 Sft.
conf room 1 x1 x2 x(23-1/6 +12 ) x3 = 211 Sft.
back corr 1 x1 x2 x(18-1/2 +6-1/3) x3 = 149 Sft.
bath 2 x1 x2 x(6-1/3 +4-1/2) x7 = 303 Sft.
stair hall 1 x1 x2 x(13-1/3 +20-1/2) x3 = 203 Sft.
Block 1 GF
porch 1 x1 x2 x(12 +11-3/4) x3 = 143 Sft.
stair hall 1 x1 x2 x(13-1/3 +20-1/2) x3 = 203 Sft.
room 1 x1 x2 x(12-3/4 +21-3/4) x3 = 207 Sft.
hall 1 x1 x2 x(23 +28 ) x3 = 306 Sft.
corr 1 x1 x2 x(13 +7 ) x3 = 120 Sft.
room 1 x1 x2 x(22 +13 ) x3 = 210 Sft.
room 1 x1 x2 x(22 +13 ) x3 = 210 Sft.
room 1 x1 x2 x(22 +13 ) x3 = 210 Sft.
corr 1 x1 x2 x(13 +7 ) x3 = 120 Sft.
lav 1 x1 x2 x(13-3/4 +20 ) x12 = 810 Sft.
kit 1 x1 x2 x(22 +13 ) x5 = 350 Sft.
cills 8 x1 x2 x(4 + 3/4) x3 = 228 Sft.
New block GF 1 x1 x2 x(11 +9 ) x3 = 120 Sft.
1 x1 x2 x(16 +11 ) x3 = 162 Sft.
1 x1 x2 x(4-1/2 +9 ) x3 = 81 Sft.
2 x1 x2 x(18 +12 ) x3 = 360 Sft.
2 x1 x2 x(28 +16 ) x3 = 528 Sft.
1 x1 x2 x(20 +16 ) x3 = 216 Sft.
New block FF 1 x4 x2 x(28 +16 ) x3 = 1056 Sft.
1 x1 x2 x(15 +8 ) x3 = 138 Sft.
1 x1 x2 x(15 +8 ) x3 = 138 Sft.
2 x1 x2 x(18 +12 ) x3 = 360 Sft.
old block
comp lab
anatomy lab 2 x1 x2 x(19 +18-3/4) x7 = 1057 Sft.
corr 1 x1 x2 x(19-4/7 +8 ) x7 = 386 Sft.
corr 1 x1 x2 x(51-3/4 +8 ) x7 = 837 Sft.
1 x1 x2 x(24-3/4 +16 ) x7 = 571 Sft.
toilet block 1 x1 x2 x(9-3/4 +16 ) x7 = 361 Sft.
3 x1 x2 x(3 +3-3/4) x7 = 284 Sft.
2 x1 x2 x(4 +6 ) x7 = 280 Sft.
back corr 1 x1 x2 x(18-1/2 +6-1/3) x7 = 348 Sft.
bath
Block 1 GF 2 x1 x2 x(6-1/3 +4-1/2) x7 = 303 Sft.
porch 1 x1 x2 x(12 +11-3/4) x7 = 333 Sft.
stair hall 1 x1 x2 x(13-1/3 +20-1/2) x7 = 474 Sft.
hall 1 x1 x2 x(23 +28 ) x7 = 714 Sft.
corr 1 x1 x2 x(14-3/4 +7 ) x7 = 305 Sft.
corr 1 x1 x2 x(14-3/4 +7 ) x7 = 305 Sft.
lav 1 x1 x2 x(13-3/4 +20 ) x5 = 338 Sft.
4 x1 x2 x(3-1/2 +5 ) x5 = 340 Sft.
kit
Block 1 FF 1 x1 x2 x(22 +13 ) x7 = 490 Sft.
hall 1 x1 x2 x(23 +28 ) x7 = 714 Sft.
room 1 x1 x2 x(12-3/4 +21-3/4) x7 = 483 Sft.
corr 1 x1 x2 x(7 +7 ) x7 = 196 Sft.
corr 1 x1 x2 x(14-3/4 +7 ) x7 = 305 Sft.
lav 1 x1 x2 x(13-3/4 +20 ) x5 = 338 Sft.
4 x1 x2 x(3-1/2 +5 ) x5 = 340 Sft.
lav 1 x1 x2 x(22 +13 ) x5 = 350 Sft.
4 x1 x2 x(3-1/2 +5 ) x5 = 340 Sft.
stair hall 1 x1 x2 x(13-1/3 +20-1/2) x7 = 474 Sft.
New block GF 2 x1 x2 x(26 +14-1/3) x7 = 1129 Sft.
room 1 x1 x2 x(11 +18 ) x7 = 406 Sft.
1 x1 x2 x(16 +11 ) x7 = 378 Sft.
1 x1 x2 x(4-1/2 +9 ) x7 = 189 Sft.
2 x1 x2 x(18 +12 ) x7 = 840 Sft.
2 x1 x2 x(28 +16 ) x7 = 1232 Sft.
New block FF 1 x4 x2 x(28 +16 ) x7 = 2464 Sft.
1 x1 x2 x(15 +8 ) x7 = 322 Sft.
1 x1 x2 x(15 +8 ) x7 = 322 Sft.
Total. (A) = 18548 Sft
Deductions
Old block GF 6 x1 x6 x6 = 216 Sft
1 x1 x6 x4-1/2 = 27 Sft
2 x1 x6-1/3 x6 = 76 Sft
1 x1 x6-1/2 x8-1/2 = 55 Sft
V 4 x1 x2-1/2 x2-1/2 = 25 Sft
1 x1 x4 x1-1/2 = 6 Sft
2 x1 x6-1/3 x6-1/3 = 80 Sft
1 x1 x4-1/2 x6 = 27 Sft
2 x1 x4 x1-1/2 = 12 Sft
V 5 x1 x5 x1-1/2 = 38 Sft
block 1 GF
W1 15 x1 x3 x7 = 315 Sft
2 x1 x4 x6 = 48 Sft
V 5 x1 x5 x1-1/2 = 38 Sft
stair hall 1 x2 x3 x11-1/2 = 69 Sft
block 1 FF
W1 15 x1 x3 x7 = 315 Sft
2 x1 x4 x6 = 48 Sft
V 5 x1 x5 x1-1/2 = 38 Sft
stair hall 1 x2 x3 x11-1/2 = 69 Sft
D old block
10 x1 x4 x8-1/2 = 340 Sft
block 1 GF 18 x1 x4 x8-1/2 = 612 Sft
block 1 FF 18 x1 x4 x8-1/2 = 612 Sft
Total. (B) = 3066 Sft
Net Total (A-B) = 15482 Sft @Rs.3770.10%Sft Rs. 583687/-
34 Painting with emulsion paint 1 coats old surface.
W 44 x1 x6 x2 = 528 Sft
10 x1 x2-1/2 x2 = 50 Sft
Total = 578 Sft @Rs.696.75/Sft Rs. 402722/-
38 Providing and laying Prepolished Granite of
specified thickness and shade of full width of
approved quality laid with adhesive bond over
3/4" thick (1:2) cement sand mortor bed ,
complete in all respect as approved and
directed by the Engineer Incharge.
i) 3/4" thick.
Disposal of
material. Take Qty item No.1 = 1156 Cft
Total = 1156 Cft @ 1784.00/%cft Rs.20623/-
Rs.25869539/-
= 2 No
Total. = 2 No @Rs.576.20/E Rs. 1152/-
4 Removing windows with chowkat.
= 5 No
Total. = 5 No @Rs.449.45/E Rs. 2247/-
5 Providing and fixing 1st class solid wood wrought joinery in panelled or
panelled and glazed doors and windows of specified thickness with 1"
thick solid wood panels with step and 1-1/2"x2-1/2" beadings all around
the panels i/c the cost of Tower bolt and handles complete in all respect
(Excluding the cost of sliding bolt,lock and chowkats (frame), etc.) as
approved and directed by the Engineer Incharge.
Ash wood/oak wood door
2" thick
2 x1 x4 x8-1/2 = 68 Sft
Total. = 68 Sft @Rs.3410.10/Sft Rs. 231887/-
6 Preparing surface and Lacquar polish to reveal wooden grains by
application of multiple coats of wood sealer , sand papering with different
no of sandpapers and Lacquar to make glossy surface finish i/c the cost of
cotton, thinner, wood sealer complete in all respects as approved and
directed by the Engineer Incharge.
Glossy finish
1 x5 x6 x8 = 240 Sft
Total. = 240 Sft @Rs.1494.05/Sft Rs. 358572/-
8
Providing and fixing Aluminum Fly screen comprising of Fiber/Aluminum wire guaze (Malasian
fixed in aluminum frame of approved manufacturer brownze Colour/powder coated of size1-
1/2"x1/2" and 1.6mm thick with rubber gasket i/c cost of Hardwares as approved and directed
by the engineer incharge.complete in all respect
1 x 1/2 x6 x8 = 24 Sft
Total. = 24 Sft @Rs.529.05/Sft Rs. 12697/-
9 Providing and fixing M.S. grill fabricated with MS Square polished
Vertical/horizontal Bars of specified size @ 4" c/c ' passed through
punched holes in MS Patti of 1-1/4"x1/8" i/c the cost of 1-1/4"x1/8''
MS patti for Frame of windows and painting 3 coat complete in all
respect as approved and directed by the Engineer Incharge.
i) 3/8" square bars.
1 x1 x6 x8 = 48 Sft
Total. = 48 Sft @Rs.1054.65/Sft Rs. 50623/-
10 Providing and laying superb quality Porcelain
glazed tiles flooring of
MASTER /equivalant brand of specified size in
approved design,Color and Shade
with adhesive/bond over 3/4"thick (1:3)
cement plaster i/c the cost of
sealer for finishing the joints i/c cutting
grinding complete in all
respect as approved and directed by the
Engineer Incharge.
a) Full body glazed tiles
ii) 600 mm x 600 mm
Disposal of
material. Take Qty item No.1 = 140 Cft
Total = 140 Cft @ 1784.00/%cft Rs.2498/-
Total Rs.1796289/-
B/wall Jungla
F/S 1 x2 x305 x2 = 1220 Sft
Hostels b/s 1 x2 x350 x2 = 1400 Sft
new building 1 x2 x200 x2 = 800 Sft
Resi side 1 x2 x490 x2 = 1960 Sft
Total. = 5380 Sft @Rs.1477.05/%Sft Rs. 79465/-
5 Painting to doors and windows 2 coats
old surface.
3 x4 x4 x3 = 144 Cft
Total = 144 Cft
@ 13994.65 /%0Cft 2015
2 C conc (1:6:12) in F&P 3 x4 x4 x 1/2 24 Cft
@ 24907.2 /%Cft 5978
3 R.C.C (1:2:4) in slab of raft ect.
3 x3-1/2 x3-1/2 x 3/4 = 28 Cft
3 x2-5/8 x2-5/8 x 1/2 = 10 Cft
3 x2-1/4 x2-1/4 x9-1/2 = 144 Cft
Total = 182 Cft
@ 543 /Cft 98924
4 Fabrication of M.S reinforcement i/c
cutting bending lying in position i/c cost
of binding wire etc.
Take 6lb/Cft Qty item No.3 = 558 Kg
@ 34739.85 /%Kg = 193830
5 Pacca brick work c/s(1:4) mortar other
than building upto 10' ht.
6 x2-5/8 x 3/8 x10 = 59 Cft
6 x2-5/8 x 3/8 x10 = 59 Cft
Total = 118 Cft
@ 37305.6 /%Cft 44067
6
Rate
Qty Per Unit Amount
MATERIAL
a)
1 Main frame angle iron 2"x2"x3/8" double to make box
2*(2*20)+2*(4*8) 144 Rft
4.63 lb/Rft 303.00 Kg.
Horizontal middle MS
flat 2"x3/8" 75 Rft
2.53 lb/Rft 86.00 Kg.
Total 1708.00
Wastage
5% 85.40
Total 1793.40 Kg. 260.00 Per Kg. 466284.00
MS Sheet 1/16" thick
3 12.015 160 Sft
2.55 lb/sft 408.00 Kg.
Wastage
5% 89.67
Total 497.67 Kg. 350.00 Per Kg. 174185.00
4 Wrought iron moulded designs
Long flowers 112.00 Nos. 1340.00 Each 150080.00
Small flowers 224.00 Nos. 850.00 Each 190400.00
Cap type 28.00 600.00 Each 16800.00
5 Cost of Mono gram Shield 30000.00
6 Cost of Locking arrangement 2000.00
7 Cost of roller bearing for gate 6000.00
8 Metallic painting i/c steel putty etc complete 360.00 Sft 80.00 /Sft 28800.00
Total 1064549.00
Contractor's Profit &
Overheads 20.00 Percent 84816.00
Total 1149365.00
LABOUR
1 Labour for cutting jointing welding etc 3102.07 Kg 60.00 /Kg 186124.20
2 Labour for fitting at site mason 2.00 No. 1500.00 per day 3000.00
3 Cooly un skilled 4.00 No. 1000.00 per day 4000.00
4 Transportation from workshop to site of work 3000.00
Total 196124.20
Sundries 10.00 Percent 19612.42
Total 215736.62
Contractor's Profit &
Overheads 20.00 Percent 43147.32
Total 258883.94
(ABSTRACT OF COST)
Sr. No. Description Amount
1 x1 = 1 job
Total = 1 job @ 15960.60/job Rs.15961/-
6 Boring of tubewell (Detail attached)
1 x1 = 1 job
Total = 1 job @ 87000.00/job Rs.87000/-
1 Boring of tube well in all type of soil except shingle and Gravel from GL to 100'
depth 4" dia
1x100 60 Rft
Total 60 Rft 417.20 P.Rft Rs. 25032/-
2 Providing / Installation of PVC strainer of BSS class D in tube well bore hole 2" dia
60 Rft
Total 157.05
60 Rft P.Rft Rs. 9423/-
3 Providing / Installation of PVC blind pipe of BSS class D in tube well bore hole 8"
dia
1x40
20 Rft
Total 1711.50
20 Rft P.Rft Rs. 34230/-
40 mm dia
65 Rft 260.80 1 Rs. 16952/-
Total 87078
Say 87000
6" dia
MB 10 x10 = 100 Rft
Total = 100 Rft @ 285.20/Rft Rs.28520/-
9" dia
2 x110 = 220 Rft
2 x60 = 120 Rft
Total = 340 Rft @ 590.60/Rft Rs.200804/-
4 Construction of Man holes size 2 1/2'x3'(Analysis
Attached
= 10 No Rs.62600/- Rs.626000/-
Total. Rs. 904665/-
1 x 7/9 x4 x4 x4 = 50 Cft
Total = 50 Cft @Rs.16740.90%oCft Rs. 837/-
2 Dry rammed brick or stone
ballast 1 1/2"-2" gauge
= 1 No
Total = 1 No @Rs.25217.50/Set Rs. 25218/-
Executive Engineer
Sub Divisional Officer
Buildings Division
Buildings Sub Division
Sargodha
Sargodha
Electric cable for service connection
Making / Fixing of Fiber glass sun shade consisting of MS box 16 SWG 1"x1" frmae
with fiber glass 3 ply on top with 3 coats of paint. Complete in all respects as approved
and directed by the Engineer Incharge.
Total 10189.22
Contractor' 20.00 Percent 2037.84
Total 12227.06
LABOUR
Total 687.50
Sundries 10.00 Percent 68.75
Total 756.25
Contractor' 20.00 Percent 151.25
Total 907.50
3 cost of welding 500.00
4 cost of painting 300.00
ITEM RATE
2 Providing / Installation of PVC strainer of BSS class B in tube well bore hole 10"
dia
60 Rft
Total 60 Rft
1639.35 P.Rft Rs. 98361/-
3 Providing / Installation of PVC blind pipe of BSS class B in tube well bore hole 10"
dia
40 Rft
Total 40 Rft
2627.45 P.Rft Rs. 105098/-
5 Shoruding with pea gravel 3/8" to 1/8" in tube well bore hole
2x3.145x0.52x0.42x80 110 Cft
Total 110 Cft 169.15 P.Cft Rs. 18607/-
6 Testing and developing of tubewell of size 6" and above continuously upto 1.5 cs
discharge.
6 Hrs
Total 6 Hrs 2730.50 P Hr Rs. 16383/-
Total 325775
Say 325800
1 x1 x30 = 30 Rft
= 30 Rft @ 2570.45/Rft Rs.77114/-
1
P/F Centrifugal pump 2 ½”x2” size KSB made coupled
with 10 BHP AC electric motor 3 Phase 2900 rpm
Siemen made with head of 100’ i/c all types of fittings
electric connection, internal wiring, cement concrete
foundation with nuts and bolts Ampere meter, Volt meter,
indicator lights i/c electric control panel board, KSB
warranted as approved and directed by the Engineer In
charge.
2 Set
Total 2 Set 1520000.00 P.Set 3040000
Total 3040000
Say 3040000
1 x1 = 1 Set
Tot= 1 Set @ 6105000.00/Sft Rs.6105000/-
Total 6105000
Add 3% contigency charges 183150
Total 6288150
Say 6288000
MATERIAL
= 1 No
@ 5500000.00 P Set 5500000
Total = 5500000
G. Total = 6105000