Professional Documents
Culture Documents
BILL OF QUANTITIES
APPROVED:
DIRECT COST
ADJUSTED UNIT COST
UNIT COST
1,179.76 1,511.28
18,680.10 17,190.52
746.05 955.70
770.09 986.48
924.27 1,184.00
189,000.00 238,140.00
28,900.00 1,285.45
73,640.00 94,332.84
30,860.00 39,531.66
33,981.00 43,529.66
331,320.00 424,420.92
13,929.50 14.77
4,530.05 4,756.55
Page 1 of 1
RECOMMENDING APPROVAL:
RICHARD P. PABLO
OIC - Director, Physical Plant & Site Development
Republic of the Philippines
QUIRINO STATE UNIVERSITY
Diffun, Quirino
21-Feb-22
EQUIPMENT
DESCRIPTION OF WORKS TO BE DONE % OF TOTAL
DESCRIPTION REQUIRED
A. Building 98.96%
B. Miscellaneous 1.04%
100.00%
A. Building P 1,850,591.41
B. Miscellaneous P 19,382.53
Total P 1,869,973.94
BREAKDOWN OF EXPENDITURE :
APPROVED:
-
QSU-PPFM-F005
Rev. 00 (Feb. 11, 2019)
UDGET FOR THE CONTRACT
APPROVED:
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
-
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials:
Gravel fill 1.50 cu.m. 600.00 900.00
Earth fill 2.50 cu.m. 350.00 875.00
SUMMARY:
A Equipment P -
B Labor 23,000.00
C Materials 1,775.00
D TOTAL DIRECT COST 24,775.00
DIRECT UNIT COST 1,179.76
E OCM 12% of D 2,973.00
F Profit 10% of D 2,477.50
G VAT 5% of (D+E+F) 1,511.28
H Total Cost (D+E+F+G) 31,736.78
I Unit Cost H/Quantity P 1,511.28
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
One bager mixer 1.00 10.00 850.00 8,500.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
Portland Cement 9 104.00 bags 260.00 27,040.00
Fine Aggregates-S1 0.5 6.00 cu.m. 600.00 3,600.00
Coarse Aggregates-G1 1 12.00 cu.m. 600.00 7,200.00
16mm x 6m RSB 246.22 kls. 50.00 12,311.00
12mm x 6m RSB 58.63 kls. 50.00 2,931.50
10mm x 6m RSB 270.10 kls. 50.00 13,505.00
# 16 Tie Wire 10.00 kls. 1,875.00 18,750.00
30pcs-2" x 2" x 12' scaffoldings/Formlumber 120.00 bd.ft. 50.00 6,000.00
30pcs-2" x 3" x 12' scaffoldings/Formlumber 180.00 bd.ft. 50.00 9,000.00
1/2 Ordinary Plywood 6.00 pcs. 780.00 4,680.00
Assorted C.W.N 7.00 kls. 75.00 525.00
Cutting disc big 5.00 pcs. 250.00 1,250.00
Construction pail 5.00 pcs. 75.00 375.00
C. SUB-TOTAL, MATERIAL P 107,167.50
SUMMARY:
A Equipment P 8,500.00
B Labor 40,000.00
C Materials 107,167.50
D TOTAL DIRECT COST 155,667.50
DIRECT UNIT COST 13,419.61
E OCM 12% of D 18,680.10
F Profit 10% of D 15,566.75
G VAT 5% of (D+E+F) 9,495.72
H Total Cost (D+E+F+G) 199,410.07
I Unit Cost H/Quantity P 17,190.52
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
-
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 5.00 550.00 2,750.00
Mason 2.00 5.00 450.00 4,500.00
Laborer 3.00 5.00 350.00 5,250.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
4" CHB 12.5 963.00 pcs. 12.00 11,556.00
Portland cement 0.759 58.47 bags 260.00 15,203.07
fine aggregates 0.084 6.47 cu.m. 600.00 3,882.00
10mm x 6.0 def bars 114.70 kls 50.00 5,735.00
# 16 tie wire 2.00 kls 75.00 150.00
Cutting Disc big 1.00 pcs. 250.00 250.00
Plastering @ .020 thicknes (2 faces) Cement 28.00 bags 250.00 7,000.00
Fine aggregates 2.00 cu.m. 600.00 1,200.00
C. SUB-TOTAL, MATERIAL P 44,976.07
SUMMARY:
A Equipment P -
B Labor 12,500.00
C Materials 44,976.07
D TOTAL DIRECT COST 57,476.07
DIRECT UNIT COST 746.05
E OCM 12% of D 6,897.13
F Profit 10% of D 5,747.61
G VAT 5% of (D+E+F) 3,506.04
H Total Cost (D+E+F+G) 73,626.85
I Unit Cost H/Quantity P 955.70
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
welding machine 1.00 22.00 500.00
500.00 11,000.00
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
labor
Construction Foreman 1 28.00 P 550.00 15,400.00
welder 2 28.00 450.00 25,200.00
Laborer 6 28.00 350.00 58,800.00
-
B. SUB-TOTAL, LABOR P 99,400.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
SUMMARY:
A Equipment P 11,000.00
B Labor 99,400.00
C Materials 282,344.70
D TOTAL DIRECT COST 392,744.70
DIRECT UNIT COST 770.09
E OCM 12% of D 47,129.36
F Profit 10% of D 39,274.47
G VAT 5% of (D+E+F) 23,957.43
H Total Cost (D+E+F+G) 503,105.96
I Unit Cost H/Quantity P 986.48
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
-
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
labor
Construction Foreman 1.00 14.00 550.00 7,700.00
Carpenter/Mason 2.00 14.00 450.00 12,600.00
Laborer 3.00 14.00 350.00 14,700.00
12mm thk Laminated White board (4" x 8") 38.00 pcs. 1,450.00 55,100.00
SUMMARY:
A Equipment P -
B Labor 35,000.00
C Materials 94,380.00
D TOTAL DIRECT COST 129,380.00
DIRECT UNIT COST 924.27
E OCM 12% of D 15,525.60
F Profit 10% of D 12,938.00
G VAT 5% of (D+E+F) 7,892.18
H Total Cost (D+E+F+G) 165,735.78
I Unit Cost H/Quantity P 1,184.00
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
-
-
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
-
- -
- -
B. SUB-TOTAL, LABOR P -
C. Name and Description Unit Qty Unit Cost Total Cost (Pesos)
Materials
D2-1.8m x 2.6m,1/2" thick glass, Two swing type double
action door full hiegth with fix glass with aluminun powder
caoted framing, with fix window ( see detail on
drawing,schedule of doors)
set 1 15,000.00 15,000.00
SUMMARY:
A Equipment P -
B Labor -
C Materials 189,000.00
D TOTAL DIRECT COST 189,000.00
DIRECT UNIT COST 189,000.00
E OCM 12% 22,680.00
F Profit 10% 15,120.00
G VAT 5% of D 11,340.00
H Total Cost of D 238,140.00
I Unit Cost of (D+E+F) P 238,140.00
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
SUMMARY:
A Equipment P -
B Labor 8,500.00
C Materials 20,400.00
D TOTAL DIRECT COST 28,900.00
DIRECT UNIT COST 28,900.00
E OCM 12% of D 3,468.00
F Profit 10% of D 2,890.00
G VAT 5% of (D+E+F) 1,762.90
H Total Cost (D+E+F+G) 37,020.90
I Unit Cost H/Quantity P 1,285.45
DETAILED UNIT PRICE ANALYSIS
IMPROVEMENT OF CROP PROCESSING LABORATORY
Location: QSU Diffun Campus, Diffun Quirino
Item No. : VIII Quantity = 361.57
Description : Painting works Unit = sq.m.
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 8.00 550.00 4,400.00
Painter 2.00 8.00 450.00 7,200.00
Laborer 3.00 8.00 350.00 8,400.00
B. SUB-TOTAL, LABOR P 20,000.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
Concrete Wall: Interior 122.3sq.m. -
Skimcoat (Acrylic Skimcoat) 48.00 pail/s 280.00 13,440.00
Primer (Flat latex permacoat) 18.00 pail/s 175.00 3,150.00
Masonry Putty 18.00 pail/s 175.00 3,150.00
Topcoat Permacoat latex (shamrock green) 35.00 pail/s 185.00 6,475.00
Exterior: 142.31sq.m. -
Skimcoat (Acrylic Skimcoat) 18.00 liters 280.00 5,040.00
Primer (Flat latex permacoat) 18.00 liters 175.00 3,150.00
Putty (spot) Acryttex cast #1701 18.00 liters 175.00 3,150.00
Thinning Solvent for Putty (Acrytex Reducer
#1750) 2.00 liters 175.00 350.00
SUMMARY:
A Equipment P -
B Labor 20,000.00
C Materials 53,640.00
D TOTAL DIRECT COST 73,640.00
DIRECT UNIT COST 73,640.00
E OCM 12% of D 8,836.80
F Profit 10% of D 7,364.00
G VAT 5% of (D+E+F) 4,492.04
H Total Cost (D+E+F+G) 94,332.84
I Unit Cost H/Quantity P 94,332.84
DETAILED UNIT PRICE ANALYSIS
IMPROVEMENT OF CROP PROCESSING LABORATORY
Location: QSU Diffun Campus, Diffun Quirino
Item No. : IX Quantity = 1.00
Description : Plumbing Works (Sanitary and Downspout) Unit = l.s.
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 5.00 550.00 2,750.00
Plumbers 1.00 5.00 450.00 2,250.00
Laborers 2.00 5.00 350.00 3,500.00
C. Name and Description Unit Qty Unit Cost Total Cost (Pesos)
Materials
Downspout ### -
100mmØ x 3.00 m. PVC orange pc/s. 12.00 485.00### 5,820.00
100mmØ Elbow, 90 Degree PVC orange pc/s. 33.00 130.00### 4,290.00
100MMØ Dome Type Strainer, PVC pc/s. 11.00 250.00### 2,750.00
Flat Bar Metal Clamp 50mm x 1.2m, pc/s. 22.00 50.00### 1,100.00
4mmØ Metal Screw with Tox Screw pc/s. 44.00 5.00### 220.00
Masonry Drill Bit pc/s. 4.00 120.00### 480.00
Steel Drill Bit pc/s. 4.00 150.00### 600.00
Solvent Cement ltr/s. 2.00 460.00 920.00
Hacsaw Blade pc/s. 2.00 75.00 150.00
Sanitary ### -
50mmØ Upvc Wye orange pc/s. 4.00 130.00### 520.00
50mmØ x 45 degree Elbow pc/s. 2.00 45.00### 90.00
50mmØ x 90degree Elbow pc/s. 5.00 45.00### 225.00
50mmØ P-Trap pc/s. 3.00 60.00### 180.00
50mmØ x 50mmØ Tee pc/s. 2.00 45.00### 90.00
50mmØ Clean-out pc/s. 2.00 80.00### 160.00
50mmØ x 3.00m PVC pc/s. 10.00 270.00### 2,700.00
Solvent Cement ltr/s. 4.00 460.00### 1,840.00
Hacksaw Blade pc/s. 3.00 75.00### 225.00
-
C. SUB-TOTAL, MATERIAL P 22,360.00
SUMMARY:
A Equipment P -
B Labor 8,500.00
C Materials 22,360.00
D TOTAL DIRECT COST 30,860.00
DIRECT UNIT COST 30,860.00
E OCM 12% of D 3,703.20
F Profit 10% of D 3,086.00
G VAT 5% of (D+E+F) 1,882.46
H Total Cost (D+E+F+G) 39,531.66
I Unit Cost H/Quantity P 39,531.66
DETAILED UNIT PRICE ANALYSIS
IMPROVEMENT OF CROP PROCESSING LABORATORY
Location: QSU Diffun Campus, Diffun Quirino
Item No. : X Quantity = 1.00
Description : Cold Water Supply Unit = l.s.
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 4.00 550.00 2,200.00
Plumber 1.00 4.00 450.00 1,800.00
Laborer 1.00 4.00 350.00 1,400.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
25mmØ coupling connector pc/s. 15.00 29.00### 435.00
25mmØ PPR Elbow 90° pc/s. 6.00 29.00### 174.00
32mmØ x 25mmØ Reducer pc/s. 1.00 55.00### 55.00
25mmØ x Tee pc/s. 7.00 33.00### 231.00
25mmØ Gate Valve pc/s. 1.00 766.00### 766.00
25mmØ PPR Elbow 90°, feamale pc/s. 6.00 30.00### 180.00
25mmØ x 4.00m PPR Pipe pc/s. 12.00 720.00### 8,640.00
Faucet (heavy duty) pc/s. 6.00 350.00### 2,100.00
32mmØ Fusion Device pc/s. 1.00 2,500.00### 2,500.00
kitchen sink stainless pc/s. 3.00 3,500.00### 10,500.00
Other Plumbing Accessories l.s 1.00 3,000.00### 3,000.00
P 28,581.00
SUMMARY:
A Equipment P
B Labor 5,400.00
C Materials 28,581.00
D TOTAL DIRECT COST 33,981.00
DIRECT UNIT COST 33,981.00
E OCM 12% of D 4,077.72
F Profit 10% of D 3,398.10
G VAT 5% of (D+E+F) 2,072.84
H Total Cost (D+E+F+G) 43,529.66
I Unit Cost H/Quantity P 43,529.66
DETAILED UNIT PRICE ANALYSIS
IMPROVEMENT OF CROP PROCESSING LABORATORY
Location: QSU Diffun Campus, Diffun Quirino
Item No. : XI Quantity = 1.00
Description : Electrical Works Unit = l.s.
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
Equipment
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
Labor
Construction Foreman 1.00 14.00 550.00 7,700.00
Electrician 3.00 14.00 450.00 18,900.00
Laborer 6.00 14.00 350.00 29,400.00
-
B. SUB-TOTAL, LABOR P 56,000.00
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
Fabricated enclosure flush mounted Firefly
nema 1 G#16 powder coated galvanized
panel board 24 branches + main koten
bolt on type with busbar size 1/4" x
3/4"; MAIN: 150 amphere trip 2pole 1 set 25,000.00 25,000.00
koten; Branches 24pcs 20AT 2pole CB
koten, with grounding busbar
electrical PVC pipe orange 20mm dia. 100 pcs 100.00 10,000.00
Electrica; long elbow orange 20mm 30 pcs 40.00 1,200.00
Electrical PVC pipe orange 50mm dia. 2 pcs 250.00 500.00
Electrical PVC long elbow orange 5mm 1 pc 80.00 80.00
Electrical tape big 10 pcs 50.00 500.00
Rubber tape 1 pc 120.00 120.00
Entrance Cap 50mm 1 pc 250.00 250.00
Male adopter 50mm 1 pc 100.00 100.00
Service drop wire #10 duplex twisted
ACSR 150 meters 140.00 21,000.00
Cut out assembly w/ long cut out and lighting arrester 1 set 7,000.00 7,000.00
SUMMARY:
A Equipment P -
B Labor 56,000.00
C Materials 275,320.00
D TOTAL DIRECT COST 331,320.00
DIRECT UNIT COST 331,320.00
E OCM 12% of D 39,758.40
F Profit 10% of D 33,132.00
G VAT 5% of (D+E+F) 20,210.52
H Total Cost (D+E+F+G) 424,420.92
I Unit Cost H/Quantity P 424,420.92
DETAILED UNIT PRICE ANALYSIS
IMPROVEMENT OF CROP PROCESSING LABORATORY
Location: QSU Diffun Campus, Diffun Quirino
A Name and Capacity of Equipment (Operated) No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
B. SUB-TOTAL, LABOR P -
C. Name and Description Qty Unit Unit Cost Total Cost (Pesos)
Materials
Safety Shoes 990.00 m-d 8.05 7,969.50
Safety Gloves 990.00 m-d 1.10 1,089.00
Safety Helmet 990.00 m-d 2.90 2,871.00
Medicine Kit 1.00 l.s 2,000.00 2,000.00
SUMMARY:
A Equipment P -
B Labor -
C Materials 13,929.50
D TOTAL DIRECT COST 13,929.50
DIRECT UNIT COST 13,929.50
E OCM 12% of D
F Profit 8% of D
G VAT 5% of (D+E+F) 696.48
H Total Cost (D+E+F+G) 14,625.98
I Unit Cost H/Quantity P 14.77
DETAILED UNIT PRICE ANALYSIS
A Name and Capacity of Equipment (Operated) Factor No. of Units No. of Days Unit Rate/Day Total Cost (Pesos)
A. SUB-TOTAL , EQUIPMENT P -
B Designation of Personnel No. of Men No. of Days Unit Rate/Day Total Cost (Pesos)
B. SUB-TOTAL, LABOR P -
C. Name and Description Factor Qty Unit Unit Cost Total Cost (Pesos)
Ink l.s. P P 3,000.00
Photo Paper l.s. 960.00
Tarpaulin- 4'x 8' 32.00 sq.ft. 17.8141 570.05
SUMMARY:
A Equipment P -
B Labor -
C Materials 4,530.05
D TOTAL DIRECT COST 4,530.05
DIRECT UNIT COST 4,530.05
E OCM 12% of D
F Profit 8% of D
G VAT 5% of (D+E+F) 226.50
H Total Cost (D+E+F+G) 4,756.55
I Unit Cost H/Quantity P 4,756.55